-
CENTRES
Progammes & Centres
Location
Energy Security in Villages through Biomass (part – II)
DR ARUN K TRIPATHI AND G R SINGH
Director, Ministry of New and Renewable Energy,
Continued from Volume V, Issue No. 23…
B |
ased on the total energy requirements and the local resource availability, the energy production systems are configured. For an energy production system based on biomass, an appropriate technology mix can be selected from available biomass conversion technologies such as:-
· Single / Biphasic biogas production using tree based organic substrates, vegetable wastes / residues, vegetable wastes / kitchen wastes, animal dung etc.
· Biomass Gasifier coupled with 100% producer gas engines for electricity generation
· Stationary diesel engines run on straight vegetable oils or bio-diesel.
· The energy efficient Improved Chulha for each household
· Raising the plantations for obtaining wood, vegetable oil and other raw materials
Depending upon specific requirements, inclusion of solar photovoltaic devices such as solar lanterns or an appropriate battery backup arrangement could be considered in the system configuration.
Electricity distribution preferably to be carried out through a local mini grid. Emphasis should be on energy to be provided for productive activities with thrust on micro enterprise development, backed by micro credit facilities, with a view to facilitating job creation, income generation, increasing the purchasing capacity and reducing the migration from villages. The Guidelines for preparation of the Village Energy Plan are given in
Formation of a Village Energy Committee
Full participation of the village community is to be secured from inception. The constitution of a Village Energy Committee (VEC) should be through the Gram Sabha and got duly notified by the Gram Panchayat as a Sub-Committee or Standing Committee of the Gram Panchayat as per the relevant provisions of the State Panchayati Raj Act and rules in this regard.
Care should be taken that the elected Panchayat member/s from that village are ex-officio members of the VEC.
Box 2 PREPARATION OF VILLAGE ENERGY PLAN
Demand – Current and potential, special emphasis on loads related to income generation. Estimate of time taken to ramp up to full projected demand
Load management – Load chart preparation taking into account seasonal variations in use of electricity, especially for irrigation
Plant sizing – Sizing of the plant, capacity utilization factor for the plant as per the load chart
Technological options – SVO or gasifier or biogas, taking into account load pattern, capacity utilization factor and type of biomass fuel available
Sources of biomass – Current and potential, its stability
Financing plan – Capital expenditure for power plant and other investments needed to reach projected demand. Sourcing working capital, sources of revenue, tariff setting, other non-tariff sources of revenue, operational sustainability, cash flow statement, plan to meet revenue gap if any, pay back period
Human resources – Community empowerment, involving them in ownership and decision-making, training in operation and management of the power plant
MIS – How information would be captured with respect to key elements and how it would be used by the management (Village Energy Committee) should be spelt out.
Risk management – Identification of risk and how it would be managed
Project implementation plan – Tasks and milestones with timelines and clear identification of responsibilities should be presented
In preparing and finalizing the VEP, Participatory Rural Appraisal (PRA) techniques should be used. This would among other things help:
Introduce the VESP project, its structure, guidelines, etc. to the community.
The community in making a choice of which energy needs is more important to them.
Creation of a Village Energy Fund
A Village Energy Fund should be got created under the provisions of State Panchayati Raj Act, initially with beneficiary contributions for sustained operation and management of the project. Subsequent monthly / annual user charges should be deposited in this account.
Grants from other Government Programmes such as rural development, forestry, tribal development, etc., if available, should be placed in this account, to be utilized towards operation and management of the project. The fund should be managed by the Village Energy Committee with two signatories nominated by the Committee. One of the signatories would be the Gram Panchayat member who is the ex-officio member on the Committee.
A separate capital account should also be got created, for receipts towards supply and installation of the energy production units. This Capital Account would also be operated by the VEC in accordance with the same procedure of joint signature and maintenance of accounts, which govern the Village Energy Fund.
Both the VEF and the Capital Account of the VEC, being the accounts of the Gram Panchayat under the provisions of the law, would be subject to the processes of accounts maintenance and audit that apply to the Gram Panchayat. Expenditure of funds by the VEC should be disclosed to the Gram Panchayat at its monthly meeting as prescribed under the Panchayati Raj Act and Rules.
VEC, being a Sub-Committee of a Standing Committee of the Gram Panchayat would also be under obligation to disclose information in accordance with the Right to Information legislation. It will also be authorized to submit the Utilization Certificate to the Gram Panchayat, which in turn will submit the Utilization Certificate to the agency concerned at the district level. Technical facilitation and capacity building through implementing Agencies or Consultants such as NGOs would be focused at the VEC level through the Gram Panchayat.
Implementation of the test projects
The test projects are undertaken by the Panchayats/VECs duly facilitated by Implementing
Agencies such as DRDAs, forest departments, NGOs, entrepreneurs, franchises, other corporate entities, cooperatives and State Nodal Agencies. An implementing agency can forward the proposals for the test projects to the Ministry through the State Nodal Agency.
The Detailed Project Report should, inter-alia, include the following information: -
(i) Census code number of the village
(ii) Village Energy Plan
(iii) Confirmation about setting up of Village Energy Committee and creation of Village Energy Fund
(iv) Plan for training
(v) Implementation modalities
(vi) O&M arrangements
(vii) Commitment about balance 10% capital cost and funds for operation and management
The projects are owned by the village community with the responsibility for overall operation / management. However, the implementation agency helps them for about two years in this activity for which one-time Central assistance is provided. During this period, the implementing agency needs to train local youth in the operation and management of the project.
After this period, the responsibility of operation / management should be undertaken by the Village Energy Committee. The Village Energy Committee may hire / lease out these services to an entrepreneur as a preferred option. The concerned State Nodal Agency closely monitors the implementation of the projects and provide monthly progress reports to the Ministry until commissioning.
Project Costs
Different packages based on the no. of households (50-250) in the village have been prepared. For bigger villages upto 400 households, projects could be considered based on similar cost benchmarks.
However, in specific cases the applicability of a package may not be dependent only on no. of households but will have to be considered on merit taking into account the resource availability, technology configuration, load profile, layout of the village etc. The cost of project depends upon the packages based on different technology configurations for electricity generation systems, biogas plants, improved chulhas, plantations etc.
to be continued…
Courtesy: Akshay Urja, Volume 2, Issue 1 (Jul-Aug 2008)
The Nuclear Illusion (part – IV)
AMORY B. LOVINS AND IMRAN SHEIKH
Continued from Volume V, Issue No. 23…
T |
he construction challenges driving cost escalation are most formidable in the
A
Yet in the five years through April 2008, the U.S. dollar declined by 27% against the Euro and by 12% against the yen. Had the dollar held its value as well as the Euro, the price of oil would have been under $70/bbl rather than $119/bbl.47 The cost of reactor components imported by the United States—but not by French/German builders in Finland—reflects the weak dollar.
Nuclear workers are becoming scarce too. Forty percent of those at
Since 1980, U.S. nuclear engineering university programs have declined from 65 to ~29 and have trouble attracting talented students; the Nuclear Energy Institute says the U.S. now has 1,900 undergraduates and 1,100 graduate students in nuclear engineering programs, but this remains far smaller than needs to offset retirements and staff proposed growth.
In 2002, the UK had no undergraduate course in nuclear engineering.48 The number of German academic institutions with nuclear courses is expected to drop from 22 in 2000 to 10 in 2005 to 5 in 2010; 46 nuclear diplomas were granted in 1993, zero in 1998, and only two in the five years ended in 2002.49 As experienced nuclear experts retire, safely running old plants will be hard enough without staffing new ones.
What the World Nuclear Industry Status Report 2007 calls “rapid loss of [construction and operating] competence and lack of manufacturing infrastructure” isn’t the only big obstacle:
The nuclear industry and utilities face challenges in a radically changed industrial environment. Today the sector has to deal with waste management and decommissioning expenses that far outweigh estimates of the past, it has to compete with a largely modernized gas and coal sector and with new competitors in the new and renewable energy sector.
Further, many countries now expose builders to the risks of free-market competition—both with micropower and with efficient use of electricity—rather than shielding investors via traditional utility rate-basing. For example, as soon as big
Enthusiasm is no guarantee of market success: high-flying U.S. merchant (non-utility) builders of combined-cycle gas-fired plants recently wrote off about $100 billion worth of plants they’d built for which there was no demand.50 And in the restructured markets now operating in nearly half the U.S. states and for more than half its electricity, developers must build power plants at their own risk or at the risk of a long-term power-purchasing entity. This exposure to competition raises financial risk and hence the cost of capital. This makes it “un-likely that we will see much if any investment in nuclear capacity” in those states.51
Nuclear plants worldwide enjoy unique legal exemption from liability for catastrophic accidents.52 The United States even offers its next half-dozen nuclear plants new federal insurance against regulatory delays,53 even though meaningful public participation in licensing has already been virtually eliminated.
