-
CENTRES
Progammes & Centres
Location
Will Power Shortages become a Thing of the Past by 2012? (part – II)
Continued from Issue No. 46…
The
Power Supply Position in 2006-07: Peak Shortages
Region |
peak demand in mw |
peak availability in mw |
surplus/defict in MW |
as % |
North |
35540 |
27860 |
-7680 |
-21.6 |
West |
35223 |
29657 |
-5566 |
-15.8 |
South |
31017 |
25973 |
-5044 |
-16.3 |
East |
11990 |
11431 |
-559 |
-4.7 |
N East |
1875 |
1814 |
-61 |
-3.3 |
Islands |
60 |
56.5 |
-3.5 |
-5.8 |
All |
115705 |
96792 |
-18913 |
-16.6 |
Power Supply Position in 2006-07: Energy Shortage
Region |
Energy require –ment in MU |
Energy availabili –ty in MU |
surplus/deficit in MU |
as % |
North |
220820 |
184217 |
-36603 |
-16.6 |
West |
224927 |
187390 |
-37537 |
-16.7 |
South |
194102 |
165859 |
-28243 |
-14.6 |
East |
69467 |
76668 |
7201 |
10.4 |
N East |
9501 |
8740 |
-761 |
-8.0 |
Islands |
280 |
212 |
- 68 |
-24 |
All |
719097 |
623087 |
-96010 |
-13.4 |
Supply Projections
Capacity addition projections for generation by the Government in the 11th plan are as optimistic as demand projections.
Guidelines used in projections on Generation Capacity additions
· Projects already taken up for execution in the 10th plan but due for commissioning in the 11th plan.
· Thermal projects by State and Central government generators for which Letter of Approval (LoA) is available
· Thermal projects from private developers which have achieved financial closure
· Thermal projects for which LoA is expected by September 2008 and commissioning expected by 2012.
· Hydro projects which have received concurrence from the
· Small hydro projects for which project gestation is less than 5 years
· Gas projects which are under execution and those projects for which gas supply has been tied up
Generation Capacity addition plans for the 11th Plan in MW
Sector |
hydro |
coal |
lignite |
gas /lng |
nuclear |
total |
projects under construction |
13,831 |
25625 |
1200 |
3142 |
3380 |
47,178 |
Committed projects |
2722 |
28630 |
250 |
1100 |
|
31,352 |
Total |
16553 |
58597 |
1450 |
4242 |
3380 |
78,530 |
Note: The above projections do not include merchant power plants that might come up during this period.
Sector-wise break up of capacity addition during 11th Plan in MW
Sector |
hydro |
coal |
lignite |
gas/lng |
nuclear |
Total |
Central |
9685 |
24310 |
1000 |
1454 |
3380 |
39829 (50.72%) |
State |
3605 |
23135 |
450 |
762 |
0 |
27,952 (35.60%) |
Private |
3263 |
5460 |
0 |
2026 |
0 |
10749 (13.68%) |
All |
16553 |
52905 |
1450 |
4242 |
3380 |
78,530 (100%) |
Growth Rates
As per the
All
The growth rates assumed for the future are much greater than the actual rates achieved in the same period in the past. Given the fact that average economic growth rates have been higher than those in the past and are expected to continue to be high in the future, high consumption growth rates may be justified. Erring on the positive side may not be as bad as erring on the negative side. CEAs figures do not take into account capacity 10,000-15,000 MW of merchant power and 10,000 MW of captive capacity which may come up by 2020 which could mean that actual capacity additions may exceed targets.
|
1995-1996 |
2003-2004 |
2011-2012 |
CAGR Actual 1993-04 to 2003-04 |
CAGR Projected 2003-04 to 2011-12 |
Electrical Energy Consum-ption in GWh |
277029 |
362799 |
755847 |
3.43 |
9.61 |
355519 |
524299 |
968659 |
4.98 |
7.98 |
|
Energy Require-ment in GWh |
50149 |
75756 |
152746 |
5.29 |
9.16 |
The targets present an optimistic picture of the future but that does not mean that
Concluded
Energy Team, ORF
China’s Approach to Securing its Energy Supplies and Implications (part – II)
(Statement of Mikkal E. Herberg Research Director, Asian Energy Security Program, The National Bureau of Asian Research, before the U.S.-China Economic and Security Review Commission)
Continued from Issue No. 46…
Does
As described above,
At the same time,
However,
In five years
Related to this point, there is a growing sense in
The crude shipped to
In broader foreign policy terms, there also seems to be some recognition that the atmosphere of zero-sum energy competition is creating serious and potentially unnecessary collateral foreign policy disputes with key powers, most importantly the
While there remain suspicions about the long-term energy in intentions of both the
Moreover, there appears to be some growing realization that as China seeks to reassure other world powers that China’s rise will be peaceful and non-threatening to the world, that one area where China can begin demonstrating a more a responsible posture, a “responsible stakeholder”, is in the management of the global energy system.
A final key change that is occurring in
Energy policy has traditionally been heavily supply-side driven, which partly explains the emphasis on accessing oil supplies abroad rather than addressing rapidly rising demand domestically. This is changing rapidly toward an understanding that demand cannot continue to grow on its current trajectory without disastrous environmental, infrastructural, and health consequences. This opens the door widely to a new interest in international cooperation on energy.
The result of all these underlying trends is that there appears to be the beginnings of a sense in
For example,
In recent bilateral meetings with the
It would be premature to say that
Consequently, it is vital that the
Energy, Pipelines, and
China sees its land-based neighbors in Eurasia as key sources of oil and natural gas supplies that can help diversify
For this and many other strategic reasons,
In reality, energy investment and trade have indeed helped cement improving strategic relations between
China also has signed a Strategic Energy Alliance with
Both sides have also recently discussed a potential natural gas pipeline to
However, the Sino-Russian energy relationship has been tortured and fraught with cross-currents of competition, suspicion, and Russian energy policy paralysis and, hence, has done little to bring the two Eurasian powers closer together, yet.
Russia has finally, apparently, begun to build a long-promised oil pipeline from
Second, even where the Kremlin has had unchallenged control of gas resources in Western Siberia, it has failed to follow-through on repeated promises, made as recently as March 2006 by President Putin in Beijing, to build a major West Siberian gas pipeline to China.
