-
CENTRES
Progammes & Centres
Location
Peak Oil, the Rise of China and India, and the Global Energy Crisis (part - II)
(MINQI LI Department of Economics,
Continued from Issue No. 37…
Global Warming and Limits to Fossil Fuels
The use of fossil fuels releases large amounts of greenhouse gases that have contributed to global warming. The potentially catastrophic consequences arising from global warming have been discussed widely, including rising sea levels, flood, drought, heat waves, spread of human and crop diseases, decline of food production and a possibility of triggering the next ice age (Kunstler, 2005: 147-66; Lovelock, 2006; Mobbs, 2005: 57-72).
A recent British government report written by a group of economists led by Nicholas Stern argued that if no action is taken to combat global warming, the global economy could shrink by between 5% and 20% over the next two centuries (reported in Financial Times, 31 October 2006). The potential human and ecological costs, however, could turn out to be much greater and the losses may be irremediable.
The Intergovernmental Panel on Climate Change estimated that to stabilise the concentration of carbon dioxide equivalent in the atmosphere at twice the pre-industrial level it is necessary to cut global annual emissions of carbon dioxide equivalent to 8-12 billions tonnes by 2100.
The current global emissions from fossil fuels stand at 27 billion tonnes. This suggests that the global use of fossil fuels needs to be cut by at least 55-70% by the end of the century. However, some argue that even such a reduction may not be sufficient to prevent global catastrophes (Goldsmith, 2005; Trainer, 2005: ch. 1).
Limits to Nuclear Energy
With the coming decline of fossil fuels, nuclear and renewable energies must play growing roles in meeting the world
The generation of nuclear electricity uses uranium, which is a finite resource. The World Energy Council estimated the world's potentially recoverable high-grade uranium (including proven reserves, estimated additional resources and speculative resources) to be 10.7 million tonnes (
Although there have been no major nuclear accidents since the Chernobyl accident in 1986, if nuclear
Limits to Renewable Energies
Renewable energies generally have much less serious environmental problems than fossil fuels or nuclear
The requirements of land impose physical limits to how much renewable
The estimates of electricity prices (costs) from different
Prices or unit costs data can be confusing or misleading sometimes, as it is not always clear whether prices or costs are subsidised or not and what items are included. Trainer (2005; 2006b) made direct estimates of capital costs of wind and solar power based on Australian prices. Trainer's estimates suggest that wind power is about 20% more expensive than a coal-fired power plant. Solar power costs range from 3 to 35 times those for coal-fired power.
If solar power is used on a large scale, then given the intermittency and variability problems, storage would be necessary to deliver a reasonably reliable electricity output. Taking into account storage, the cost of solar power is likely to range from 6 to 35 times that of coal-fired power. (6)
How expensive is too expensive? If the entire world
If the entire world
Such a severe burden could force society to sacrifice other essential goods or services in order to divert resources into
It seems that in the three large economies (
By contrast,
World-wide, biomass may have a potential to replace about 20% of the world's present oil consumption and this assumes that 600 million hectares, or 40% of the world's total arable land, is used to grow
Given the intermittent and variable nature of wind power, there would be great difficulty in using wind as a primary source of electricity or
Boyle (2004: 285) cited an estimate that assumes wind power would generate 20% of the world's electricity by 2020. By this estimate, the wind power potential by 2020 would be 5,177 trillion watt-hours or 445 million tonnes of oil equivalent. Suppose world electricity consumption rises by 2% a year from 2020 to 2050 and wind meets 20% of world electricity demand by 2050, then the potential primary
The
Tide, wave and geothermal are unlikely to make a large world-wide contribution (Hayden, 2004: 209-12; Heinberg, 2003: 151-4; Trainer, 2006b). The potential for hydropower is also limited, especially in advanced capitalist countries. Hydropower also has environmental problems (Boyle, 2004: 177-82; 190-1; Heinberg, 2003: 149-50; Kunstler, 2005:119-21).
Notes:
(5) On the potentials and limitations of renewable energies, see Boyle (2004), Hayden (2004), McCluney (2005), Mobbs (2005: 107-42) and Trainer (2005; 2006b).
(6) The ratios of solar and wind power cost relative to coal-fired power cost used in this paper are somewhat smaller than suggested by Trainer. Trainer's ratios are based on an estimate of coal-fired power plant capital and fuel cost at $A2.8 billion (Trainer, 2005: ch. 2). But, later, Trainer (2006b) suggested a higher estimate at $A3.7 billion. This paper uses the higher estimate.
(7) It is often claimed that the prices of solar photovoltaic cells have fallen rapidly in the past, suggesting that they could keep falling in the future. However, evidence from the last few years suggests that photovoltaic cell prices have stabilised (see Hayden, 2004: 197-203; Meadows et al., 2006: 98). Further, in the case of solar thermal and photovoltaic plants, the cost mainly has to do with the "balance of system" cost or the cost of plant construction, which is unlikely to be affected by technological progress.
to be continued…
Courtesy: Journal of Contemporary
Short-Term Trading of Natural Gas: Some Risks Involved (part – III)
Ahmed El Hachemi Mazighi, Advisor, Strategy & Prospects, Sonatrach- Commercialisation,
Continued from Issue No. 38…
Infrastructure-building risk
Unlike oil, where liquid and flexible markets have been developed during the last 30 years, the development of new LNG chains, which are necessary for the globalisation of the gas business, is very costly, in terms of infrastructure-building. Most often, due to a misunderstanding of the gas business (Banks, 2002, 2003), the risks related to the building of this gas infrastructure are neglected in the literature, even though such risks are highly important.