Yet governments cannot so easily quash uncertainties about what nuclear plants will cost and whether, once built, they can remain competitive for decades. These uncertainties deter equity investors and drive developers to high debt ratios that weaken credit ratings.
Nuclear Engineering International54 concludes that this means “there aren’t many company boards that would give the go-ahead to a new nuclear plant.” So far, no
A further issue arises in states that still rate-base new power plants: financial comparisons between power plants typically use levelized costs, but utility customers would feel sticker shock. A total construction cost ~$5,200/kW, near the low end of Moody’s October 2007 estimate, implies a levelized busbar cost of ~16¢/kWh. But this would require a typical regulated utility in 2013 to collect first-year project revenue of ~27¢/kWh—three times typical tariffs55—plus delivery cost to customers. At that rate, even photovoltaics could look like a bargain.
A “death spiral” of rising price and falling demand may ensue because customers now have more choices than just buying ever more grid electricity: they can vote with their feet by buying less electricity, more efficiency, and more onsite generation—all now becoming widely available.
What are new nuclear plants’ competitors?
The MIT study compared new nuclear power only with other central thermal plants, while the Keystone study made no comparison. All nuclear advocates and most nuclear analysts, including those in the capital markets, assume that the only game in town is coal- or gas-fired central power stations. These have well-known attributes.
Coal is abundant but becoming costlier— in 2007 and early 2008, world spot prices tripled and a key
Coal plants emit more conventional air pollution and are less efficient than modern gas plants. Burning coal contributes greatly, gas 2-4×less, to climate change.
It’s becoming much harder both economically and politically to build new coal plants, especially in the United States,57 where three leading investment banks no longer finance them without proof that they’ll compete even under “potentially stringent” carbon pricing, and will favor energy efficiency and renewables instead.58
Only a third of announced new
However, focusing on these three kinds of central plants is obsolete. In today’s market they’re all the wrong competitors, because two other diverse classes of electrical resources are walloping all central plants in the global marketplace. These new competitors are negawatts— electricity saved by more efficient or more thoughtfully timed end-use by customers60—and micropower— the Economist magazine’s generic term for two diverse classes of less centralized resources.
Micropower comprises two classes of technologies:
1. onsite generation of electricity (at the customer, not at a remote utility plant)—usually cogeneration of electricity plus recovered waste heat (outside the
2. distributed renewables—all renewable power sources except big hydro plants, which are defined here as dams larger than 10 megawatts (MW).
The nuclear industry professes to support both these options, but denies they can offer serious alternatives to nuclear power because they’re too costly, too unreliable, too small individually, too slow to build, and too small in total ultimate potential. Let’s examine these claims in turn.
Notes:
43 “Supply chain could slow the path to construction, officials say,” Nucleonics Week, 15 Feb 2007.
44 R. Smith, “Utilities Fret as Reactor-Part Suppliers Shrink,” Wall St. J., p. B1, 11 Apr 2008. She quotes the Chair-man of the U.S. Nuclear Regulatory Commission: “The global supply chain is stretched, if not to the breaking point, at least to the tipping point.”
45 “Subcontractor inexperience delayed Olkiluoto-3 projects, officials say,” Nucleonics Week, 14 June 2007.
46 Smith, ref 44.
47 Wall St. J. editorial, “The Fed’s Bender,” p. A18, 28 Apr 2008.
48 For further
49 These human-resources data are from ref. 4.
50 They were misled by two disinformation campaigns. The first, by the Western Fuels Association and its surrogates like the Greening Earth Society, claimed that the Internet uses an order of magnitude more electricity than it does and will soon account for half of total demand (see Epilogue, pp. 213–219, in J.G. Koomey, Turning Numbers Into Knowledge, 2nd edn., 2008, Analytics Press, Oakland, www.analyticspress.com). The second campaign alleged that the lights went off in
51 P. Joskow, “The Future of Nuclear Power in the United States: Economic and Regulatory Challenges,” AEI-Brookings Joint Center for Regulatory Studies, Wkg. Paper 06-25, Dec 2006, http://econ-www.mit.edu/files/1192. The main exception is the NRG merchant nuclear project proposed in South Texas based on estimated costs roughly half those found by other utilities in 2008.
52 This subsidy, via laws like the U.S. Price-Anderson Act, must be valuable because the industry perennially says that despite its safe operations, it cannot operate without such a liability shield. Tellingly, Koplow has shown that single nuclear operator firms buy property insurance for their nuclear plant and business that exceed by an order of magnitude the outdated coverage for their offsite liability, and that their self-coverage exceeds the entire national nuclear industry’s liability caps (ref. 186).
53 The
54 Ref. Error! Bookmark not defined.
55 J. Harding calculation at a 4%/y real discount rate: personal communication, 15 Jan 2008.
56 S. Oster and A. Davis, “
57 In 2007, for example, TXU’s plans for 11 coal-fired plants in
58 J. Ball, “Wall Street Shows Skepticism Over Coal,” Wall St. J., p. A6, 4 Feb 2008. The common assumption that “Carbon Caps May Give Nuclear Power a Lift” (R. Smith, Wall St. J., p. A4, 19 May 2008, www.climateark.org/shared/reader/welcome.aspx?linkid=99837) simply assumes that efficiency and renewables won’t be serious competitors, though it does highlight the huge market distortions that could arise if carbon emissions allowances were given to nuclear utilities and not to their nonutility competitors. The Congressional Budget Office’s May 2008 report “Nuclear Power’s Role in Generating Electricity” concludes that nuclear may undercut coal power with a $45/t carbon tax (www.cbo.gov/ftpdocs/91xx/doc9133/05-02-Nuclear.pdf), but contrary to Smith’s summary (id.), compares nuclear only with coal and central gas plants, not with “any other form of power generation.”
59 E. Schuster, “Tracking New Coal-Fired Power Plants,” NETL, 10 Oct 2007, www.netl.doe.gov/coal/refshelf/ncp.pdf.
60 Scores of utilities have demonstrated, and implemented at scale, rapid, large, predictable, extremely cheap negawatts.
to be continued…
Courtesy: Rocky Mountain Institute (Ambio Nov 08 preprint, dr 18, 27 May 2008, DRAFT subject to further peer review/editing)
NEWS BRIEF
NATIONAL
OIL & GAS
Upstream
OVL may sign pact with
December 2, 2008. ONGC Videsh Ltd, is likely to sign agreement in next couple of months for an oil block in
The company will hold 100 per cent interest in the block and will invest $250 mn in initial exploration phase. The contract will be similar to the one China National Petroleum Corp (CNPC) signed last month for developing Al-Ahdad oilfield in central
It would act as the operator of the field until it recoups all its costs and set up a joint operating company with the local operator to take over once development costs have been repaid.
Oil product sales fall as economy slows
December 1, 2008. Domestic oil product sales declined in October for the first time in 17 months as slowing economic activity crimped demand for industrial fuels and diesel. Oil product sales, a proxy for demand, fell 1.7 per cent from the same month a year ago to 10.71 mt as diesel consumption slowed to its lowest level since June, when
The fall in
India's crude imports during the month were up 13.2 per cent to 11.365 mt, or nearly 2.7 million bpd, on higher purchases by private refiners. Reliance Industries, which is ready to commission its 580,000 bpd refinery in western
SpiceGas aims 700 gas stations
November 30, 2008. Delhi-based SpiceGas plans to invest Rs 400 crore ($80.69 mn) over the next seven years to set up about 700 gas stations in the country. The fund will be made available through internal accrual and some outside investors. The company is targeting a revenue of Rs 1,694 crore ($341.73 mn) annually by March 2013 and Rs 3,066 crore ($618.51 mn) annually by March 2018.
It will set up about 40 stations in the first year in the states of Gujarat,
Oil companies to earn more profits
November 30, 2008. Oil marketing companies will earn more profits, Rs 14.89/litre on petrol and Rs 3.03 per litre on diesel, since December 1 due to falling oil prices in international markets. This is Rs 6.74 per litre more on diesel and Rs 2.38 per litre more on petrol than what they earned last month. But there will be no immediate change in consumer prices of the two fuels.