In a recent deal
So Sino-Russian energy relations have been rocky, at best, despite the natural strategic resource fit. Over the long-run, however, the logic of more oil and gas moving from
Therefore, in
Most forecasts suggest a range of oil exports from
Most likely combined would be in the 1.5-2.0 MMBD range in 20 years. Alternatively, on current trends, in 20 years
Another small increment of oil imports could avoid the Malacca Straits through a proposed oil pipeline through
Concluded
Courtesy: The National Bureau of Asian Research
NEWS BRIEF
NATIONAL
OIL & GAS
Upstream
ONGC sets up pilot plant to extract helium
May 13, 2008. The Oil and Natural Gas Corporation (ONGC) launched
ONGC insures offshore installations for FY'09
May 9, 2008. ONGC has insured its offshore installations at annual gross premium of $29.025 mn for 2008-09. The premium for the Offshore Package Insurance Policy for the company is almost at the same gross premium as last year despite an overall upward revision of around 32 pc in the insured asset value -- from $15.89 bn to $21 bn. The renewal programme was managed by United India Insurance Company (UIIC), who led the consortium of nationalised insurance companies comprising UIIC, NIAC, OICL and NIC. ONGC policy is reinsurance driven with a major portion of risk being reinsured in International Reinsurance Market and risk retention in the India Insurance Market being 10-13 per cent. ONGC's major critical offshore operational assets -- production complexes, well-head platforms, pipelines, trunklines, drilling rigs, multipurpose support vessels, specialised vessels, third party liabilities and operational risks -- are insured under a comprehensive Energy Offshore Package Insurance Policy for a Combined Single Limit (CSL) of $750 mn for any one accident/one occurrence.
Nelp VII deadline extended to June 30
May 7, 2008. The deadline for submission of bid for oil and gas exploration blocks under the seventh round of the New Exploration and Licensing Policy (Nelp VII) has been extended till June 30 from May 16 as there is still no clarity from the finance ministry on whether gas production is eligible for an income-tax holiday. Bidding for the 57 blocks on offer under Nelp VII was originally supposed to close on April 11. However, this was extended to April 25 and then to May 16. In the Budget 2008-09, the finance ministry proposed to withdraw the tax benefit given to the companies under Section 80 IB (9). The income-tax department's argument is that the tax benefit is meant only for oil production and not for gas. According to the Finance Ministry the decision on the tax holiday would be taken by the various courts and tribunals hearing the issue, which would reach a decision within a year. Oil and gas companies say that due to the lack of clarity on the tax holiday they have not yet been able to firm up their bids. Most companies are preparing two bids — one in a tax holiday scenario and the other in a scenario where the tax holiday is withdrawn. Of the 57 blocks on offer, 39 have been recycled from previous Nelp rounds. These blocks were relinquished by the companies as they did not find any oil or gas or were not able to complete their minimum work programmes on the block.
ONGC`s Bassein output likely to halve by 2012
May 7, 2008. ONGC is likely to see the output from its largest gas field in Mumbai offshore fall to half by 2012 as natural decline sets in the 20-year-old field. Gas production from Bassein and its satellite fields will dip to 5,040 million standard cubic meters (about 13.8 million standard cubic meters a day) in 2011-12 from 10,129 million standard cubic meters (27.5 mmscmd) in 2007-08. The reservoir pressure at the gas field has declined, with continuous production for over 20 years. Bassein field was discovered in 1977, some 80 kms west of Mumbai. When the gas production began in 1988, recoverable reserves were estimated at 226 billion cubic meters (7.98 trillion cubic feet). The reserves are now estimated at about 58 billion cubic meters (2.04 tcf). The Bassein field accounts for 45 per cent of ONGC's gas production. Gas output from the field is estimated at 27.3 mmscmd in the current year and will fall to 22.75 mmscmd in 2009-10 and to 17.7 mmscmd in 2010-11.
The gas production from Mumbai High will decline from 5,328 million standard cubic meters (14.59 mmscmd) in 2007-08 to 3,188 million standard cubic meters (8.7 mmscmd) in 2011-12, while the output from Neerlam, Heera and B-173 fields would dip from 2.7 mmscmd to 2.06 mmscmd. ONGC expects to make up some of the decline by operationalizing new and marginal fields that will produce one mmscmd gas in the current year and scale it up to 13 mmscmd in 2011-12. Meanwhile, ONGC has decided to invest Rs 35.7 billion to maintain oil and gas production from its existing fields. The state-run exploration company also made seven new oil and natural gas discoveries last month. Three of the new discoveries are from exploratory wells and four new pools from development wells. Most of ONGC's producing fields have matured and are now depleting, forcing the company to undertake major revamping to maintain hydrocarbon production.
High crude prices puts brakes on ONGC's retail plans
May 13, 2008. Following the Government’s decision to compensate only IndianOil, Hindustan Petroleum and Bharat Petroleum for under recoveries, the Oil and Natural Gas Corporation has put its retail outlet plans (under the brand OVAL) on the backburner. Originally, ONGC was permitted to have 1,100 retail stations, while its subsidiary MRPL (Mangalore Refinery and Petrochemicals Ltd) was approved 500 outlets. Currently, ONGC has only one outlet, which is run on a trial basis at Mangalore. The company is of the view that with the crude oil prices soaring, the company would incur losses by opening more outlets.These comments come on the back of RIL closing down its fuel stations to offset the rising losses. Opening fuel stations is not commercially viable because the government compensates only oil marketing firms such as Indian Oil Corporation, Hindustan Petroleum Corporation and Bharat Petroleum for under-recoveries. Under-recoveries are the losses incurred by oil companies for selling fuel at subsidised prices.
RIL, Essar Oil eye
May 8, 2008. After the UK-based Hinduja group, ONGC’s proposed Rs 26,500-crore ($6.3 bn) refinery at
According to RIL the petrochemical plant will add value as the petrochemicals margins are expected to remain strong till the end of 2013. and it expects the margins to remain positive even during the expected downturn in the petrochemical industry after 2013. ONGC has, however, sought incentives worth Rs 16,000 crore ($3.8 bn) from the Andhra Pradesh government over eight years to make the refinery financially viable. ONGC wants exemption from sales tax on the sale of petroleum and petrochemical products, free power and water supply during the construction phase, and road and rail connectivity. ONGC, which has often been asked by the petroleum ministry to focus on its core business of exploration and production, says that it is only the incentives, along with the petrochemical plant, which will make the refinery feasible. The Andhra Pradesh government, however, has been lobbying with the central government saying the refinery is feasible.
Transportation / Trade
GAIL to buy spot LNG cargo
May 13, 2008. Indian gas firm GAIL India plans to buy five to six liquefied natural gas (LNG) cargoes from the spot market in the last quarter of fiscal 2008/09 to fire its Dabhol power plant. GAIL’s 5 million tonne (mt) LNG terminal will be mechanically ready by September-October, and will be ready to receive LNG cargoes during January-March.The company would float a tender to buy the LNG and each cargo would have 135,000 cubic metres of gas.