In fact, the security of gas supply is not only a question of having access to gas reserves; the building of the infrastructure — from field development to consumer equipment in the residential sector — is, without any doubt, the second layer of security of gas supply.
However, with the short-term trading of natural gas, the producer loses the guarantee that it can sell its gas; the volumes it can place on the market become uncertain. As a result, in its long-term planning, the producer will be obliged to replace known quantities on the basis of scenarios on demand growth.
In other words, certainty is replaced by uncertainty which, given the lack of accuracy of forecasts and the difficulty in accessing capital markets, can reduce the willingness of the producer to invest in infrastructure.
One of the lessons learned from the Californian crisis is that investment in capacity is reduced when producers have to face both volume and price risks. A second lesson is that risk-averse producers will only invest in the maintenance of existing capacity, which, when there is demand growth, will create structural disequilibrium and price shocks that are completely out of line with supply security requirements.
Another uncertainty is related to investment in the midstream gas sector (transportation) and in the reinforcement of gas interconnections in gas-consuming countries. Indeed, to make the principle of flexibility operate within a particular area, we need a high interconnection rate, so that excess demand and supply can clear rapidly.
How-ever, this seems to be very difficult to carry out. In a model of the vertically integrated market, the development of midstream gas was “subsidised” through the segments of gas sales to eligible and final consumers.
Indeed, midstream gas is more capital-intensive than the other segments. The unbundling of the different activities of the gas chain, combined with third-party access and regulation procedures in gas-consuming countries, creates disincentives to invest in the midstream and even disinvestment (Mercey, 2003), due to the relatively low return on this vital segment of the gas chain.
On the whole, the short-term trading of gas can be suitable for neither the development of
Concluding remarks
There is no free lunch. Switching from the long-term trading of gas to a short-term trading system is far from providing only benefits. Moreover, flexibility — which is considered to be the main benefit — is not an end in itself.
From the volume, price and infrastructure risks, one can ask which risk is the most threatening.
The price risk — paradoxically — is not, in my opinion, the most dangerous. In the case where markets are liquid enough, volatility is only a reflection of the fact that markets are operating efficiently, but the unpredictability of prices, that results from this efficiency, obliges the producer and the consumer to have recourse to hedging tools or create stabilisation funds, which is costly.
The volume risk requires us to give much attention to the building of storage facilities in the long term, because more and more power plants, in the coming years, will use gas only.
The infrastructure-building risk is certainly the most important risk, because it represents a direct threat to the development of new gas chains that are necessary to meet the long-term increase in natural gas demand.
It is worth noting that there is a fundamental paradox between the willingness of developing countries to increase the relative share of natural gas and their intentions to increase the short-term trading of natural gas.
In the coming years, TOP contracts will certainly continue to be the norm for the development of
Concluded
Courtesy: OPEC Review
NEWS BRIEF
NATIONAL
OIL & GAS
Upstream
ONGC investing $4 bn to improve oil recovery: Dinsha Patel
March 18, 2008. According to the Minister of State for Petroleum and Natural Gas, Dinsha Patel, Oil and Natural Gas Corp is investing over Rs 14,000 crore ($3.5 bn) in improving recovery from its major oil and gas fields in the country. ONGC has identified 14 of its major oil and gas fields which contribute nearly 80 per cent of the total production, for implementing Improved Oil Recovery (IOR) and Enhance Oil Recovery (EOR) schemes. The fields identified for IOR/EOR are Mumbai High, Heera, Neelam, Gandhar, Kalol, Sanand,
RIL's KG block oil field to boost govt revenues
March 18, 2008. Reliance Industries' oil field in its predominantly gas rich KG-D6 block in Krishna Godavari basin will boost government revenues by at least 1.6 billion dollars. According to the Minister of State for Petroleum and Natural Gas Dinsha Patel the 1.6 billion dollar revenues from the MA oil find is in addition to the revenues expected from the development of D1 and D3 gas fields in KG-D6 that lie off the east coast. However, these revenues are dependent upon variation in the projected parameters such as quantum of production, capital costs, operating costs and prevailing oil and gas prices. Reliance is to initially produce 40 million standard cubic meters per day of gas, which will gradually increase to plateau production of 80 mmscmd. Reliance is to begin gas production from KG-D6 later this year.
ONGC sees 1.2 mbpd oil & gas output by ’09
March 17, 2008. Oil and Natural Gas Corp (ONGC), oil and natural gas production was expected reach a total of about 1.2 million barrels per day of oil equivalent (boepd) by 2009. The company would spend about Rs 76000 crore ($18.6 bn), including Rs 453oo crore ($11.1 bn) for overseas expansion, by fiscal 2012 to boost its production. By the next fiscal year that ends in March 2009, domestic oil and natural gas annual production was expected to hit a total of 1.03 million boepd, including 580,000 barrels per day of crude. Overseas production of oil and gas in the same period was likely to reach around 180,000 boepd. The company is of the view that the Rs 76000 crore ($18.6 bn) capex would be mostly funded by the company's internal resources.