Had oil marketing companies passed on the benefit of the sharp fall in global oil prices to consumers, petrol would have cost them Rs 35.73 a litre, price last seen in June 2004. Similarly, diesel would have cost Rs 31.83 a litre, prevalent in February. But retail prices of controlled items such as petrol and diesel in
Prices of four ‘sensitive’ petroleum products (petrol, diesel, kerosene sold at ration shops and cooking gas) are controlled by the government while prices of other petroleum products are market determined. In June, when the average price of crude oil import touched $122/barrel, the government increased petrol prices by Rs 5 a litre, diesel by Rs 3 a litre and cooking gas by Rs 50 per cylinder. There was no final decision on the price revision as yet but cooking gas prices could be reduced only marginally as public sector oil companies are still losing Rs 143 on every cylinder.
The government is under pressure from the opposition parties to cut petrol and diesel prices but it is restrained by the election codes. The model code of conduct for election prohibits the government to announce or promise any financial grant that may influence voting behaviour. The model code of conduct is effective till December 24.
Mittal puts on hold investment in Vizag refinery-cum-petrochem
November 27, 2008. Having lost 17 bn pounds in the global financial meltdown, India-born billionaire Lakshmi Mittal has put on hold his investments in USD 10 bn refinery-cum-petrochemical project planned at Vizag. Mittal is, however, going ahead with investing in Hindustan Petroleum Corp Ltd's Rs 18,919-crore ($3.87 bn), 9 mtpa Bhatinda refinery in
The five-way alliance of HPCL, Mittal, French energy giant Total, gas utility GAIL and Oil India Ltd was currently doing pre-feasibility study for the project and the partners are scheduled to take an investment decision in March 2009. While the export-oriented refinery will be of the order of 14-15 mtpa, the petrochemical plant would be of at least one million tons capacity.
Saudi Aramco could join a planned Rs 500 bn ($10 bn) oil refinery in Andhra Pradesh. Saudi Aramco could be offered as much as 15% stake in the refinery being planned by Hindustan Petroleum Corp. Ltd. (HPCL), GAIL India Ltd., Oil India Ltd., Total SA and Lakshmi Mittal.
Transportation / Trade
Oil PSUs cut jet fuel prices again
December 1, 2008. This was the sixth cut in jet fuel prices since August when rates rose to an all-time high of Rs 71,028.26 per kilolitre. Public sector oil marketing companies, IOC, HPCL and BPCL have slashed the price of Aviation Turbine Fuel (ATF) for the sixth time in three months, in line with falling crude oil prices.
In
Policy / Performance
‘
December 2, 2008. According to Oil Secretary R.S. Pandey,
Oil has fallen nearly $100 from a record high of $147.27 hit in mid-July as worries about the economic slowdown in the
Oil companies allowed to sell bonds to RBI
December 2, 2008. IndianOil, Hindustan Petroleum Corporation and Bharat Petroleum Corporation have been allowed to sell their oil bonds to the Reserve Bank of
They can then buy their forex from the market with these rupees and fund their monthly crude and product bills. This move will ensure that not too much forex moves out of the banking system. It could also be intended to prevent high volatility in the rupee. On an average, the three oil majors buy crude worth $3 bn a month (Rs 15,000 crore) of which IOC accounts for over half of this amount with HPCL and BPCL taking up the balance.
The Government had, last month, issued Rs 22,000 crore ($4.39 bn) oil bonds to the three companies which were intended to partially compensate them for losses incurred on sale of petrol, diesel, cooking gas and kerosene at subsidised prices. Of this, IOC got Rs 11,975.51 crore ($2.39 bn) followed by HPCL and BPCL with Rs 5,330.76 crore ($1.06 bn) and Rs 4,693.73 crore ($937.43 mn) each. These bonds were only part of the Rs 65,000-crore ($12.98 bn) package earmarked between January and September. The balance Rs 43,000 crore ($8.58 bn) is expected in two tranches by the end of February.
The Government has already hinted that no more oil bonds will be issued for the rest of the year because the losses on sale of fuels have since fallen considerably. In fact, the oil PSUs have begun making profits on petrol and diesel. The companies are only concerned that the entire process of getting money against the bonds could be a long drawn out process which brings added problems of higher interest costs. They are also hoping to get a financial package which can make up for the losses incurred between October and March 2009 as well as for the balance for the first half which have not been completely compensated.
Non-domestic LPG prices cut by Rs 240-270 a cylinder
December 1, 2008. Private and public players in the non-domestic liquefied petroleum gas (LPG) business have passed on the benefit of reduction in international product prices to customers. The price of commercial LPG that is sold in 19-kg cylinder has been reduced in the range of Rs 240-270. The prices are expected to go down further in January as the LPG prices for December in the global market has gone done by another $150 a tonne and is ruling close to $340 a tonne. Originally, the non-domestic LPG prices was expected to go down by Rs 300-Rs 320 a cylinder, but due to rupee depreciation the entire benefit of the international prices could not be passed on to the customers. If the rupee was at Rs 41 versus dollar then the price would have come down by over Rs 300 a cylinder.
Commercial LPG has seen a growth of about seven-eight per cent. The decline in non-domestic LPG prices is also going to boost the auto gas sector, which saw a nil growth in the last quarter. The auto gas sector had seen a growth of nearly 40 per cent in the last fiscal. The category is expected to pick up considerably as auto gas is cheaper than petrol by almost 35 per cent.
While prices of commercial LPG (19 kg) has decreased to Rs 831.1 a cylinder from Rs 1,108.5 a cylinder in
Kerala opposes declared goods status to ATF
December 1, 2008. The Kerala Government is not in favour of the move by the Union Finance Ministry to accord declared goods status to aviation turbine fuel (ATF). The proposal is aimed at enabling the domestic airline industry to save on fuel cost. However, it will result in revenue loss to the states. If declared goods status was given to ATF through an amendment to the Central Sales Tax Act, states would be able to levy sales tax on the commodity only at the standard rate of four per cent.
This would result in a combined annual revenue loss of Rs 3,500 crore ($691.69 mn) to the states as most of them were levying more than four per cent tax on ATF. States were in the grip of financial difficulties in the wake of mounting expenses and pressure on infrastructure requirements. Besides, the recession had started adversely affecting the revenue receipts of most state governments.
Deora invites CIS investments in oil and gas sector
November 26, 2008. Murli Deora, the Union Minister of Petroleum and Natural Gas said that
The Petroleum Minister pointed out that
Mukesh Ambani for stable oil pricing globally
November 26, 2008. According to Mukesh Ambani globally a stable oil pricing regime was needed to sustain investments and economic growth. Energy had crucial role to play in economic prosperity and social equity and it has to available, accessible and affordable. Stable oil pricing regime was the need of the hour. According to him, availability was not an issue as 2 trillion barrels of conventional oil reserves still remained to be exploited that would be enough to support world demand for 3-4 decades.
Another trillion barrel reserves are trapped in non- conventional sources such as oil shells and tar sands. However, accessibility is an issue as most of the reserves are in hostile and remote physical environments. Crude at even USD 60 per barrel is unaffordable to many nations. One time (oil-cartel) OPEC had talked of maintaining crude oil price in a band of USD 25-30 a barrel. This would be necessary (for) economic prosperity.
POWER
Generation
GVK Power’s hydro project to go on stream before schedule
December 1, 2008. Infrastructure developer GVK Power and Infrastructure (GVKPIL) is set to complete its Rs 2,069-crore ($408.89 mn) Alaknanda hydro power project in Rishikesh ahead of schedule. Several other private infrastructure projects in the country are getting delayed as service providers are finding it tough to raise money due to the credit crunch. But GVKPIL’s Alaknanda project features in the list of few projects that are on track.
The company has also received financial commitments from international private equity players to fund the ongoing project. Foreign PE funds have expressed their interest to fund the Alaknanda project. The company had earlier infused Rs 142 crore ($28.06 mn) as promoter’s equity for the project. It raised around Rs 1,600 crore ($316.2 mn) from a consortium of 11 banks and one financial institution from
GVK is implementing 330 MW Alaknanda hydro power project, located 110 km from Rishikesh. It comprises four units of 82.5 MW each. The power purchase agreement (PPA) for the project was inked with the Uttar Pradesh Power Corporation (UPPCL) in 2006. The project achieved financial closure in August 2007. Bharat Heavy Electricals (Bhel) bagged the contract for electro-mechanical works. GVKPIL has diverse interests in urban infrastructure, energy, aviation, hospitality and manufacturing.
Apart from this project, the company is also developing other power projects that are based of coal and gas resources in several states including Andhra Pradesh and
Nuclear Power Corporation identifies 4-5 sites to set up 1,000 MW units
November 30, 2008. Nuclear Power Corporation of India Ltd (NPC) plans to set up clusters of nuclear power plants in identified ‘Nuclear Parks’ in the country. At least 4-5 such sites that include Koodankulam in Tamil Nadu and Ratnagiri in
The company said that about 10 large reactors of the Light Water Reactor (LWR) are also planned with participation of global players. The company also said that discussions are on with energy majors such as GE, Westinghouse of the
Under an accelerated expansion programme during the current Eleventh Plan, NPC has got the mandate to implement eight units of the Pressurised Heavy Water Reactor (PHWR) of 700 MW rating.