MOL picks 35 pc stake in ONGC
May 9, 2008. Budapest-based MOL Hungarian Oil and Gas Plc has taken a 35 per cent stake in Oil and Natural Gas Corporation's onshore exploration block in the Himalayan foothills. MOL will take stake in block HF-ONN-2001/1. Block HF-ONN-2001/1 that ONGC had won in the third round of bidding under New Exploration Licensing Policy (NELP) has an aerial extent of 1,513 square kilometres. MOL has experience of working geologically complex fold belt areas in similar geological setting in
Reliance ready to offer market value for land use
May 9, 2008. Reliance Gas Transportation and Infrastructure Company (RGTIL) informed the Supreme Court that it was ready to compensate farmers at market rate for right to use land for laying a pipeline to transport natural gas from Krishna-Godavari basin to
MRPL set to seal 0.25 mt
May 7, 2008. Indian refiner MRPL will soon conclude a deal to sell 250,000 tonnes of diesel to
Policy / Performance
SC stays ONGC bidding process on B-22 oil field
May 13, 2008. In a relief to construction major Larsen and Toubro, the Supreme Court stayed the Delhi High Court order that directed ONGC to consider Malaysia-based Ramunia Fabricators Sdn Bhds' bid for development of B-22 oil field in Mumbai offshore. The court while issuing notice to ONGC, Ramunia Fabricators and its Hong Kong-based subsidiary also restrained the state-run exploration major from taking any action in considering the bid. L&T alleged that the High Court should not have asked the state-run exploration major to consider Ramunia's bid despite the fact that it violated the mandatory and essential terms of the tender. According to Larsen and Toubro (L&T) while Malaysia-based Ramunia Fabricators Sdn Bhd had submitted its bid pursuant to ONGC's decision to invite bids in May 2007 for its B-22 field development project, the tender documents were submitted by its
Govt stand differs on pricing of RIL gas to RNRL, NTPC
May 13, 2008. The government has adopted a dual stand on gas sales from Reliance Industries (RIL’s) Krishna Godavari (KG) basin to Reliance Natural Resources (RNRL) and the sales to its own company NTPC. In a rejoinder filed in the Bombay High Court for the ongoing RNRL-RIL case seeking vacation of the stay on Mukesh Ambani-run Reliance Industries for selling gas to third parties, the government has said that the price fixed in the year 2004 cannot be taken as the basis for the prevailing price and it has no approval of the government. The same rejoinder also states that as far as NTPC-RIL case is concerned, the government is only concerned with the valuation of the gas sold at which government entitlements, royalty, profit petroleum and taxes will be determined. This rejoinder was filed with respect to RNRL’s reply stating that government has no role in the gas settlement dispute between RIL and RNRL. The government had earlier filed an application for being a party to the case between RIL and RNRL on April 28. The government’s rejoinder raises serious doubts over NTPC getting gas at $2.34 per mmbtu from RIL because in 2006, the government had rejected RIL’s proposal to sell gas to RNRL at price of $2.34 per mmbtu. This was the price at which RIL agreed to sell gas to NTPC through an international competitive bidding (ICB) in 2004. The government rejected RIL-RNRL gas deal stating it was not an arms length contract and the price was not arrived through ICB. In 2007, the government approved a benchmark price for sale of gas at $4.2 per mmbtu. NTPC will lose close to Rs 20,000 crore ($5 bn) if it has to buy gas at government approved price of $4.2 per mmbtu against $2.34 per mmbtu at which it entered into contract with RIL through ICB in 2004. RIL-NTPC case in Mumbai High Court is not over pricing but over the cap on liability clause. The RNRL-RIL case will come up for hearing on July 22 and the Bombay High Court has maintained status quo in the long-drawn out legal battle till then.
‘No fresh oil bonds, but no fuel price rise’: Deora
May 13, 2008. Petroleum and Natural Gas Minister Murli Deora indicated there will be no hike in petro products prices for now, though the finance ministry had rejected his demand to issue fresh oil bonds to counteract the losses of state oil companies due to global rising oil prices. Deora met Finance Minister P. Chidambaram to seek issue of oil bonds worth Rs.440 billion, amounting to 57.1 percent of the Rs.770 billion losses incurred by the state-run oil marketing companies during 2007-08. The central government currently issues bonds for 42.7 percent of the oil firms' losses, with another 33 percent coming from upstream oil companies.
Branded petrol, diesel price to rise
May 12, 2008. The government has asked oil companies to raise prices of branded petrol and diesel substantially and introduce non-subsidised premium cooking gas for those who can pay. Oil companies have also been advised to diversify their crude oil portfolio to save money on imports of the raw material as an immediate measure to shield themselves from rising global crude prices. The government may also consider a marginal hike in auto fuel prices after inflation calms down. The government is closely monitoring pricing of sensitive petroleum products (petrol, diesel, PDS kerosene and domestic LPG). A price hike is difficult unless inflation is tamed. But in a scenario where crude has crossed $125/barrel mark, highly subsidised fuel supply could not be sustained for long. According to official estimates, a 10% price increase of the four sensitive petroleum products is likely to impact the wholesale price index (WPI) by 171 basis points. Public sector oil marketing companies (OMCs) have also been asked to increase prices of branded petrol and diesel. Branded fuel market of petrol and diesel together is about 17%. It is being argued that most city consumers have ability to pay and they would not mind paying Rs 5-10 extra. Prices of branded fuels are not regulated by the government. They currently attract a premium of Rs 2-3/litre more than the normal petrol (Rs 45.52/litre in
‘High oil prices could slow down economic growth’: Rangarajan
May 12, 2008. Rising global crude oil prices could slow down the country’s economic growth in 2008-09 to between 8-8.5 per cent, the Chairman of the Prime Minister’s Economic Advisory Council, Dr C. Rangarajan, has said. This estimate is lower than the 8.5 per cent growth projected for 2008-09 by the Advisory Council in January this year. According to Dr Rangarajan, the country, for the time being, would still be “shielded away” from high international oil prices but this is perhaps not the best moment to make the adjustment.
‘Negotiate gas contracts by strengthening political ties’: ASSOCHAM
May 11, 2008. India's natural gas requirement is likely to swell to over 120 BCM by 2015, the year in which most of gas producing country’s will have expired their supplies contracts with Asian gas guzzlers and thus it is suggested that India further tightens its diplomatic ties with gas producing nations to ensure that adequate gas supplies are hedged for India even with higher prices, according to the Associated Chambers of Commerce and Industry of India (ASSOCHAM). The price suggested by the industry chamber for securing long term gas contracts should be within the range of US$12-14 per MMBtu, since most of Asian gas buyer have aggressively started negotiating long term gas deal with gas producing nations. Currently the spot gas price at which
Petroleum imports outpace exports
May 8, 2008. Rising export of petroleum products helped Commerce Ministry meet 96 per cent of the targeted $160 billion worth of exports in 2007-08, but it could not contain the country's net oil import bill. The net oil import bill in 2007-08 is likely to rise by around 41 per cent over 2006-07 as the country's refineries consumed 9 per cent more crude oil to meet surging demand even as crude oil prices rose nearly 53 per cent during the year. The net oil import bill (import of crude oil and oil products minus export of oil products) rose to around $63.52 billion in 2007-08 compared with $45.05 billion in 2006-07. The overall oil import bill rose by nearly 38 per cent to $90.02 billion compared with $65.08 billion in 2006-07. The country's crude oil import bill rose to $77.02 billion in 2007-08, 40 per cent over $54.99 billion in 2006-07. The price of crude oil rose from around $67 per barrel in April 2007 to over $103 per barrel in March 2008.