ONGC introduces SAP powered “Reverse Auction” process
March 17, 2008. Oil and Natural Gas Corporation Ltd. (ONGC), the largest Oil & Gas Exploration and Production company in Asia achieved another first by becoming the only PSU to introduce SAP powered “Reverse Auction” process. Termed as “Live Action Cockpit” (LAC), the system will enable ONGC to collect and compare price and bid information of various suppliers in a real-time, open bidding environment. The company said that it strongly believes in adopting world-class processes and technologies to generate better value for its stakeholders. The reverse auction will ensure transparency in the tendering process and thereby generate confidence amongst the bidders. It will also add speed to the process of procurement which will allow ONGC to source best in class technology. On the basis of the pilot project it is estimated that reverse auction will be able to accrue a cost saving of nearly 10%. LAC will be the sole procurement window for all ‘high value’ tenders, valuing more than Rs10mn. This process will provide a level playing field to bidders having necessary techno-commercial capabilities. Adhering to the guidelines of CVC the Reverse Auction process will ensure standardization of the procurement process of ONGC. The LAC will bring in higher efficiency, cost savings and transparency to ONGC’s procurement processes as it continues on its path of being a global Oil & Gas leader. Such initiatives prove that when it comes to harnessing technology for more efficient business operations, public sector companies like ONGC are second to none globally. The reverse auction process enables supplier selection process by facilitating vendors worldwide to participate in the bidding process seamlessly. ERP software implemented by SAP at ONGC, supports industry best practices in procurement and delivers advanced e-procurement. This is among the largest such projects undertaken by SAP in the public sector.
Bathinda refinery assures
March 18, 2008. Guru Gobind Singh Refinery Project (GGSRP) assured Punjab Government that Rs. 18,900 crore ($4.7 bn) refinery, proposed to be set up in Bathinda, would be commissioned within stipulated time. GGSRP, a joint venture between HPCL-Mittal Energy Limited, assured
Essar Oil to raise $2 bn
March 14, 2008. Essar Oil today will raise $2 bn (Rs 8,094 crore) through securities for the proposed expansion of its refining and exploration capacity. The shareholders has approved the raising of Rs 8,000 crore ($1.97 bn) by issuance of Foreign Currency Convertible Bonds (FCCBs), Global Depository Receipts (GDR) and other securities, Essar Oil informed the BSE.
Gujarat refinery scouts for more land in Vadodara
March 13, 2008. Indian Oil Corporation (IOC)'s largest refinery at Koyali in
Indian crude basket crosses US$100 per barrel
March 12, 2008. With crude oil futures in the
Transportation / Trade
Cairn
March 18, 2008. Oil exploration and production company Cairn
Confidence Petro enters into JV with US company
March 18, 2008. Confidence Petroleum
A new subsidiary of Primecyl LLC, Confi Energtek Asia, will be established in
IOC begins piped LPG in North-East
March 17, 2008. The Indian Oil Corporation (IOC) launched its first reticulated LPG supply system, which is also known as 'piped LPG' and has gained popularity in other parts of the country, in North East. In a reticulated system, the distribution of LPG to the customers is done through a pipeline network with metering facility. LPG is sourced from centralised cylinder bank or bulk LPG storage facility housed in the premises of the building. This system of LPG supply was launched in the country around one and half years back. IOC is now looking North East and wants to make the system popular.
In case of private apartments, the builder or the residents need to make the necessary investment, which would cost around Rs. 10,000 to Rs. 15,000 per flat depending on the number of flats and layout. In the case of commercial and industrial establishments, IOC "may invest" depending on the viability of the project. The advantages of reticulated system are that it ensures continuous supply of LPG, besides payment at the end of billing cycle for used quantity only. It also frees the consumer from the hassle of ordering a refill and waiting for delivery.
Moreover, the reticulated connection of LPG comes with enhanced security and has in-built safety system that ensures LPG supply shut off in case of leakage. IOC conducts periodic safety audits to check the performance of the system in individual apartments. The reticulated system is also compatible with the piped natural gas distribution system, which has already gained popularity in parts of
Gujarat gas lines up $37 mn for household gas connections
March 17, 2008. Ahmedabad-based Gujarat Gas Company Limited (GGCL), primarily engaged in procurement and distribution of natural gas, is now focusing on household gas connections. The company has earmarked Rs 130-150 crore ($32 – 37 mn) for the same during 2008. GGCL will start providing household gas through pipeline in Kim, Karanj, Vyara, Bardoli, Jhagadia, Vilayat, Sachin, Bardoli, Olpaad, Pal, Veddabholi, Mota Varachha and Suroli this year. As of now, the company’s pipeline network covers over 2,100 km. GGCL has its base in the golden corridor of south
Confidence Petro to acquire Agwan Coach
March 13, 2008. Confidence Petroleum India Ltd. has entered into a MoU for acquiring Mumbai-based petro logistics company Agwan Coach Pvt Ltd. The acquisition of Agwan Coach finds synergy with the existing business of the company and will increase the strength and support the bottling business. Confidence Petroleum is the flagship company of Nagpur-based Confidence Group involved in the business of LPG Cylinder manufacturing, LPG Bottling, LPG Marketing, LPG Blending, Auto LPG Cylinder Manufacturing & Auto LPG Dispensing for more than a decade. Agwan Coach is in the business of providing logistics support to oil companies from the last 14 years. Agwan Coach will become a 100% subsidiary of Confidence Petroleum.
Policy / Performance
ASSOCHAM for uniform VAT on Petrol & Diesel
March 14, 2008. Although sales tax has been abolished but state governments continue to subject oil companies to sales tax which varies from 33% to 18.9% in case of petrol and 34% to 8.23% for diesel and therefore it is suggested that a uniform VAT of 8% be levied on petrol and diesel so that oil companies are able to stand the burden of rising crude oil prices. These observations are made by the Associated Chambers of Commerce and Industry of India (ASSOCHAM) on taxation part for petroleum products, saying that in addition to sales tax, the states continue to levy entry tax/octroi on movements of crude which also varies in different states between the range of 4% to 2% and thus put an additional burden of taxation on oil companies, that lead to shrinkage of their margins.