BHEL to set up supercritical power plant in Tamil Nadu
November 26, 2008. Bharat Heavy Electricals Ltd. (BHEL) has formed a joint venture to set up a thermal power plant in Tamil Nadu based on the supercritical technology. BHEL signed the agreement with the Tamil Nadu Electricity Board (TNEB) in Chennai. The company has partnered with TNEB to set up the plant with two units of 800 MW each. The plant will be built through turbines using the supercritical technology.
Steam turbines based on supercritical technology use less energy and generate higher pressure for greater efficiency than traditional plants. The land for the project, proposed to be set up at Udangudi in Tiruchendur Taluk of Tuticorin District, has already been identified. With a total capital outlay of around Rs 87 bn ($1.76 bn), the project will be the first supercritical power project to be installed in the state of Tamil Nadu and will strengthen the power availability in the southern state. The Boilers and auxiliaries will be manufactured by BHEL at its Tiruchirapalli and Ranipet works in Tamil Nadu.
These 800 MW coal-fired units will be able to harness the multiple benefits of higher plant efficiencies and economies of scale and will generate electricity in an environment friendly manner. The present installed power generating capacity in Tamil Nadu is 10,122 MW, of which 5,808 MW is contributed by BHEL sets. The proposed 1,600 MW capacity to be contributed by Udangudi power project will give a boost to the developmental efforts of the Govt. of Tamil Nadu. The joint venture has been registered under the name Udankudi Power Corporation Ltd.
The first of the two 800-MW units would start operation in March 2012 and the second in September. TNEB and BHEL signed an MoU for the project in October 2007. The environment impact assessment has been done and a public hearing would soon be held. The feasibility report has been finalised and a detailed project report completed soon. BHEL has already bagged major orders for power generating equipment with supercritical parameters, from NTPC for the 2x660 MW Barh Thermal Power Project Stage-II, and from APGenco for the 2x800 MW Krishnapatnam Power Project.
Transmission / Distribution / Trade
Coal
December 2, 2008. Coal
Central Electricity Authority (CEA) has reportedly agreed to accept the annual action plan (AAP) targets set by the Planning Commission as CIL’s total annual coal supplies to the power sector. The latter would therefore meet the additional requirements, if any, through its captive production and (or) imports. Once CEA agreed to accept the action plan targets CIL was also agreeable to set the trigger level at 90 per cent of the same.
The company had previously set the trigger at 60 per cent which was rejected by NTPC and most of the other utilities. Failure to meet the assured supply/off-take clause would invite penalty either on the seller or the buyer. CEA had further agreed to meet with all the utilities and re-allocate the annual supplies among all power plants in a manner that coal can be reached to all in the most efficient manner from CIL mines taking into account the logistics and other related issues.
The CIL has supplied 164 mt coal to power utilities between April and October, this year which was 2.5 mt more than the action plan targets.
Proposed power projects in
December 1, 2008. The commissioning of proposed thermal power plants in
The commissioning of plants could be delayed due to state government's unwillingness to acquire land by applying force, keeping perhaps in mind the trouble at Singur and Nandigram in
The government recently announced that a person whose land would be acquired would get Rs 1.95 lakh per acre and if donated voluntarily he would get Rs 2.40 lakh per acre. If any residential land was acquired, the land owner would get the cost of land for building house, Rs 10,000 for temporary accommodation and Rs 5,000 for carrying household goods. Out of 14 plants lined up for investment, only one plant being set up by JAS Infrastructure Capital Pvt Ltd, Patna has made some progress as it has identified 415 acres of land for acquisition.
GMR Energy to supply 200 MW power to
December 1, 2008. GMR Infrastructure Ltd. has announced that GMR Energy Ltd. has signed a contract for supply of 200 MW power on a round-the clock basis to Bangalore Electricity Supply Company Ltd. (BESCOM), from November 16, 2008 up to January 31, 2009. Prior to this, GEL supplied 200 MW of power to Rajasthan State Electricity Board, on a round-the-clock basis from November 4, 2008 to November 15, 2008.
Coal India reintroduces long wall mining at Moonidih
December 2, 2008. As part of its renewed focus on underground mining, Coal
The project would produce 3.5 mt of coking coal within four years using longwall mining technology. The contract includes Rs 130 crore ($25.96 mn) for the long wall power support equipment and Rs 306 crore ($61.11 mn) for operation, maintenance and after sales support for five years with penalty/bonus clause on assured production of 0.7 mtpa. The introduction of technology is expected to bring down the cost of production at the loss making Moonidih from Rs 3,200 a tonne to Rs 1,015 a tonne.
At the current price of Rs 1,720 a tonne for raw coking coal, CIL therefore will recover the cost of the technology in two years. The share of underground production in CIL’s total production has witnessed a steady fall for last three decades. From 65 mt in 1975, underground production was 43.2 mt in 2006-07. The declining trend was arrested in 2007-08 with an underground production of 43.4 mt. The total production of the company during the year was 380 mt.
Several high capacity mines had been selected for enhanced production and expression of interest (EOI) had been floated. Under the annual action plan of the 11th Five Year plan, CIL aimed to produce around 292.93 mt coal for power sector utilities. CIL achieved production of about 164 mt of coal as against the targeted 161.5
Move to tap 150 GW hydel potential to hit
December 2, 2008. India's plan to tap 1,50,000 MW of hydro potential to meet its target of generating 3,98,000 MW by 2030 will bring about a major ecological disaster, according to Euro-India Economic & Business Group (EIEBG). EIEBG is a business group working in
According to International Energy Agency (IEA) report,
According to the group, there is the need to be cautious as over-harnessing of hydro potential has caused a major disaster in
Tilaiya UMPP bids deferred till Dec 29
December 2, 2008. Power Finance Corporation (PFC), the nodal agency for the government’s ambitious plan to develop ultra mega power projects (UMPP), is set to be delayed with bids for the Tilaiya project in Jharkhand being deferred for the fifth time. The bids are now rescheduled for December 29. PFC was forced to defer the price bids as power companies have expressed concerns over the availability of funds for the project, given the current global liquidity crunch.
Bidders also want clarity over the issue of the coal transportation system in the project. PFC decided to postpone the bidding as bidders wanted more time for placing their financial bids due to concerns over raising funds and getting financial closure for the project. The additional time would also be used to clear problems being faced by the railways for setting up coal transportation network (mainly merry-go-round system) for the pit head power project.
Nine prospective bidders including Tata Power, NTPC, Reliance Power, Essar Power, L&T and Sterlite Industries are in the fray for the Tilaiya project. Only three of the bidders wanted to go ahead at this stage, while the other contenders wanted more time. As per the original plan, the government wanted to complete the bidding for Tilaiya UMPP as early as July 2007.
Earlier, the project faced some delays over identification of site, getting water source and obtaining other regulatory clearances. The delays may now impact five other UMPPs that the government intends to bid over the next few months. The Tilaiya project would require investment of Rs 16,000-18,000 crore ($3.19 – 3.59 bn). With a debt-equity ratio of 70:30 for most power projects, raising a huge amount of finances is considered difficult. The government, on its part, has tried to address the issue by relaxing norms for foreign loans by allowing companies to raise up to $500 mn through the automatic route.
Energy costs make
December 2, 2008.
According to him,
Hydro projects, rural power to get priority funds
November 29, 2008. The government is re-considering the proposal to include rural electrification and hydro power projects under the priority sector lending target of banks. The proposal, earlier approved by a sub-committee of the group of ministers (GoM) on power sector-related financial issues, was turned down by the finance ministry on technical grounds. The move is expected to unlock over Rs 2,00,000 crore ($40.34 bn) for the sectors facing resource crunch.
Banks are required to lend 40% of their total loans to the identified priority sectors such as agriculture and small & medium enterprises (SMEs). The proposal seeks favourable lending from banks for rural electrification, decentralised distributed generation projects and micro hydro projects where investments in plant and machinery do not exceed Rs 10 crore ($2 mn).
A committee in the Planning Commission is considering the proposal to accelerate investments in the infrastructure sector. Its recommendations would be sent to the finance ministry and the Reserve Bank of India (RBI) for further action. The committee is likely to submit its report next month. Rural electrification is one of the flagship programmes of the United Progressive Alliance (UPA) government and a component of the Bharat Nirman programme. The programme is aimed at creating rural infrastructure such as housing, roads, telecommunications and water supply.