POWER
Generation
Bhel to build coal-based power plant
May 13 2008. State-run Bharat Heavy Electricals would set up Integrated Coal Gasification Combined Cycle (IGCC) power plant at Vijaywada with Andhra Pradesh Power Generation Corporation (APGenco). Bhel has signed a Memorandum of Understanding with APGenco to set up country's biggest 125 MW IGCC power plant at Vijaywada. Bhel has earmarked on several initiatives to meet the growing demands of the country's power sector.The company is confident of meeting the capacity addition targets for the Eleventh Plan period. Bhel plans to increase its power equipment manufacturing capacity from 10,000 MW to 15,000 MW per annum by 2009.
Videocon to foray into hydropower
May 13, 2008. After foraying into thermal power sector, Videocon Industries said the group is sewing up plans to enter into hydropower. The company is in talks with the Uttarakhand government for various projects. The company is interested in the hydropower and hotel sectors, and is ready to invest in Uttarakhand. As far as hydropower is concerned, Videocon expects to produce nearly 2,000 mw in the first phase of the plan. Already, company has held talks with the top state government authorities. The company has also held talks with the Uttarakhand Power Corporation (UPCL) for selling the power. The company is identifying various sites for hydropower in Uttarakhand. Videocon recently came up with a proposal to set up a thermal power plant in the
PCBL sign agreement for
May 12, 2008. Phillips Carbon Black Ltd (PCBL) has signed a joint venture with subsidiaries of Vietnam National Chemical Corp for setting up a carbon black facility of 1,00,000 MT and co-generation of 16 MW of power in phases in Vietnam. The
Phase-2 of Simhadri power plant by 2011
May 12, 2008. According to the power generation major, NTPC, the phase two of the Simhadri thermal power plant of the NTPC, adding two more units of 500 MW each, will be completed by 2011 and the additional power will be shared among the southern States. NTPC has currently 1,000 MW being generated by the plant was being allocated exclusively for Andhra Pradesh.
NTPC had not yet been decided in what ratio the additional power (1,000 MW) should be distributed among the southern States. During 2007-08 the Simhadri power plant had generated 7,779.66 million units at a plant load factor of 88.57 per cent. During the financial year, the NTPC southern region had achieved a total generation of 30,088.940 million units and the NTPC Ramagundam in Andhra Pradesh had achieved 2,0587.668 MUs at a plant load factor of 90.14 per cent. It was the highest ever power generation at Ramagundam.
During the year, the power station at Kayamkulam had achieved generation of 1,721.546 MUs at a plant load factor of 54.51 per cent against the MoU target of 1,200 MUs. According to the company the Ramagundam station had achieved 60.82 per cent (28.75 lakh tonnes) of ash utilisation against the target of 26.86 lakh tonnes. Simhadri station had achieved 70.54 per cent (16.25 lakh tonnes) against a target of 13.54 lakh tonnes.
Tata Power to take all safety measures in Orissa plant
May 11, 2008. Optimistic about completion of land acquisition for its 1,000 MW power plant near
1,000 MW power project in J&K soon
May 9, 2008. According to the Union Power Ministry the power starved Jammu & Kashmir would get a 1,000 MW thermal power project shortly to cater to the demand of power during the winter months when electricity generation goes very low in the state. With the operation of this project, J&K would not be facing power crisis during the winters, when water level goes very low in the snow-fed rivers, badly affecting the electricity generation. The ministry said that a memorandum of understanding (MoU) between the power ministry and the state government on construction of three more power projects over
Toshiba, JSW to set up JV for power equipment
May 8, 2008. Japanese electronics and electrical maker Toshiba Corporation has teamed up with the OP Jindal-promoted JSW Group to establish a joint venture company in
The joint venture, to be established by June 2008, will manufacture and market medium-to-large steam turbines and generators ranging from 500 mw to 1,000 mw. The venture will have an initial capitalisation of $50 mn (Rs 210 crore). Toshiba will hold a stake of 75 per cent, JSW Energy will own 20 per cent and group company JSW Steel hold the remaining share. The operations are expected to begin in September 2009.
As per JSW Energy the alliance is aimed at giving us an advantage in the domestic energy sector and capitalising on the growing electricity demand. The company was talking to multiple Indian companies for foraying into the power generation equipment manufacturing space in
Bhel to invest $240 mn in Tiruchi plant
May 8, 2008. State-run power equipment-maker Bharat Heavy Electricals Ltd (Bhel) would invest Rs 1,000 crore ($239.5 mn) in its Tiruchi plant in the current fiscal to increase boiler capacity from 5,750 MW to 10,000 MW by June-July '09. The current order book of Tiruchi plant stands at Rs 7,200 crore ($1.7 bn), and the company is of the view that it would take this figure to Rs 17,000 crore ($4 bn) in three years time. Bhel also plans to form joint venture with Tamil Nadu Electricity Board (TNEB) to build boilers, in which it would have 26 per cent stake.
The company has signed a Memorandum of Understanding with TNEB to form joint venture. The company is contemplating more joint ventures with other state electricity boards. The company has already designed 800 MW boiler, but the order for the same are yet to be placed. Bhel and country's largest power producer NTPC Ltd formed 50:50 joint venture on April 29 last month to carry out engineering construction procurement contracts for power plants and infrastructure projects manufacture and supply equipments in
Transmission / Distribution / Trade
Jyoti bags $7 mn order from Aravali Power
May 13, 2008. Jyoti has received a turnkey order from Aravali Power Co, for design, engineering, supply, erection, testing and commissioning of cooling water system and make up water system for Indira Gandhi super thermal power plant - Jhajjar (3x500 MW). Aravali Power is a joint venture between NTPC, HPGCL and IPGCL. Jyoti has associated itself with Hyosung Ebara Co,
Power situation improves in TN
May 13, 2008. According to the Tamil Nadu ministry for power, the government would soon lift restrictions on power usage clamped on the industries as the power supply situation has improved in the state. The ministry said that the state would need Rs 2,000 crore ($475.3 mn) in excess to install additional transformers and feeders. The power situation had improved in the state since wind mills had started generating the energy from April 27 this year against the routine availability commencing in the second fortnight of May every year. The recent generation was to the tune of 1,000 Mw to 1,500 Mw and therefore the state was not to purchase power from the neighboring states.