The element of taxation on petrol and diesel is to the extent of about 140% and therefore, at least their should be a uniform VAT of 8% on petroleum products particularly that of diesel and petrol so that oil companies are given some respite from higher crude oil prices internationally and aam adami is also not subjected to unnecessary burdens. The share of tax in the selling price of petrol in
In the case of diesel, the other countries have kept the taxes to less than 20%. Out of the retail price of petrol in
Although, with the recent hike in petrol and diesel prices, the oil companies are likely to get some relief but their losses would exceed Rs800bn for current fiscal as crude oil prices have gone up beyond imaginary levels and therefore, in the current budget session itself, the government should sacrifice its tax collections in the form of custom and excise on crude oil and rationalize the local levies and create consensus for uniform VAT of 8% on petrol and diesel. The Chamber stressed that the oil companies in the government sector should also be encouraged for export of petroleum products just as the private sector does it so that companies like Indian Oil Corporation Ltd., Bharat Petroleum Corporation Ltd., Hindustan Petroleum Corporation Ltd. etc. also avail of the benefits of duty drawback scheme. The Chamber is also of the view that the government should gradually phase out subsidies extended to sectors like food, fertilizer and petroleum and particularly this exercise should be commenced with
GAIL plans arm for city gas supply
March 12, 2008. GAIL India, the country’s largest transporter and marketer of natural gas, will set up a wholly owned subsidiary to sell gas to households, vehicles and industries in cities across the country. GAIL will register the new company in next 2-3 months. The government-owned gas utility has already identified 17 cities to bid for gas distribution rights, for which the new company plans to spend around Rs 500 crore ($124 mn). The new company will bid for all
GAIL already has joint ventures with other gas companies for distribution in various cities across the country. GAIL’s equity share in the existing joint ventures, such as Indraprastha Gas in
POWER
Generation
Indiabulls Power wins power plant bid in central India
March 18, 2008. Indiabulls Power Services Ltd, a unit of Indiabullls Real Estate, has won a bid to build a 1,600 MW power plant along with a coal mine in central
China Light pips Lanco in bid for Haryana project
March 18, 2008. Hong Kong-based China Light and Power Holdings has emerged the lowest bidder for setting up the 1,326 mw power generation project at Jhajjar in Haryana. CLP had quoted a price less than Rs 3 a unit, while Lanco Infratech emerged the second lowest bidder at Rs 3.04 a unit. The third bidder was Torrent Power. Haryana Power Generation Corp is setting up the Rs 7,000 crore ($1.7 bn) power plant. Coal
Dhoot plans power units
March 17, 2008. Kolkata-based real estate development company, Dhoot Group has planned to invest Rs 1,000 crore ($245.6 mn) in real estate projects in
NTPC commissions 2nd unit at Kahalgaon project
March 17, 2008. National Thermal Power Corporation Ltd (NTPC) announced that the Second Unit of the 500 MW Kahalgaon Thermal Power Project - Stage II in
R-Power to pick
March 17, 2008. Reliance Power, the flagship power company of the Anil Dhirubhai Ambani group, has struck a deal to buy out a coal mine in
Reliance Power is understood to have acquired the coal mine for about Rs 1,000 crore ($245.6 mn). It has acquired 100% interest in this coal mine. Experts say that this coal mine could be compared to one of the largest coal mines in
Given that the acquired mine has resources of 2 billion tonnes, it is expected that the production from this mine should be more than the largest mine in
Tata Power, another leading power company which won the first imported coal based power project at Mundra have also bought a 30% stake in a coal company Bumi in
Maharashtra signs MoU with Malu Paper
March 16, 2008. The
NCL, Neyveli plan $1 bn power plant
March 14, 2008. Northern Coalfields Ltd (NCL) and Neyveli Lignite Corporation (NLC) will be investing Rs 5,200 crore ($1.3 bn) for setting up a 1,000 MW pit-head power station at Gorbi mines in the Singrauli Coalfields. The scope of the project also includes mine development. While Rs 4,500 crore ($1.1 bn) would go in for setting up the pit-head power unit, another Rs 700 crore ($173.2 mn) would be invested for development of mines. The two PSUs have already inked a memorandum of understanding (MoU) to go ahead with the project.
The two companies would be forming a special purpose vehicle for the pit-head power unit and mine development. NLC is also holding talks with Mahanadi Coalfields (MCL) for setting up a 2,000 mw pit-head power unit at Vasundhara mines in the Ib Valley coalfields. The country’s largest coal producing company, South Eastern Coalfields, (SECL) has already entered into an MoU with Chhattisgarh State Electricity Board (CSEB) for setting up another pit-head power station.
According to the CIL, the necessity to set up pit-head power stations was mostly because of evacuation problems currently faced by its subsidiaries such as MCL and Central Coalfields. Huge amount of coal is lying unutilised in the Manoharpur and Gopalpur blocks of MCL. Similarly, north Karanpura coalfield in the CCL area is also facing evacuation problems.
With the Tori-Sibpur coal evacuation railway line yet to take shape, there is virtually no material movement from some parts of the Central Coalfields. The setting up of the pit-head power station at Gorbi mines will help NCL directly feed the power stations of Panipat, Rajghat and Indraprastha. Meanwhile, proposals are currently being looked into for expansion of capacity of the Jayanta coalmines in the Singrauli coalfields. Like other CIL subsidiaries, NCL is desperately trying to combat evacuation problems currently faced in the Singrauli coalfields. NCL currently has 8 open cast mines and no underground mines.
Jindal Stainless to enter power sector
March 14, 2008.