The finance ministry is not in favour of extending the priority sector loan status to any sector without proper distinction. The government has set up a sub-committee of the GoM on power sector to exclusively look into financing issues including upgradation of transmission and distribution networks. The sub-committee is headed by Planning Commission deputy chairman Montek Singh Ahluwalia and includes power ministers of
There are several proposals to include priority lending status to sectors like power, road and aviation. All proposals cannot be entertained but specific needs of a sector can be considered. Banks already have a high credit exposure to the power sector. Their exposure to power sector is around 50% of total infrastructure financing. However, in real terms banks’ exposure to the power sector is only around Rs 60,000 crore ($12.1 bn) while their investment requirement is over 10,00,000 crore ($201.73 bn) in the Eleventh Five Year Plan (2007-12).
Once RBI clears the proposal, banks would be free to include these segments as part of their exposure to meet priority sector lending target. With banks’ total credit standing at about Rs 27,00,000 crore ($544.68 bn) as on November 7 this year and growing at over 30%, about Rs 10,00,000 crore ($201.73 bn) would be available for priority sector lending.
BHEL wants 15 pc duty on power equipment
November 26, 2008. State-owned Bharat Heavy Electricals is lobbying hard with the finance ministry to impose a 15% duty on imported power generating equipment in a bid to counter the increasing competition from Chinese players. Post Olympics,
As per the company, if the Indian government does not impose a duty on Chinese companies, BHEL would be wiped off after five years. Chinese equipment makers such as Dongfang Electric, Shanghai Electric and Harbin Power Equipment have already supplied equipment to the
Indian companies placed orders with the Chinese companies as their power equipment is cheaper than Bhel’s. The domestic power equipment company is unable to cater to the rising domestic demand due to its own capacity constraints. It is increasing capacity to produce equipment for generating 15,000 MW power by December 2009 and 20,000 MW by 2011. Bhel has an order book position of Rs 27,000 crore ($5.48 bn) and expects to close seven power projects of 3,500 MW in four months. But the company’s growth will be lower this year compared to 41% last year.
INTERNATIONAL
OIL & GAS
Upstream
Edison to pay $1.4bn for
December 2, 2008.
Edison,
The cash flows generated by the concession will cover the investments starting from 2012. The investments made before 2012, estimated at about $750 mn, will be funded half through cash flow from the concession and half through dedicated financings. The concession, which produces around 1.5 billion bcm of gas per year and 1.5 million barrels of oil, has a 20-year duration and can be extended for a further 10 years.
Saratoga turns on taps at 2 Grand Bay wells, establishes new benchmark
December 2, 2008. Saratoga has established record levels of production for the Company of net 1,803 barrels of oil per day (BOPD) plus 7,661 thousand cubic feet per day (MCFPD), the equivalent of 3,080 barrels of oil equivalent per day (BOEPD). Contributing to these totals are the recent recompletions at SL 195 QQ#205 and SL 195 QQ#15.
The QQ#205 well was completed on November 23rd at an initial rate of 305 BOPD, 340 MCFPD plus 3 barrels of water per day (BWPD) through a 15/64 inch choke. The Company has also begun shallow gas production from Pliocene aged sands at a depth of 1,600 feet at Grand Bay Field. The QQ#15 well was completed on November 25th and is currently producing 1,063 MCFPD plus 3 BWPD through a 19/64 inch choke.
Shell JV spies gas at Browse Basin's Libra-1
December 2, 2008. Nexus has advised that on December 2, the Libra-1 exploration well in exploration permit AC/P41 in the
Further wireline logging and pressure data is required to determine reservoir quality, column height and hydrocarbon composition. The Ocean Epoch semisubmersible rig is drilling the exploration well which is operated by Shell Development (Australia) Pty Ltd on behalf of the joint venture.
Uruguay opens bids for offshore oil, gas blocks
December 1, 2008. Uruguay Energy Ministry and ANCAP, the National Oil Company, will launch the offshore licensing round for exploration and exploitation of gas and oil on December 1-3. The blocks on offer, lie in the Punta del Este and
The blocks' areas range from 2,500 to 10,000 square kilometers. In the offshore of
In addition to new deep 2D seismic studies by Wavefield Inseis, the whole seismic, stratigraphic and structural integrated studies allowed ANCAP's technicians to establish a number of leads and plays located in offshore Uruguay in bathymetries ranging from depths less than 200 to depths greater than 1500 meters. The main exploratory situations are linked to the sedimentary sequences corresponding to the prerift, sinrift and sag evolution phases of these basins.
In South America, between
PetroChina starts developing offshore block in
December 1, 2008. According to CNPC, PetroChina Co. has started developing an offshore block in
As an aging field, Liaohe faces depletion of reserves and needs Yuedong as a replacement. Development of Yuedong is highly risky and expensive due to active tides and a long icing period in the block. PetroChina has formulated an overall development plan for the block, including construction of four artificial islands, an oil pipeline and one land-based processing station.
Cooper increases PEL92 production to 5,000 bopd
December 1, 2008. According to Cooper Energy, production from the prolific PEL92 production area has been boosted to approximately 5,000 barrels of oil per day (Cooper Energy share 1,250 barrels of oil per day). Following a series of successful well workovers, the PEL92 fields exported over 5,000 barrels of oil per day. The Callawonga Oil Field alone contributed approximately 4,000 barrels of oil per day to this total.
The Parsons to Callawonga 9 kilometer 5 inch flowline connects the Parsons Oilfield through the Callawonga and Tantanna facilities to the
Ensco 107 gears up at Maari Oilfield, first oil expected in February
December 1, 2008. Initial drilling of the Maari oil field production wells by the Ensco 107 jack-up drill rig has made good progress in the second half of November. The US$600 million OMV-operated project in offshore south Taranaki is forecast to produce 50 million barrels of crude oil at up to 35,000 barrels a day.
The Australian stock exchange-listed Horizon Oil Ltd, is a joint venture partner in the Maari project. Ensco 107 will drill 5 oil development wells and 3 water injection wells into the main Moki sands at Maari. The Maari field is located in PMP 38160, some 40 km south of the
North American Energy Resources completes second well in six well package
November 26, 2008. North American Energy Resources has completed drilling the second well of its six well package in the Mississippi Chat formation at a total depth of 1,540 feet. The well will produce both oil and gas. The Company has installed an oil separator and tank battery on the Washington County, OK property and will begin collecting oil from the well. The gas production will be connected to the Company's 75% owned Apwash pipeline. Logs indicate an additional oil show in the Wayside formation.
Downstream
Spain refinery upgrades on track; more diesel seen
December 2, 2008. Spanish energy companies say that plans to upgrade refineries and reduce the country's yawning deficit in diesel are on track despite the credit crunch. Earmarked for investment by 2011 are more than 6 billion euros ($7.57 billion) to upgrade six of
Along with other planned expansions, it would add 260,000 bpd in crude distillation capacity to a current total of 1.37 million bpd. According to Repsol, which is
In the 12 months to September, the latest date for which data is available, net diesel imports were 12 mt, or 33.7 percent of consumption logged by Spain's energy reserves body CORES. The only oil product in which
Cepsa will spend 1.65 billion euros by 2010 to boost output of middle distillates, including diesel and kerosene, by 39 percent and up its total refining capacity by 17 percent. Repsol has the lion's share of planned investment, including 3.2 billion euros aimed at raising crude distillation capacity at its
Shell says oil sands upgrader work cuts output
December 2, 2008. Royal Dutch Shell Plc’s 155,000 barrel per day Scotford oil sands upgrader near
US Gasoline demand increases
December 2, 2008.
The average price for gasoline, which has been well above year-ago levels for much of the year, is now 40.1 percent lower than it was one year ago. The four-week moving average for gasoline demand dropped 2.1 percent from year-ago levels. The one region that was the exception to the rule was the West Coast, where demand was down 4 percent as gasoline prices remain comparatively high at an average of $2.08 per gallon.
Lukoil pays first tranche for ERG refinery
December 1, 2008.
Vietnam's first refinery gets crude for test run
December 1, 2008. The first ever Dung Quat Oil Refinery in central Quang Ngai
The Dung Quat oil refinery will kick off its official operation in 2010, with a plan to produce 5.7 million tons of petrol and oil of international standard to primarily serve domestic demand. The country's first refinery is designed to be capable of refining 6.5 million tons of crude oil annually, which are expected to meet around 30 percent of local demand for fuel. So far, the Dung Quat refinery has almost 98 percent of its construction workload completed. It is expected to start commercial operation by late February, 2009.