KEC International bags $27 mn PGCIL order
May 13, 2008. KEC International has bagged a contract valued at Rs 111.41 crore ($26.5 mn) from Power Grid Corporation of
JSPL stops power supply to industrial park
May 10, 2008. The fate of as many as 32 industrial units in the OP Jindal Industrial Park hangs in the balance after Jindal Steel and Power Ltd (JSPL) today stopped power supply following the decision of the Appellate Tribunal for Electricity to cancel the distribution licence granted to the company. The tribunal's decision came as a big setback for JSPL, which was planning to develop the industrial park as a model. The firm is also taking up a major expansion plan to step up its steel capacity to 5 million tonne per annum by 2011. The Chhattisgarh State Electricity Regulatory Commission (CSERC) had granted distribution licence to JSPL on November 29, 2005, for supplying power to the industrial park spread over 750 acres. The company was supplying power from its captive power plant at the rate of Rs 2.50 per unit.
According to company, the park was set up after the company sealed a pact with the Chhattisgarh government on October 23, 2002. The state government granted permission for supplying power to the industrial units on January 29, 2003, while the state-run Chhattisgarh State Electricity Board (CSEB) gave permission for construction of transmission line for supply of power to the industrial park on May 31, 2003. All these permissions were granted before the Electricity Act, 2003, came into effect in the state. The company applied to the CSERC for the distribution licence according to the provisions of the Electricity Act, 2003.
CSEB, however, vehemently opposed, despite having earlier given permission for laying transmission line for supplying power to the industrial park. CSERC finally granted distribution licence to the JSPL. CSEB filed an appeal before the Appellate Tribunal for Electricity. The Tribunal pronounced judgment in JSPL's favour on May 11, 2006. CSEB later moved to the apex court to challenge the tribunal's verdict. The Supreme Court referred the matter back to the Tribunal, which, on May 7, 2008, cancelled the distribution licence granted to the company.
Tata Power eyes shipping biz
May 7, 2008. Tata Power plans to foray into shipping. The company will invest $500 mn through its Singapore-based special purpose vehicle, TPC Energy Asia, to prepare a fleet of nine vessels to transport coal from
Most of the new capacity being added by the country's largest private sector electricity generator will be fuelled by imported coal, largely from
Tata Power's main business is electricity generation and bulk supply for the Mumbai metropolitan area, which is regulated by the Maharashtra Electricity Regulatory Commission. The company is setting up a 4,000 mw ultra mega power project at Mundra in
Haldia Petro buys out L&T in power JV
May 7, 2008. Haldia Petrochemicals Ltd (HPL) had acquired Larsen & Toubro's 51 per cent stake in Rs 133 crore ($32.2 mn) HPL Cogeneration Ltd (HPLCL), the joint venture for captive power supply to HPL, for an estimated Rs 180 crore ($43.5 mn). The buy-out came at a time when the company was operating in adverse circumstances, with the bottomline under great pressure. The 10-year joint venture produced 116MW for HPL's operations. HPL planned to invest in HPLCL to improve the energy efficiency of the plant by utilising alternative feedstock that matched its expansion plans. It could use mixed gases in place of naphtha for power generation. The company currently used 70MW power from HPLCL. Its energy requirements were estimated to rise post its 30 per cent capacity expansion project that is likely to be commissioned by end of 2008. The total installed capacity will be 1.7 million tonnes per annum after expansion.
Power sector raises $2 bn in foreign aid
May 13, 2008. The Indian power sector tied up external assistance of Rs85bn (over $2.1 bn) from multilateral bilateral agencies such as World Bank, Asian Development Bank, Japan Bank of International Co-operation and KfW (Germany) in the year 2007-08 despite a very limited basket and stiff competition from projects in other sectors as well as from other developing countries. Agreements in respect of nine power projects spanning across power generation, transmission and distribution were signed. Thus, a record growth of 175% over the previous year has been achieved, demonstrating conclusively a perceptible change in the risk perception of these agencies in respect of the Indian power sector. In the year 2006-07, agreements for four power projects with aggregate external assistance of Rs31bn (US$775mn) were signed. The projects sanctioned during 2007-08 were: Rampur HEP/SJVNL(WB), PSDP-IV/PGCIL(WB), Power Sector Transmission-IV/PGCIL(ADB), M.P. Power investment-I/MPPTCL(ADB), M.P. Power investment-II/East DISCOM(ADB), M.P. Power investment-III/MPPTCL(ADB), M.P. Power investment-IV/E,W,C DISCOM(ADB), Maharashtra Transmission system (JBIC), EHV Transmission system in Haryana/REC(JBIC). On its part, the Government boosted absorption of developmental external assistance in power sector. During 2007-08, the utilization of external assistance in 23 power projects in central and state sectors was Rs28.30bn which is about 18% higher than the utilization of Rs24.08bn in these projects during 2006-07. Engagement of Multilateral/Bilateral agencies in Indian power sector has, thus, increased manifold in the recent past. These agencies are instrumental in providing long term developmental financial assistance to specific projects in central and state sectors on highly competitive terms & conditions.
Himachal hydel power PSU gets mini ratna status
May 13, 2008. 'SJVNL has been conferred the prestigious status of mini ratna category 1 within only four years of coming into operation. The 'mini ratna' status grants enhanced autonomy and delegation of financial powers to profit making companies to make them more efficient and competitive. SJVNL has built and now runs the country's largest hydel project - the 1,500 MW Nathpa Jhakri project. During the last fiscal year the project generated a record 6,432 million units of energy. This energy is supplied to the power hungry northern grid. The company is currently in the process of building the 412 MW Rampur project at a cost of Rs.20.47 billion. This project also falls in the
NTPC eyeing stakes in
May 12, 2008. NTPC Ltd,
REC,
May 8, 2008. Rural Electrification Corporation (REC) and Damodar Valley Corporation may come together to form a joint venture for buying coal mines abroad. REC has got a proposal from DVC for a joint venture to buy coal mines abroad. It is at a very preliminary stage. REC has already signed MoU with IDFC and they will invest Rs 150 crore ($36 mn) each in the joint venture that will take up consultancy and funding of power distribution projects.