Vedanta inks pact with
March 13, 2008. Vedanta group signed a development agreement with the West Bengal Industrial Development Corporation (WBIDC) for a Rs 20,000 crore ($4.9 bn) aluminium and power project. The project entails setting up a 6.5 lakh tonne smelter and a 3,000 mw power plant at Bidhanbagh in the Burdwan district. The plant would be operational within three years. Out of the total capacity of 3000 MW, the 1,500 MW would be for captive use and the balance could be supplied to the metals park. The group has decided to locate the project in
NTPC to invest $3 bn for adding 2.7 GW in FY09
March 13, 2008. As part of its ambitious plan to become a 50,000-MW company by 2012, state-run NTPC Ltd said it will invest Rs 13,000 crore ($3.2 bn) for adding 2,700 MW capacity during the next financial year. On funding, it said it would be a mix of equity and debt in 30:70 ratio. Its spending plan for FY'08 was Rs 11,000 crore ($2.7 bn). As part of the 11th Five Year Plan, NTPC aims to become a 50,000-MW company by 2012. The company is seeking three million LNG import from
Transmission / Distribution / Trade
JSW firms sign coal shipping deal with Japanese co
March 18, 2008. Sajjan Jindal’s JSW Steel Group has signed a $2 billion deal with a Japanese shipping firm for transportation of coal over ten years. JSW Steel and JSW Energy have contracted Tokyo-based Kawasaki Kisen Kaisha Ltd to ship coking coal and steaming coal on ten vessels. Ports of loading under these contracts could vary, but the coal will be imported exclusively from
The transport volume for the two companies could reach 12 million tonnes by 2015, when all the vessels enter the service. JSW Steel, which produces 4.5 million tonnes of crude steel, is expanding an existing mill at Vijaynagar and plans to build two
Power shortage rises to highest level in Jan
March 18, 2008. According to the Centre for Monitoring Indian Economy monthly report the country’s power shortage rose to its highest level at 12.8 per cent in January 2008 as compared to 12.51 per cent in January 2007. The report said that growth of total power generation in
The year-on-year rise in hydro-power generation of 6.5 per cent was nearly offset by an equal fall in power generated by the nuclear plants. During January, thermal power output rose 3.9 per cent to 50.68 billion Kwh on the back of 9.2 per cent rise in coal dispatches. A healthy 5.5 per cent rise in thermal power generation together with a 9.6 per cent surge in hydel power output led to 6.3 per cent increase in total power generation during April-January 2007-08.
Power supply rose 6.5 per cent in April-January, while the demand for it increased by a lower 6.1 per cent, thus, leading to an improvement in power situation in the country with average power deficit marginally lower at nine per cent.
BHEL bags order for NTPC’s
March 18, 2008. Power equipment maker Bharat Heavy Electricals (BHEL) has secured order worth Rs 2,030 crore ($504.3 mn) for supply of main plant package to a 1,000-mw project in
Power scenario bleak in K`taka
March 17, 2008. The state-owned Karnataka Power Transmission Corporation Limited (KPTCL), which handles transmission and distribution of power, is beginning to find itself in a piquant situation as it can afford to supply only about 125-130 MUs per day by harnessing all the resources at its disposal. In fact, when the demand for power peaked to 141 MUs per day in the summer of 2007, the effects on the common man and the industry were quite harsh. According to the KPTCL’s own projections, the total power required during February-May 2008 is 12,981 MUs and the power available from all sources is 11,155 MUs. By the end of May, power deficit is likely to touch 1,826 MUs and that would manifest in more power cuts. What has compounded the problem is the Union government’s recent decision to divert 100 MW of Karnataka’s share in the central grid to Tamil Nadu because of political compulsions.
Reliance Energy eyes road, rail deals
March 17, 2008. According to the Reliance Energy Ltd, it will focus on infrastructure projects in its home market, where it sees the biggest opportunities. Reliance Energy, which is seeking shareholders' approval to change its name to Reliance Infrastructure, has diversified into construction in recent years. The firm has several projects underway that will require about $3.5 billion in capital expenditure, and is committed to developing two large special economic zones in
Genus Power merges power unit of Genus Paper with self
March 17, 2008. Genus Power Infrastructures Ltd’s board has approved spinning off a 6-megawatt power unit of Genus Paper Products. The power unit will be, now, part of Genus Power Infrastructures, it said in a statement. Shareholders of Genus Paper would get one equity share of Genus Power for every 60 equity shares held by them.
Delhi asks to Centre for more power
March 15, 2008. In an attempt to bridge a possible gap between peak demand and supply in the summer months,
The Union government has unallocated power at its disposal which it can allocate according to the needs of the states and the situation. Last month the
Coal
March 18, 2008. Coal
Most of the underground mines run at a loss and since policy dictates that the selling price should recover production costs, customers should expect that the reserve price of superior coal from such mines would be higher than spot prices. The average spot price is currently at a 130% premium to the notified price and Coal
BHEL, RPL may plug into largest PPP project
March 17, 2008. In what could transform into the biggest public-private joint venture in the power sector, public sector Bharat Heavy Electricals (BHEL) and Reliance Power (RPL) are exploring possibility of a tie-up for equipment manufacturing.
Reliance Power recently announced its intention to venture into power equipment manufacturing. The company, which is part of the Reliance-Anil Dhirubhai Ambani Group (R-ADAG), is in talks with the public sector engineering major to leverage its expertise in manufacturing. BHEL and Reliance Power would have equal equity partnership in the proposed special purpose vehicle (SPV).
Both the companies would have 50:50 equity partnerships. BHEL is tying up with several companies for increasing its manufacturing capacity. The government has set a target of adding over 78,000 MW of generation capacity during 11th Plan. BHEL would be able to meet just over 50% of this target even with its proposed expansion.