CB&I, Hoegh target Q2 for decision on floating LNG plant
November 29, 2008. Chicago Bridge & Iron Co NV (CB&I) and Norwegian shipper Lief Hoegh plan to take a final investment decision (FID) on building a floating liquefied natural gas plant in the second quarter of next year. Hoegh is talking to gas suppliers and offtakers, and by the early part of the second quarter they should have FID. LNG is gas chilled to its liquid form for ease of transport beyond the reach of pipelines.
Floating LNG projects allow for gas to be explored in areas -- onshore or offshore -- that are too small to be developed by conventional means. While yet untried, producers hope they will take less time to build, roughly three years versus eight to 10 years for conventional LNG projects, and may even be cheaper than onshore alternatives. A floating LNG production facility would cost about $800 per tonne per year (tpa).
Flex LNG Ltd, which is poised to build the world's first floating LNG production facility with its Nigerian joint venture with Mitsubishi Corp and Peak Petroleum, estimates it will cost $550 to $700 per tpa, less than what the company says onshore plants cost -- at more than $1,000 per tpa. Royal Dutch Shell and Inpex are also planning to build floating LNG projects
Transportation / Trade
Pacific trail seeks interest for Kitimat pipeline
December 2, 2008. Pacific Trail Pipelines (PTP), operator of a proposed natural gas pipeline in
Kitimat LNG, wholly owned by Galveston LNG, expects to start reviewing interest in mid-December. Pacific Trail Pipelines is a partnership between Pacific Northern Gas Ltd and Galveston LNG. LNG is natural gas cooled to liquid for transport in specially designed tankers and then regasified at a terminal for transport ashore through pipelines.
Gazprom holds talks on construction status of Gryazovets-Vyborg pipeline
December 2, 2008. Gazprom Management Committee held a meeting at the Gazprom Headquarters dedicated to implementing the project for the Gryazovets-Vyborg gas pipeline construction and developing the gas supply to the Kaliningrad Oblast. The meeting brought together the Gas Transportation, Underground Storage and Utilization Department, and the relevant divisions of the Gazprom Administration, as well as Yamalgazinvest, Gazprom invest Zapad, Gazkomplektimpex and Giprospetsgaz.
The meeting participants discussed the current construction status of the Gryazovets-Vyborg gas pipeline to be utilized, inter alia, for gas conveyance to the Nord Stream gas pipeline. It was noted that the pipeline construction was progressing on schedule. The current year will see the commissioning of some 165 km of its line pipe, at the same time the total length of the completed and brought onstream linear part of the Gryazovets-Vyborg gas pipeline will total some 475 km.
The meeting also addressed the progress in developing the gas supply to the Kaliningrad Oblast. It was emphasized that expansion of the gas transportation capacities and creation of the
SESH to hold expansion open season
December 1, 2008. Southeast Supply Header, LLC (SESH), a 50/50 joint venture between affiliates of Spectra Energy Corp and CenterPoint Energy, Inc., announced that it is conducting a non-binding open season for a proposed expansion along its existing 274-mile pipeline system. The pipeline currently extends from CenterPoint Energy's Perryville Hub, near
The SESH pipeline is strategically positioned to provide flexible and economic transportation solutions to meet the energy needs of the southeast
During the open season SESH will accept non-binding nominations for service from any existing or proposed receipt points to any existing or proposed delivery points on the SESH system. The specific scope of the expansion will be finalized following the results of the open season. The target in-service date would be as early as mid-2011.
BP will back CPC expansion if allowed to sell its stake
November 29, 2008. Oil major BP will back the long-delayed expansion of the CPC pipeline from
BP, the only shareholder that still opposes the terms, has said it was considering selling the stake if no compromise was found. The group's shareholders hope to sign the memorandum on CPC expansion at their meeting on December 17. BP wants to sell its stakes in CPC to Russian oil major LUKOIL and Kazakh KazMunaiGas but needs the sale to be approved by all other private and state shareholders of the pipeline consortium.
BP supports the principles of CPC extension only if it has a clear and unencumbered right to sell its stake to a selected group of companies. BP was in talks with LUKOIL and KazMunaiGas to sell its stakes in its joint ventures with the Russian and Kazakh companies, LUCARCO and Kazakhstan Pipeline Ventures, which are members of the consortium. BP's stakes in the ventures bring its share in CPC to 6.6 percent.
Russian pipeline monopoly Transneft, which holds the country's 31 percent stake in CPC, had long opposed the plan to double the pipeline's capacity from the current 700,000 barrels per day, but it has now dropped its objections. Transneft previously argued that the pipeline yielded low returns and that expansion would add pressure on the already congested Turkish Straits shipping route.
In summer, most of the partners agreed to raise the shipping tariff to $38 per tonne from $30.24 last year and private investors agreed to halve interest rates on a $5 billion loan to CPC to 6 percent, easing worries over funding. Transneft, which owns all pipelines on Russian territory except CPC, has said BP was insisting on borrowing more to fund the expansion. Chevron holds 15 percent in CPC. Its private shareholders also include Royal Dutch Shell, ExxonMobil and
Policy / Performance
Iran,
December 2, 2008.
The first MoU is a framework agreement for cooperation between NIOC and Petrofield LNG Co. Under this MoU, the two sides aim to develop the Golshan and Ferdowsi gas fields and establish LNG production units. The preliminary agreement also includes setting up a joint shipping company to transport LNG. The third MoU covers the refining of the Iranian heavy and ultra-heavy crude oil at Keda refinery in
China's natural gas market set to achieve balance by 2015
December 1, 2008. The demand and supply on
It is predicted that
Putin clears new Baltic pipeline to cut oil transit
December 1, 2008.
The project would be financed mainly through the issuance of long-term rouble bonds by pipeline monopoly Transneft to be allocated via a closed subscription mainly to state financial institutions. Transneft designed the project nearly two years ago after a pricing dispute with
Putin's approval is a big boost for Transneft, which also needs to find billions of dollars to finish building
Crude oil slips below $52 per barrel
December 1, 2008. OPEC defers a decision to cut output for another two weeks. It has postponed a decision until Dec. 17 to gauge the impact of a 1.5 mn barrel cut agreed in October. Oil prices fell below US$52 per barrel after the Organisation of Petroleum Exporting Countries (OPEC) deferred a decision to cut output for another two weeks.
As per the OPEC, slowing global growth means demand will be much lower than expected a month ago. Crude oil for January delivery fell as much as $2.65, or 4.9%, to $51.78 per barrel in electronic trading on the New York Mercantile Exchange. It was at $52.04 a barrel at 11:16 a.m. in
On Nov. 21, it touched a three and half year low of $48.25. The Organisation is of the view that oil demand is likely to drop further next year. The global market is oversupplied by more than 2 mn barrels per day.
‘New refinery part of $44 bn Mexican infrastructure plan’: President
December 1, 2008. According to
The Bank of Mexico has forecast economic growth of 0.5% to 1.5% for 2009, while the Finance Ministry has put growth at 1.8%. The central bank and ministry both expect the economy to grow 2% this year, down from 3.2% in 2007.
Calderon said major infrastructure projects for next year include breaking ground on a new metro line in the capital of
Oil and related taxes account for over a third of the federal government's annual revenues. Pemex has struggled to replace output from aging fields due to a lack of investment in exploration and field development in recent decades. For the first 10 months of the year, average production was down 9.6% to 2.82 million barrels a day, due to a 31% drop at the giant Cantarell oil field. Oil exports were at 1.43 million barrels a day in October.
Russia may work with OPEC on output cut
November 26, 2008.
Even after the 13-nation Organization of Petroleum Exporting Countries cut oil production by 1.5 million barrels a day last month crude oil prices have fallen to about $50 a barrel - a third of their July peak of nearly $150. He pointed out that many of the budgets of oil producing countries have been balanced based on the oil price band of between $70 to 90 per barrel.
He also mentioned that Russian investment has also been budgeted at $70 per barrel. Shmatko also said that
POWER
Grid-connected photovoltaic power plant built in
December 2, 2008. Hubei's first grid-connected photovoltaic power plant, currently under construction in
The project, with an installed capacity of 1.2 MW, involves a total investment of 66.05 million yuan. The annual electricity-generating capacity will reach 1.6-1.8 million kilowatt-hours. The grid-connected photovoltaic power plant, currently
The grid-connected BIPV electricity-generating technology can be applied in public buildings such as industrial factories, urban residences and new buildings in rural areas. The energy section of the Hubei Development and Reform Commission disclosed that
Transmission / Distribution / Trade
Study says competition good for electricity consumers
December 2, 2008. Retail electric competition has helped put downward pressure on the price of electricity for
The study found that the primary price component analyzed in the study (the cost of power generation) decreased as much as 13 percent in the latter period, following the inception of retail electric competition in 2002. The study notes that the overall price of residential electric service has increased since 2002, but it attributes the increase to factors other than retail competition, notably the significant increase in the price of natural gas. The price of natural gas in August 2008 was more than three-and-a-half times the fuel’s price in January 2002.