'Govt investing heavily in uranium exploration': DAE
May 11, 2008. According to the Department of Atomic Energy (DAE) to ensure that the country's nuclear programme is not dependent on the implementation of the Indo- US civil nuclear deal, the government is investing heavily in uranium exploration. Rajasthan, Andhra Pradesh, Karnataka, Meghalaya and other regions are among those DAE is looking at for uranium exploration. Approximately Rs 700 crore ($168.3 mn) is being invested in using the latest technology to explore multiple states for uranium. The DAE is of the view that as it is making massive investment in uranium exploration and if it hits a huge find then the problem is over. According to the DAE currently the country has four uranium mines, all of which are located in Jharkhand. However, nuclear power plants in the country have been reportedly functioning at half the capacity due to lack of uranium, a radioactive metallic chemical element used as a fuel in nuclear reactors. Uranium plays a crucial role in
GMDC looks for coal mine partners in
May 11, 2008. After the Adani Group’s foray into
Govt Okays $2 bn FDI in Essar Power
May 10, 2008. The government has approved Essar Power’s proposal to infuse up to Rs 8,000 crore ($1.9 bn) as foreign equity in the company for undertaking various downstream projects, including power and coal mining. The proposal has already been cleared by the Foreign Investment Promotion Board (FIPB). Since the investment inflows have exceeded Rs 600 crore ($144.2 mn), the proposal needed to be cleared by the Cabinet Committee on Economic Affairs (CCEA). The FDI would be in the form of equity from Essar Power Holdings (EPHL), a foreign entity which is part of the Essar Group and is incorporated in
Govt to usher in power reforms
May 9, 2008. The government is soon going to introduce the revised Accelerated Power Development and Reforms Programme (APDRP Phase II). The new Rs 50,000-crore ($12 bn) APDRP scheme plans to bring the Aggregate Technical and Commercial (AT&C) losses to less than 15 per cent by the end of 11th Five Year Plan in the urban and high population density areas. According to the ministry it should reduce the distribution losses to 10 per cent. According to the Power Ministry, overall AT&C losses are around 35 per cent against about 39 per cent in 2001-02. The government had approved APDRP in March 2003 to accelerate distribution sector reforms. Besides reducing AT&C losses, the scheme seeks to bring commercial viability in the power sector and reduce outages and interruptions. Under the scheme, the government provides 50 per cent central assistance for strengthening and upgrading sub-transmission and distribution network. Finance Ministry has earmarked an annual budgetary support of Rs 800 crore ($192.6 mn) under the APDRP scheme in the Union Budget 2008-09.
Govt may relax rules for power plants in SEZs
May 8 2008. The government is considering relaxing or diluting rules that prevent power plants in special economic zones, or SEZs, from selling power outside such zones without paying significant extra taxes and levies, in an attempt to meet growing demand for power in a rapidly expanding economy. The move will likely benefit customers, but will put power plants outside such zones at a disadvantage. That is because units, including power plants, located in SEZs are eligible for a range of fiscal incentives that lower their production and operating costs. This means power plants located in SEZs can sell power at a lower price than those located elsewhere. Existing rules take this factor into account and say that power generated within an SEZ “may be transferred to domestic tariff area on payment of duty on consumables and raw materials used for generation of power”. The rules add that these units will also have to pay extra taxes, including basic customs duties, countervailing duties (to offset against the domestic excise and sales tax levies) and a special additional duty (4%) to make up for the fiscal incentives. It is these rules that the government now wants to relax or dilute. Discussions are on among the ministries of commerce, power and finance on firming up the regulations under which power plants located at these zones should function. Once the basic issues are sorted out, a proposal may be sent to the Union cabinet for clearance. These SEZs would help utilities (power generation firms) cut down their costs and, thereby, bring down power tariffs in the country. As per the proposal, these power units should be allowed to supply power to the domestic tariff area where the SEZ is based by paying reduced duties. The idea is to frame a comprehensive policy for setting up SEZs specifically for the power sector. The power generated within these SEZs will be treated as merchant power.
Centre ups e-sale quota of coal by 5 times
May 8, 2008. The Union ministry of coal has directed all the state governments to indicate the exact requirement of coal by the small and medium scale industries in the respective states, so that new coal distribution centers can be set up to help the SMEs. According to Union ministry for coal it is ready to set up as many distribution centers closer to the user groups as per the recommendation of the state governments. However, till now none of the states have come forward with their requirement of coal. The ministry has recently increased the coal allotment quota under e-sale system by five times from the present 3 million tonne per month to 15 mt per month. From now on, SMEs will be supplied coal at a rate on par with big industries.
INTERNATIONAL
OIL & GAS
Upstream
Dana makes oil discovery at East Rinnes
May 12, 2008. Dana Petroleum announced the discovery of the East Rinnes Oil Field in Block 210/24a in the UK Northern North Sea. The Company reported finding the West Rinnes oil accumulation, just 5 kilometers from the Dana operated
Oil search signs Kurdistan PSC
May 12, 2008. Oil Search Limited has signed a Production Sharing Contract (PSC) for the 632 square kilometer Shakal Block with the Kurdistan Regional Government (KRG) in
OPEC Output Down for April
May 9, 2008. The 13 members of the Organization of Petroleum Exporting Countries (OPEC) pumped an average 31.87 million barrels per day (b/d) of crude oil in April, a 350,000 b/d decrease from March, according to a Platts survey of OPEC. The sharp drop was largely the result of steep output losses in
Shell to Start Output at
May 8, 2008. Royal Dutch Shell PLC (RDSA) next year will start producing from heavy oil fields in the BC-10 block in
StatoilHydro makes gas discovery on Alve
May 8, 2008. StatoilHydro has confirmed the existence of gas and condensate on the Alve field in the
Devon's increased production in Q1 ups sales 52 pc
May 7, 2008. Devon Energy reported that combined oil, gas and natural gas liquids production from continuing operations averaged 640 thousand oil-equivalent barrels (Boe) per day in the first quarter of 2008. This was a nine percent increase in production from continuing operations compared with the first quarter of 2007. The production growth was concentrated in onshore fields within the
Downstream
Vietnam breaks ground on $6 bn refinery
May 12, 2008.