The company is, therefore, looking at all options to expand its manufacturing base. Reliance Power on the other hand has plans to set up 13 projects with total capacity of 28,200 MW. Of this, 10,300 MW is gas-based, 3,300 MW is hydel and the rest is coal-based. While the company is looking all over the globe for equipment suppliers, it has favoured its own manufacturing facilities to reduce cost of generation and timely completion of projects. It is expected that the proposed JV with BHEL would not be restricted for captive use of Reliance Power and venture would look for commercial business from other power stations too.
Electricity on demand by 2012: Shinde
March 17, 2008. Government said the country will have electricity on demand by 2012 and it needs nuclear
The country had added 54,000 MW generation capacity during the last 15 years (8th, 9th and 10th Plans). He also pointed out that the country needs nuclear power for its future
Haryana to invest $6 bn in power sector in 11th Plan
March 16, 2008. To augment power generation and strengthen its distribution system in the state, the Haryana government has prepared a mega investment proposal of Rs 24,316.82 crore ($6 bn) during the 11th five year plan. Out of this, Rs 10,042.01 crore ($2.5 bn) would be spent on power generation, while Rs 7,697.72 ($1.9 bn) crore is earmarked for transmission and Rs 6,577.09 crore ($1.6 bn) is for strengthening of distribution system in the state.
A comprehensive plan has been formulated to construct 255 new substations, augment 154 existing ones and construct associated transmission lines at cost of Rs 4020 crore ($1 bn) to strengthen the power transmission and distribution system in the state. Seventy new sub stations have been commissioned besides augmenting 180 existing sub stations and erecting 1100-km-long transmission lines at a cost of Rs 500 crore ($123.6 mn) after the present government came to power in Haryana. The DHBVN and the Haryana Vidyut Prasaran Nigam (HVPN) plan to spend Rs 460 crore ($113.7 mn) to strengthen Power transmission and distribution system in Bhiwani district.
India-Sri Lanka power transfer project feasibility report soon
March 15, 2008. The feasibility study for the proposed $450-million mega undersea power transmission link between
The report on the HVDC (high voltage direct current) link between the two countries is being prepared by State-owned transmission major Power Grid Corporation of India Ltd (PGCIL), which had earlier estimated that it can set up the link in around 40 months once all clearances are in place. The link is likely to connect
While a joint Steering Committee has been set up to oversee the project, a task force comprising representatives of the Power Ministry, Central Electricity Authority and PGCIL on the Indian side and the Sri Lankan Energy Ministry and Ceylon Electricity Board (CEB) on the other, has been firmed up to study the feasibility report and make recommendations to the Committee. Indian utilities could get higher tariffs from electricity supplies to the country.
Initially, surplus power would be transmitted from
Sri Lanka currently uses diesel — one of the most expensive power generating resource — for nearly 65 per cent of its power generation. The generation cost there is around Sri Lankan Rupees 15 per unit (about Indian Rs 6.21 per unit), according to CEB data.
India considering 3 more large power projects
March 14, 2008.
The state government had written to the federal government offering coal blocks for the new plants.
The government has awarded three of these projects- two to Reliance Power Ltd in south and central
Kalam pitches for more nuclear power plants
March 13, 2008. Amidst the debate over Indo-US civil nuclear deal, former President APJ Abdul Kalam has thrown his weight behind nuclear power saying
He expressed that very soon, oil and gas will see its finiteness. It is high time that we realize this factor and work towards the fuel of the future. Kalam said hydrogen fuel, emulsified fuels, solar
INTERNATIONAL
OIL & GAS
Upstream
LLOG claims 3 new deepwater discoveries
March 18, 2008. LLOG Exploration Co., LLC announced three new deepwater discoveries from their 2007/2008 drilling program. The new discoveries are Mississippi Canyon (MC) 72 #1, Mississippi Canyon 503 #1, and Green Canyon (GC) 448 #1. All of these discoveries should be producing by mid-2008.
CNX gas predicts 72 bcf for ’08 output
March 18, 2008. CNX Gas Corp. expects to produce 72 bcf of natural gas this year and has hedged more of its expected output to reflect higher prices for the fuel. Consol, which owns a controlling stake in CNX, in January announced plans to buy the remainder in a stock-for-stock deal in the first half of this year.
CNX has hedged 35.9 bcf of its expected 2008 production at an average price of $8.84 per 1,000 cubic feet. In addition, it has hedged 24.7 bcf of 2009 output and 5.6 bcf of 2010 production at average prices of $9.02 and $9.14 per 1,000 cubic feet, respectively.
Lukoil plans to produce 15 bcm of gas this year
March 18, 2008. OAO Lukoil plans to produce 15 bcm of gas this year. About 9 bcm will be natural gas while the remaining amount will be associated gas, released during crude oil extraction operations. Lukoil produced 14 bcm of natural gas last year.
Mexico’s proven hydrocarbon reserves 14.7bn boe
March 18, 2008.
Mexico's proven reserves as of January 1, 2008 were equivalent to 9.2 years of crude production, and 8.2 years of natural gas production. Pemex produced an average of 3.1 million barrels a day of crude oil last year, and 6.058 bcf a day of natural gas.
Lundin begins exploration drilling of Wan Machar
March 14, 2008. Lundin
The partners in Block 5B are Petronas Carigali White Nile (5B) Ltd (Petronas) (39%), Lundin Petroleum (24.5%), ONGC Videsh Ltd (23.5%) and Sudapet Ltd (13%). Furthermore, the partnership has accepted the recommendation of the National Petroleum Commission to assign a 10 percent share to the National Oil Company of Southern Sudan to be allocated on a pro rata basis from each of the partners' shares. The operator of Block 5B is White Nile Petroleum Operating Company (WNPOC) a joint venture between Sudapet Ltd and Petronas.