California grid operator set to overhaul real-time market
December 2, 2008.
It also will change the way power deliveries are priced. The system, particularly the transmission pricing changes, will make
Utilities generally turn to the California ISO's real-time electricity market when power plants or transmission lines they rely on shut down or are curtailed unexpectedly, and they need extra power fast.
Under the new system, power deliveries will be priced based on the distance between the generator and the delivery point, measured in "nodes" or geographical markers. Real-time power deliveries in
The new system's tighter focus will allow the ISO to identify areas of
The Electric Reliability Council of Texas, which operates
Electricity tariffs adjusted
November 28, 2008. According to Public Utilities Corporation (PUC), water and electricity bills received from December 1 onwards will reflect between 20% and 35% increases. Electricity consumers will on average pay 20% more and water bills will show a 30% increase. The rates for electricity will be adjusted every month while those for water will be reviewed every three months.
The electricity rate reviews will be more frequent because of the rapid manner in which oil prices change and the water rates are higher because besides using electricity to pump water, the PUC also needs chemicals and other materials whose prices have gone up. The discounts given for the first 300 units of electricity used were costing the PUC R1.5 million monthly but have now been removed.
The discount was meant for those who could ill afford electricity, but the reductions were being enjoyed by all consumers. But now people who have difficulty paying are expected to seek help from the Social Welfare Agency. The PUC was forced to revise the rates to recover its costs, which have risen with the increased cost of fuel.
The rate for the first 300 units of electricity was R1 per kilowatt hour because the PUC was giving a 30-cent discount, which has now been removed, so the increase for the initial 300 units is going to be 40 cents per unit. It is no longer possible for the PUC to sustain the R90 discount for the first 300 units. The rates for electricity were last revised in August and for water in January. The PUC said that the government has not subsidised electricity production for over 11 months now.
Policy / Performance
CBP scheme to be applied for electricity pricing in Vietnam
December 2, 2008. Ministry of Industry and Trade (MOIT) has submitted to the Prime Minister a plan on building up the competitive electricity generation market in
Under the scheme, all power plants with the capacity of 30 MW and higher will have to bid prices on the market, except the BOT (build-operation-transfer) power plants. Electricity generation units will sign contracts on selling electricity with the only buyer. Power plants with have different modes of investment (thermopower, hydropower, multi-functional hydropower plants and BOT plants) will have to offer prices in accordance with different principles and with different ceiling and floor prices, which aim to avoid sudden price increases on the market.
Leaders of MOIT believe that CBP is the optimum model. They say it will allow electricity stability and avoid unexpected price increases, while minimising risks for investors. MOIT has also suggested three plans to restructure the electricity industry to make it suitable to the competitive power generation market and the CBP scheme. MOIT has suggested assigning the National Load Dispatch Centre to give advice to the MOIT on the issue of state management, in order to ensure the safe, effective and stable provision of electricity.
The centre also has the function of reporting to the Ministry of Industry and Trade, so that the ministry can submit plans on electricity price retailing to the government for approval. The centre will also have the function of verifying and assessing the power development strategies in provinces and cities put under central management.
Power tariffs to double in
December 2, 2008. According to South African Government, electricity tariffs in
Last January, the country suffered widespread blackouts that forced Eskom to ration power and shut down the key mining industry for a week. Households account for more than a third of all electricity usage. The government says if homes adopted energy-saving measures,
Work together and save electricity: Dy. President
December 2, 2008. According to Deputy President Baleka Mbete, work together to save power and cut out the waste. Immediate way South Africans could help was through simple behavioural changes to halt unnecessary power use, or even wastage, of electricity. Eskom, the national power utility, needed to increase power savings to allow maintenance of electricity plants in January.
For its part, government had refitted 4 000 buildings, saving what the deputy president said was R56-million a year in electricity costs. For businesses, government is providing free technical support to identify ways to save electricity. Government is also exploring tax incentives for more energy efficient production. Government was also trying to re-shape electricity tariffs to encourage more efficient electricity usage. Government planned to work with civil society, churches, organised business and labour to save power and allow society to benefit from a safe and security supply of electricity.
Regulator freezes prices of gas and electricity
December 1, 2008. The energy regulator has announced there will be no increases in the price of gas or electricity next year in
In making its decision, the Commission had taken into account recent falls in the price of gas, coal and oil on the international fuel markets. The Commission says electricity prices should fall by up to 2%, thanks to a €300 mn rebate and the sale of a number of ESB power stations. The regulator had also been careful to ensure prices are cost reflective so as not to distort competition in the retail gas and electricity markets. In early November Bord Gáis had proposed a price increase of on average 3.9 per cent, while the ESB had proposed a 5.6 per cent increase. Employers’ group Ibec also welcomed the decision but expressed concern that energy costs in
‘True cost of electricity needed to sustain privatization efforts’: IFC
November 27, 2008. According to International Finance Corp. (IFC), the government needs to reflect the true cost of electricity in the power generation rates of state-owned National Power Corp. (Napocor) if it wants to sustain its privatization program. Regulators should update the present tariffs of Napocor and enforce an automatic cost recovery scheme in order to keep electricity rates up to date.
Napocor currently recovers its fuel and foreign exchange costs through deferred accounting adjustments comprised of the Generation Rate Adjustment Mechanism and the Incremental Currency Exchange Rate Adjustment Mechanism, respectively. These pass-though costs have to be filed for applications before the Energy Regulatory Commission (ERC) on a periodic basis.
Renewable Energy Trends
National
Campco plans wind energy production
December 2, 2008.
The 1.25 MW plant would come up at Hoovina Hadagali. The power produced will not be sold. After wheeling it, the power will be used for its chocolate factory in Puttur. The electricity produced at Hoovina Hadagali will be supplied to the grid and used for its factory consumption. The Campco board has already adopted a resolution in this matter. Around Rs 7 crore ($1.39 mn) will be invested in this project. The generation cost at the proposed Hoovina Hadagali plant will be to the tune of Rs 1.78 per unit. Another seven per cent wheeling charge will be added to this.
Wind power body asks TN electricity regulator to hike tariff
December 1, 2008. The Indian Wind Power Association, while welcoming the Tamil Nadu Electricity Regulatory Commission (TNERC) order approving its petition seeking permission to let wind energy generators bank energy, has asked the commission to hike the tariff to make investments in wind mills viable in the State.
According to the association, the TNERC, through an order on November 21, has directed the Tamil Nadu Electricity Board (TNEB) to let the wind energy generators use the banked energy in five equal monthly instalments from December 2008 to April 2009. In its petition, the association had said that following the acute shortage of power in the State, the TNEB, which imposed restrictive and control measures with effect from November, had ignored the banked energy while working out the quota of power that can be used by the units with captive wind power generation facilities.
Banked energy is the surplus energy that wind energy generators produce over and above their own consumption during the windy season. Under the wheeling agreement with TNEB, the generators bank the excess power during the season and use it during the non-wind season, after paying the banking charges. The petition also pointed out that other captive power generators were allowed to use the power generated by them over and above the quota fixed by the electricity board.
The association has also asked the regulatory commission to fix a tariff of Rs 3.90 a unit as the present tariff of Rs 2.70 a unit paid by TNEB to the wind energy generators had not been revised since 2001. The association said that the cost of wind electric generators has increased to Rs 6.75 crore ($1.33 mn) a MW from Rs 4.50 crore ($0.88 mn) earlier and interest rates had increased to 14 per cent. It is because of the unviable tariff and restrictive practices of the TNEB that expansion of wind energy capacity in Tamil Nadu had been affected in the last two years while
Textile mills for uniform power cut of 20-25 pc in Tamil Nadu
December 2, 2008. According to the Southern India Mills Association (SIMA) imposing a 20-25 per cent uniform power cut across the State of
The order of the Tamil Nadu Electricity Regulatory Commission (TNERC) with regard to utilisation of banked wind energy generated between April 1 and October 31 in five equal monthly instalments during December 1 to April 30, 2009, by enhancing the demand and energy quota proportionately was a major relief to the textile industry which accounted for 75 per cent of the wind turbine generator capacity installed in the State (over 3,000 MW).
TNERC to verify the data provided by TNEB with regard to actual generation, shortage and distribution of power shortage across the industry and ensure equal distribution of power and draw up principles and protocols in line with the Maharashtra State Electricity Regulatory Commission for load shedding and power cut to minimise the losses incurred by the industry.