Korean, Japanese firms win contracts for Kuwaiti refinery
May 12, 2008. Four South Korean and a Japanese firm were declared winners of four major contracts worth billions of dollars to build a new refinery in
Venezuela to own 49 pc of Petroecuador refinery
May 12, 2008. Petroleos de Venezuela, or PdVSA, will have 49% of the shares in the Refineria del Pacifico-CEM, a company that will be established with Petroecuador to build a new refinery for heavy crude. Petroecuador will hold 51% of the company's shares. The refinery would process around 300,000 barrels of heavy crude a day and could require at least a $4 bn investment. Refineria del Pacifico will choose a construction company for the new refinery. The construction company chosen will be expected to finance 70% of the refinery's cost and the remaining 30% will be financed by PdVSA and Petroecuador. The new refinery project is important for
CNPC aims to account for 40 pc of
May 8, 2008. China National Petroleum Corp. (CNPC) intends to build six ten-million-ton oil refinery bases by 2010. With a processing capacity of 160 million tons annually, these bases would account for 40% of the nation's total oil refining capacity. The oil producer also projected to build up 18 ten-million-ton oil refinery bases by 2020, which would have a yearly production capacity of 300 million tons (including 150 million tons for sour crude oil), amounting to 45% of the nation's total. Unlike China Petrochemical Corp., which is more sensitive to the fluctuating prices of crude oil in the global market, CNPC can support 83% of crude oil by itself. Up till now, CNPC has the nation's biggest refinery that has a production capacity of 20.5 million tons in
Transportation / Trade
Abu Dhabi to invest $25 bn in gas processing & pipelines
May 12, 2008. State-controlled Abu Dhabi Gas Industries (Gasco) is investing about $25 billion in gas-processing plants and pipelines as it develops more fields to meet surging demand. Two major gas-processing plants and around 10 new onshore gas pipelines covering a total of 1,500 kilometres are being built in and around
Peru leans toward Mountain gas pipeline route
May 12, 2008. High-level government officials are signaling that
Magellan plans
May 12, 2008. Magellan Midstream Partners, L.P. (MMP) plans to invest $240 mn to build energy infrastructure in
North West shelf LNG confirms sales agreement with
May 9, 2008. The North West Shelf LNG Venture sellers confirm that following the signing of a binding Heads of Agreement a Sales and Purchase Agreement (SPA) has now been executed with
Petrobras' Gasene pipeline project enters final stretch
May 9, 2008. State-run oil firm Petroleo Brasileiro SA (PBR), or Petrobras, expects the construction of a gas pipeline linking
Fresno
May 9, 2008. The dry
Policy / Performance
Serbian cabinet agrees to sell refinery to Gazprom
May 12, 2008. Serbian cabinet ministers approved an oil and gas deal with
First Sino-foreign refinery posts heavy losses, seeks govt support
May 12, 2008. Dalian West Pacific Petrochemical Co Ltd, whose investors include PetroChina, Total and Sinochem, has suffered heavy losses due to soaring crude costs and caps on domestic fuel prices, the Caijing magazine reported. According to the company the refinery, the first such Sino-foreign project in China, posted losses of over 1 bn yuan since the beginning of the year, the report said, citing a company official. The Dalian refinery, which was originally allowed to export half of its output, has had difficulty obtaining export licenses, with the government restricting outbound shipments to meet strong domestic demand, the official was quoted as saying. The company is seeking government action to stem the losses, including the sale of diesel at prices in line with international market, the report said.
Bangladesh unable to ensure gas to Tata
May 10, 2008.
Morocco reveals strategy to explore oil amid spiking oil prices
May 9, 2008.
Norway announces APA 2008
May 9, 2008. The Norwegian Ministry of Petroleum and Energy has announced the Awards in Predefined Areas (APA) 2008. With this announcement prospective blocks for exploration activities in mature areas of the Norwegian Continental Shelf (NCS) are being made available to the industry. In APA 2008 the predefined area has been extended with 4 blocks in the Barents Sea, 3 blocks in the Norwegian Sea and 11 blocks in the
Australia awards $425 mn in offshore permits
May 9, 2008. The Australian Ministry for Resources and Energy has awarded nine exploration permits representing a $425 mn investment in
POWER
Tenaska sells power plants to International Power
May 12, 2008. Tenaska Capital Management has agreed to sell four power plants to London-based International Power for more than $856 mn. The plants are in
TransCanada,
May 12, 2008. TransCanada Corp jumped into the high-growth western
Transmission / Distribution / Trade
South Africans electricity usage reduced by 7 percent: Eskom
May 13, 2008. According to the Eskom, South Africans had managed to save up to 7 percent in electricity demand last month. According to the Presidential Special Joint Working group, Load shedding has been suspended on the basis of progress towards meeting the 10 percent savings target and reviewing the most effective approach in achieving sustained savings. It was agreed that an Advisory Council chaired by the President, Thabo Mbeki, will soon be formed to provide implementation of the National Electricity Response Plan. Members of the Council will be leaders from labour, business, government and civil society.
China to build Qinghai-Tibet electricity transmission line
May 10, 2008.
The transmission line, dubbed as "Qinghai-Tibet electricity route", is a 500KV power transmission line, with the first phase project target of transmitting 6.5 billion kwh annually. The project is expected to be completed and go into operation in 2010. The planned project will be the world's first electricity transmission line above the 5,000 meter altitude. The Xibei Electric Power Design Institute has concentrated on anti-permafrost research in preparation for the project construction, which is expected to be finished in June or July this year. The project can transmit thermal power to meet
Policy / Performance
Ukraine ready to export electricity to Lithuania
May 13, 2008.
Victoria seeks brown coal opportunities with
May 12, 2008.
But
Brown coal is not suited for deep underground mining, but for opencast mining (extracting coal from seams at shallow depth), a technique with which
At least 40 developing countries want nuclear power programs
May 12, 2008. At least 40 developing countries, from the Persian Gulf region to
Much of the new interest is driven by economic considerations, particularly the soaring cost of fossil fuels. According to the U.S. and international nuclear officials for some Middle Eastern states with ready access to huge stocks of oil or natural gas, such as Kuwait, Saudi Arabia and the United Arab Emirates, the investment in nuclear power appears to be linked partly to concerns about a future regional arms race stoked in part by Iran’s alleged interest in such an arsenal.
Although the
‘Coal-fired power plants pose risks to health’: WHO
May 11, 2008. The World Health Organisation (WHO) said that climate change poses significant health risks and called for lessening reliance on coal-fired power generation. According to a WHO report, a drop in coal-fired power generation will reduce air pollution and associated diseases and deaths. It called for changing the mode of transport and promoting bicycling and walking to reduce pollution and traffic-related injuries and deaths. Production and transportation of food are major emitters of greenhouse gases, the report said. The report said that global warming would be gradual, but the increasing frequency and severity of extreme weather events, such as storms, heatwaves, droughts and floods, would be abrupt and the consequences would be acute.
Chinese eyeing NSW electricity industry
May 9, 2008.
Renewable Energy Trends
National
GPEC gets $106 mn ADB loan for wind energy projects
May 13, 2008. Gujarat Paguthan Energy Corporation’s (GPEC) wind energy projects in Gujarat and Karnataka will get a loan of up to Rs 445 crore ($105.8 mn) from Asian Development Bank. The bank has given an in-principle approval for the loan which will be used to set up wind farms at Samana in
Coir body for ban on use of coconut husk for power production
May 12, 2008. The Tamil Nadu State Coir Associations' Federation demanded a total ban on use of coconut husk to generate biomass power. The Association is of the view that it will badly hit the labour intensive coir industry and throw hundreds of people out of job.the Association said the government should initiate action against industries using coconut husk for biomass power generation. The Association also requested the central and state governments to provide financial and tehnical assistance for value addition and marketing of coir products. As per the Association the biomass power generation was a threat to the 2.5 lakh coir workers.