WW
March 13, 2008. WW Energy Inc., a holding company that was created to acquire oil and gas service companies as well as oil and gas-related assets, announced that the Company has gone forward with the signing of a letter of intent which would lead to the production of wells in Terry County, Texas.
This purchase of the working interest in the Terry County, TX. Wells will generate revenues of $500,000.00 per month producing 2,150 bbls. of oil and 3,985 mcfd per day. Of the approximately 75 wells identified to be drilled, six have been completed and another twenty-four wells have been identified for drilling.
The strategic ownership of critical pipeline infrastructure, proprietary seismic data and participation in key wells and leases can bring nothing but excitement to this dynamic company. The addition of this revenue for this company will increase its position in the
VAALCO plans drilling in Gabon, Angola,
March 13, 2008. VAALCO Energy's current exploration and development schedule includes up to seven wells to be drilled in
Dynamic's
March 13, 2008. Dynamic Resources reported that the project partners have drilled their fourth successful
The first three wells drilled to the
Downstream
BP joins
March 18, 2008. BP and Irving Oil have entered into a Memorandum of Understanding to work together on the next phase of engineering, design, and feasibility for the proposed Eider Rock refinery in
Irving Oil conducted initial feasibility work and informal public consultation in 2006, and has been engaged since January 2007 in permitting, public consultation, and engineering design for the proposed 300,000 barrel per day refinery. The refinery would be situated close to Irving Oil's existing 300,000 barrel per day refinery and the existing Irving Canaport deepwater crude oil terminal which receives VLCC cargoes of crude oil and is located 65 miles (105 km) from the
This next phase of engineering, design and feasibility work, combined with ongoing permitting and community engagement activities represents over US$100 mn of investment over the next 12-15 months. A final investment decision is not expected before 2009 and, although the final costings will only be clear once all the detailed engineering and design work is completed, the refinery is expected to cost at least US$7 bn.
If permitting approval is received and an investment decision is made to proceed, site preparation would begin in 2010, and full scale construction would begin in 2011 with start-up expected in 2015. Irving Oil has committed to using the best available proven technology to develop a refinery with leading environmental performance and economic efficiency.
5 mn barrel shortfall expected at Syncrude for Q1
March 18, 2008. According to Canadian Oil Sands Trust (Canadian Oil Sands) crude oil production from the Syncrude facility is expected to average about 265,000 barrels per day (97,000 barrels per day net to the Trust) for the first quarter of 2008.
While Syncrude has been undergoing various initiatives with a view to achieving higher production, the reduced production to date following the disruption at the end of January/early February has resulted in a shortfall of about 5 million barrels, gross to Syncrude.
Shell to boost refining, downstream GTL assets by 8 pc
March 17, 2008. Shell is rejuvenating its portfolio for a world of higher and more volatile commodity prices, increased competition, and higher costs. As part of the annual review of strategy, Shell is building over 50 large projects that will underpin new cash flows for decades to come. Upstream, Shell has over 10 billion barrels of oil equivalent (boe) resources under construction, which will add 1 mn boe/d of production. Shell's industry-leading fuels and lubricants portfolio is being positioned into growth markets.
The company is also building significant new petrochemicals facilities, and new refining and downstream gas-to-liquids (GTL) capacity totaling 300,000 b/d for Shell. Major investments underway today include:
· Investment in some 10 billion boe of resources that will deliver 1 million boe/d of oil & gas, and are the foundation for long-term growth potential of 2-3%/year
· 60,000 b/d of oil sands capacity, an increase of more than 60% from today's levels
· Over 7 million tonnes per year of new liquefied natural gas (LNG) capacity, an increase of 50%
· New refining and downstream GTL assets, totaling 300,000 barrels per day of downstream capacity for Shell, an increase of some 8%.
· Positioning Shell's leading fuels and lubricants marketing businesses in new growth markets
· 800,000 tonnes per year of ethylene and 750,000 tonnes per year of mono-ethylene glycol. This is a 13% increase in Shell's ethylene capacity and a 60% increase in its mono-ethylene glycol capacity
· Over 100 MW of new wind power capacity. Renewables investment continues, with particular focus on wind power and next generation biofuels.
Looking beyond the portfolio that is currently under construction, Shell has significant additional resources that could be developed for production, and exploration portfolios in some 14 focus basins. Over 20 potential new projects are being designed, that could commercialize over 6 billion boe of discovered resources, and produce 0.8 million boe/d. There is particular potential in North America heavy oil and tight gas, and LNG in
Group oil and gas resources estimates have been increased to some 66 billion boe, with a resources life of some 55 years. This improvement reflects exploration performance, where Shell added 1.4 billion boe in 2007, and an update to the portfolio overall.
Mitsui set to join
March 17, 2008.
PetroVietnam expected a joint venture contract to be signed in early April. The Vietnamese group will hold a 25-percent stake with the three foreign partners dividing up the rest. The joint venture is expected to officially receive an investment license by June, and construction will start in 2010.
The refinery with annual processing capacity of some 10 million tons is slated for completion within 60 months. The project will include the oil refinery, refined and material factories,
In addition to LPG, unleaded gasoline, kerosene, jet fuel, diesel and FO, the refinery is projected to produce bitumen, propylene and BTX as a raw material for the domestic petrochemical industry. Crude oil may come from the Su Tu Den (Black Lion) oilfield off
The Nghi Son refinery and the Dung Quat oil refinery,
PetroVietnam is working on another plan to develop the country's third oil refinery in
Transportation / Trade
Corrintec surveys subsea section of OCP
March 18, 2008. Corrintec, the specialists in subsea pipeline cathodic protection surveys, has carried out a survey on the final section of a 500-km pipeline that transports crude oil from the jungles of the Amazon, across the Andes, to a terminal near Esmeraldas on the
The survey has been commissioned by SLEM
Each of the pipelines has a maximum flow rate of 60,000 barrels per hour. In addition, Corrintec engineers have carried out a 500 meter landfall survey on the four pipelines.