According to SIMA a uniform power cut of 20-25 per cent would be an ideal solution. The diesel captive power generation model would be the ultimate solution to tide over the power crisis in Tamil Nadu for the next three or four years. But with the proposed power restrictions, the textile industry would be able to achieve only 40 per cent capacity utilisation that would bring it to a halt.
Reliance Industries Limited enters into pact with 3 power discoms
December 1, 2008. Reliance Industries Ltd. (RIL) has entered into an agreement to sell solar energy to three three power companies of Rajasthan — Jaipur Discom, Ajmer Discom and Jodhpur Discom. RIL is setting up a 5 MW solar power generation plant at the Khimsar village in Nagaur district. As per the Jaipur Discom, the agreement is first of its kind to tap the solar energy for the benefit of consumers in the state.
According to the agreement, RIL will get Rs 15.78 a unit. The power purchase rate would be Rs 3.67 for 10 years while Indian Renewable Energy Development Agency (IREDA) will pay Rs 11.33 a unit as per the directives of Renewable Energy Regulatory Commission (RERC) to promote solar green energy. Besides, the discoms will pay 78 paise a unit to the power generation company. The tariff and incentives will be applicable only if the plant is commissioned by December 2009. Electricity generation from solar energy is prohibitively expensive.
Tatas to invest more in wind power sector
November 30, 2008. Aiming at reducing carbon emission, the Tata Power will make additional investments in the wind power sector to take its production capacity from the present 200 MW to 500 MW by 2011. It has started to concentrate more renewable energy and is planning to increase its production capacity from the present 14 percent to 25 percent in the next couple of years.
The company was planning to reduce its dependency on coal for power generation and to concentrate more on solar, hydro-carbon and gas, considering the negative aspects of global warming. The Tata group was already exporting electric version of the Indica car to
India’s green spending could reach $150 bn by ’17
November 28, 2008. Biofuels, wind and clean coal are among the top climate change investment themes for
The report said
It estimated the total annual emissions saving of these investments at 480 mt of carbon dioxide from financial year 2018 onwards. But the report also highlighted risks from the global financial crisis to investment, which it said had thrown into question the durability of climate change as an investment theme. Although power capacity increased only 21,180 MW under the last Five Year Plan, this is set to grow four-fold in the current planning period to more than 80,000 MW.
India has the fourth-highest installed wind power capacity in the world. Despite strong annual growth, HSBC estimated installed capacity by March 31 this year amounted to just 6.2 percent of
The report also pointed to the government's backing of more efficient coal generation, such as supercritical and ultra supercritical technologies that make use of higher pressures and temperatures to boost efficiency and cut emissions. Assuming a benchmark cost of 45 million rupees per MW, the report estimated a capital investment of 1.7 trillion rupees in supercritical technology over FY 2008-17. These investments are likely to result in annual emission savings of 28 mt from 2017.
Global
TVA issues RFP for renewable, clean energy power supply
December 2, 2008. The Tennessee Valley Authority is requesting proposals to supply up to 2,000 MW of power generation from renewable and clean energy sources to TVA by June 1, 2011. Up to 1,000 MW of generation would be delivered to TVA by June 1, 2009, according to the Renewable Energy and/or Clean Energy Resources request.
The amount would increase to a maximum of 1,500 MW a year later and to 2,000 megawatts by June 1, 2011. TVA is targeting individual companies capable of producing at least 1 MW of electricity from renewable or clean energy resources and is interested in proposals that would provide the power supply from 1 to 20 years.
TVA's Environmental Policy approved by the TVA Board forecasts that more than 50 percent of total power generation will come from zero or low carbon-emitting sources such as nuclear and renewable energy by 2020. Renewable energy generation technologies that will be considered include solar, wind, hydropower, ocean, tidal, geothermal, biomass and other biologically derived fuels.
Clean energy generation technologies include combined heat and power, waste heat recovery and other low-carbon emitting resources. TVA will contract for the output of renewable and clean energy generation through power purchase agreements. In addition, as TVA evaluates its renewable and clean energy portfolio, another RFP is being issued to allow others to partner with TVA on the continued operation, study and use of TVA's original three wind turbines on
TVA installed the wind turbines in 2001 and established the first successful wind farm in the Southeast. Since then, 15 additional wind turbines have been installed on
Areva to build bioenergy power plants in
December 1, 2008. Evonik New Energies, a utility company, has awarded Areva the construction contract for a biogas power plant in
The biogas combined heat-and-power facility will generate in total 1.43 MWe of electricity. In parallel, the heat produced will be used to power the fermenters and dry the digestates to produce fertilizer. Construction of the plant will be finalized in 2010. Intrinergy has selected a consortium comprising Areva and KEM, a Danish supplier of biomass technology, to supply a turnkey cogeneration biomass plant and wood pellet manufacturing facility in
Solar and wind power generating facilities installed at Nakaze Plant
December 1, 2008. Yamaha Motor Co., Ltd. has installed both solar and wind powered generating systems at its Nakaze Plant in
The newly installed solar and wind power generating systems went into operation today at the factory. This is the first case of simultaneous operation of solar and wind power generation at a Yamaha Motor group factory. The combined annual generating capacity of the two systems is approximately 26,000 kwh and they are expected to enable a reduction of CO2 emissions equivalent to approximately 18 tons.
According to Yamaha Motor, the electricity generated by these two systems will be used for the lighting and air-conditioning system for the offices of the factory’s employee welfare building. The solar power generation system has been installed as a joint research project with the independent public sector organization New Energy and Industrial Technology Development Organization (NEDO) and it is the seventh system to be installed by Yamaha Motor.
Under the joint agreement, Yamaha Motor will supply data to NEDO on the system’s operation for the first four years. The system adopts a new format modular type design with a larger annual generating capacity than conventional systems of the same rated output and is also has a smaller environmental footprint in that it is manufactured by a process that results in lower CO2 emissions. The vertical type wind power generation system is the first of its type to be adopted by Yamaha Motor.
This type is quieter than a propeller-fitted windmill type, which makes it a more community-friendly system from the standpoint of neighbouring residents in the factory area. Yamaha Motor has pursued numerous means to reduce the environmental impact of its manufacturing operations, such as the installation of cogeneration systems and solar generation and changing from petroleum to natural gas as the fuel for its Aluminium melting ovens.
Under the corporate environmental plan, Yamaha Motor has set a goal of reducing CO2 emissions in its manufacturing operations by 12.5% compared to the 1990 level of 99,853 tons by the year 2010. That goal has already been achieved in 2007, when the reduction versus the 1990 level reached 14.4%. The company will continue to actively pursue environmental initiative including the switch to alternative fuels to replace petroleum and adopting new forms of energy.
Dear Reader, You may have received complimentary copies of the ORF Energy News Monitor. Our objective in bringing out the newsletter is to provide a platform for focused debate on We look forward to receiving your patronage and support. ORF Centre for Resources Management |
ORF ENERGY NEWS MONITOR Subscription Form Please fill in BLOCK LETTERS |
Subscription rate slabs for Commercial entries, Research Institutes, Academics and Individuals will be provided on request. The subscription can be made for soft copy or for hard copy or for both. Selected ORF publications as well as advertising space in one issue of the ORF Energy News Monitor are offered as introductory free gifts for Commercial Sector only. |
Yes! I/we would like to receive copies of the weekly ORF Energy News Monitor for a period of ______year(s). I/we shall be entitled to one hard copy along with the option of soft copies to a list of e-mail addresses provided by me/us for the period of subscription. I/we also note that I/we shall get select ORF publications brought out during the period of subscription free. Name……………………………Address…………….………………………Telephone……………………Fax………………….E-mail………………… Please find enclosed cheque/Bank Draft No.........................dated …………………drawn at Please fill in this form and mail it with your remittance to ORF Centre for Resources Management OBSERVER RESEARCH FOUNDATION 20 Rouse Avenue New Delhi - 110 002 Phone +91.11.4352 0020 extn 2120 (Vinod Tomar) Fax: +91.11.4352 0003 E-mail: [email protected] |
Registered with the Registrar of News Paper for
Published on behalf of Observer Research Foundation,
Disclaimer: Information in this newsletter is for educational purposes only and has been compiled, adapted and edited from reliable sources. ORF does not accept any liability for errors therein. News material belongs to respective owners and is provided here for wider dissemination only. Sources will be provided on request.
Publisher:
Production team:
The views expressed above belong to the author(s). ORF research and analyses now available on Telegram! Click here to access our curated content — blogs, longforms and interviews.