NTPC to set up R&D fund
May 12, 2008. NTPC has decided to allocate 0.5% of distributable profit annually for its “Research and Development Fund for Sustainable Energy”. This fund will be used for sponsoring / undertaking research leading to development of green and clean technologies. The research project may include development of Coal Gasification Technology for commercial use, reducing cost of harnessing Solar Energy, LED lighting, improvement in efficiency of its power stations, etc. As a responsible Corporate Citizen, NTPC is committed to controlling CO2 per unit of power generation with portfolio management, adoption of the state of the art technology with special thrust on the renewable energy sources, develop one million square feet of Green Building Space within NTPC premises by the year 2017, spearhead awareness campaigns nation wide to orient the people, strengthen and leverage the Government’s efforts in this area. With its priority of generating clean power, the long-term focus areas of NTPC shall cover re-powering and replacement of old units, introduction of ultra super critical technology, modifying the fuel portfolio with higher share of renewable, clean coal technologies. The company is undertaking massive afforestation covering vast areas of land in and around its projects and till date it has planted more than 18.37 million trees at its projects. As a result of pursuing sound environment management systems and practices, all NTPC stations have been certified with ISO 14001 and OHSAS 18001 by reputed national and international certifying agencies.
US group Astonfield lines up mega investments
May 10, 2008. US-based Astonfield group of companies has decided to invest Rs 16,000 crore ($3.8 bn) to set up green energy capacities in India, a solar panel manufacturing unit in West Bengal and a WiMax network in rural India. Plans include setting up of renewal generation capacities of 2,000 mw at an investment of Rs 8,000 crore ($1.9 bn) approximately and a solar panel assembly plant at a capex of Rs 6,000 crore over the next two-three years. The Wimax network will be rolled out at an investment of $500 mn. It also plans to approach the equity market with an IPO in 2009. In
Nandan plans eco-zones to make bio-fuel
May 9, 2008. Nandan Biomatrix, a Hyderabad-based agri-biotechnology and medicinal plantation company, is planning to set up bioinvestment eco-industrial zones (BIEZs) across the country. The project aims to bring fallow land under Jatropha cultivation, which will be used to make biofuel. BIEZs would work to achieve energy efficiency. The zones will have farms and laboratories for mass production of plantlets along with nursery production centres, demonstration areas and training centres. It will follow the contract farming model, assuring farmers of buying Jatropha seeds. IL&FS Infrastructure Development Corporation, which is associated with the development of the project, is preparing a feasibility report. The company was targeting cultivation for biofuel on 100,000 hectares. The project will be implemented on a public-private-panchayat partnership model. The model will be replicated abroad, too. The input cost for jatropha cultivation is estimated at Rs 16,000 per acre spread over two years, with expected returns of Rs 12,000 from the third or fourth year of planting. The company signed a memorandum of understanding in this regard with Bharat Petroleum Corporation (BPCL), one of the stakeholders in the project. BPCL will procure the biofuel produced from the BIEZ and will set up refineries for blending requirements. Shapoorji Pallonji (SP), the Germany-based Alphakat and
Indian industry looks to investing in bio-fuel in
May 9, 2008. South America's expertise in bio-fuel could come to the aid of
Global
Foster Wheeler awarded contract for CFB gasifier for BTL pilot plant
May 12, 2008. Foster Wheeler Ltd.’s Finnish subsidiary Foster Wheeler Energia Oy, part of its Global Power Group, has been awarded a contract by NSE Biofuels Oy Ltd. for a circulating fluidized-bed (CFB) biomass gasifier to be located in
REpower consortium wins 954 MW order in
May 7, 2008. The St-Laurent Énergies consortium, with which German wind turbine maker REpower Systems AG has concluded an exclusive option agreement concerning the delivery of wind turbines last year, has been awarded five wind projects by the energy supplier Hydro-Quebec Distribution, representing a total capacity of 954 Megawatts (MW) in the Canadian province of Québec. The consortium is led by EDF Energies Nouvelles (a subsidiary of the electric utility EDF and long-term REpower client) and includes Hydromega Services Inc. (a Québec independent power producer), and RES Canada (international wind farm developer and construction company). On September 18, 2007, the consortium submitted a bid with a total power of 1,048 MW to Hydro-Quebec Distribution which will exclusively be equipped with REpower turbines of the 2-MW class. Once the Power Purchase Agreements (PPA) are finalised between Hydro-Québec and St-Laurent Énergies, the order would be amongst the biggest in the wind industry. The five wind farm projects with a total capacity of 954 MW have in-service dates between December 2011 and December 2015. These five projects represent a total investment in excess of US$2bn and will significantly contribute to the
Dear Reader, You may have received complimentary copies of the ORF Energy News Monitor. Our objective in bringing out the newsletter is to provide a platform for focused debate on We look forward to receiving your patronage and support. ORF Centre for Resources Management |
ORF ENERGY NEWS MONITOR Subscription Form Please fill in BLOCK LETTERS |
Subscription rate slabs for Commercial entries, Research Institutes, Academics and Individuals will be provided on request. The subscription can be made for soft copy or for hard copy or for both. Selected ORF publications as well as advertising space in one issue of the ORF Energy News Monitor are offered as introductory free gifts for Commercial Sector only. |
Yes! I/we would like to receive copies of the weekly ORF Energy News Monitor for a period of ______year(s). I/we shall be entitled to one hard copy along with the option of soft copies to a list of e-mail addresses provided by me/us for the period of subscription. I/we also note that I/we shall get select ORF publications brought out during the period of subscription free. Name……………………………Address…………….………………………Telephone……………………Fax………………….E-mail………………… Please find enclosed cheque/Bank Draft No.........................dated …………………drawn at Please fill in this form and mail it with your remittance to ORF Centre for Resources Management OBSERVER RESEARCH FOUNDATION 20 Rouse Avenue New Delhi - 110 002 Phone +91.11.4352 0020 extn 2120 (Vinod Tomar) Fax: +91.11.4352 0003 E-mail: [email protected] |
Registered with the Registrar of News Paper for
Published on behalf of Observer Research Foundation,
Disclaimer: Information in this newsletter is for educational purposes only and has been compiled, adapted and edited from reliable sources. ORF does not accept any liability for errors therein. News material belongs to respective owners and is provided here for wider dissemination only. Sources will be provided on request.
Publisher:
Production team:
The views expressed above belong to the author(s). ORF research and analyses now available on Telegram! Click here to access our curated content — blogs, longforms and interviews.