PGN to build gas pipeline in
March 17, 2008. Indonesian state gas distributor company PT Perusahaan Gas Negara (PGN) will build a 664-kilometer-long gas transmission pipeline linking Sumatra's towns of Duri, Dumai and
The LNG terminal will have a capacity to store 3.0 mt of LNG per year or 400 mmscfd. Gas will be supplied from the Bontang LNG project developed by Total, as well as from the Tangguh LNG project developed by BP.
European companies to explore integrated pipeline network
March 14, 2008. Gas transmission companies from Central and
NETS would aim to attract capital, accelerate infrastructure development and inter-connectivity, enhance value, competition and the supply security of the region. The companies include
Williams, TransCanada propose new western gas pipeline
March 13, 2008. Williams and TransCanada Corp. are evaluating the joint development of Sunstone Pipeline, a major new natural gas transmission pipeline that would offer producers and end-users a cost-effective way to move natural gas supply from the Rockies to markets in the western
The proposed Sunstone Pipeline is a 618-mile, 42-inch-diameter pipeline with capacity of up to 1.2 bcf per day. The project, which is proposed for service in 2011, would involve constructing a new pipeline substantially parallel to the existing Williams Northwest Pipeline system between the Opal Hub in Wyoming and Stanfield, Ore. Williams' Northwest system interconnects at Stanfield with TransCanada's Gas Transmission Northwest (GTN) pipeline system.
The project provides the option to deliver gas to markets served by the Northwest and GTN pipeline systems. Sunstone's open season will commence March 17 and run through April 30, 2008. GTN will hold an additional open season to offer existing capacity available on its pipeline system between Stanfield and GTN's terminus near
Williams, through its subsidiaries, finds, produces, gathers, processes and transports natural gas. Williams' operations are concentrated in the Pacific Northwest, Rocky Mountains,
TransCanada's network of wholly owned pipelines extends more than 59,000 kilometers (36,500 miles), tapping into virtually all major gas supply basins in North America. TransCanada is one of the continent's largest providers of gas storage and related services with approximately 355 billion cubic feet of storage capacity.
Sinopec's oil pipeline network reaches more than half of refineries
March 12, 2008. Sinopec Group's crude pipeline network has covers 18 refineries in North China, East China, and
25 wells have been connected to Atmos gas gathering system
March 12, 2008. Australian-Canadian Oil Royalties Ltd. (ACOR) announced that 25 out of 34 of ACOR's existing gas wells operated by Resource and Energy Technologies Company (RETCO) are currently being connected to a natural gas gathering system owned by a unit of Atmos Energy Corporation and to a gas processing facility, and operated by RETCO. The gas plant is completely finished.
Policy / Performance
Keystone work to start in Q2
March 17, 2008. TransCanada Corp. (TransCanada), on behalf of TransCanada Keystone Pipeline, LP (Keystone), announced that the U.S. Department of State has issued a Presidential Permit to Keystone authorizing the construction, maintenance and operation of facilities at the United States and Canada border to transport crude oil between the two countries.
The Permit follows the Department of State's Record of Decision and National Interest Determination, which found that issuance of the Presidential Permit for the Keystone Pipeline would serve the national interest. The Presidential Permit is a significant regulatory approval required to proceed with construction of the Keystone Pipeline, which will move a growing supply of Canadian crude oil to key
Venezuela aims to increase ’08 oil output from old fields
March 17, 2008.
Venezuela's western provinces include the oil-rich
The government claims to produce close to 3.2 mn barrels a day, but data from the Organization of Petroleum Exporting Countries and other sources puts total production closer to 2.4 mn barrels a day. The country has struggled with oil production since 2003 and when President Hugo Chavez fired thousands of PdVSA workers and executives following an oil strike.
OPEC to rake in $900 bn in 2008
March 16, 2008. The Organization of Petroleum Exporting Countries (OPEC) will earn more than $900 bn in oil exports this year as the average price for the group’s crude surpasses $100 a barrel for the first time. OPEC members may earn $927 bn from net oil exports in 2008, raising a January estimate by 9 per cent.
OIL EXPORT REVENUE |
||
Opec |
Oil export revenues |
Per capita oil |
Saudi Arabia |
$193.80 |
$7,012 |
UAE |
$63.00 |
$23,817 |
Iran |
$57.30 |
$876 |
Nigeria |
$55.30 |
$409 |
Kuwait |
$54.30 |
$21,619 |
Algeria |
$50.60 |
$1,516 |
Venezuela |
$48.30 |
$1,850 |
Angola |
$43.80 |
$3,566 |
Libya |
$40.60 |
$6,712 |
Iraq |
$37.80 |
$1,372 |
Qatar |
$26.60 |
$29,235 |
Ecuador |
$7.80 |
$565 |
Indonesia |
-$4.20 |
-$18 |
Opec |
$674.70 |
$1,147 |
US crude futures have traded above $100 for most of the past three weeks and reached a record $111 on March 13. OPEC’s so-called basket price is cheaper than those futures, because OPEC oil is generally heavier and lower quality. OPEC pumps more than 40 per cent of the world’s oil. Oil prices have rallied against a backdrop of a
Adding to the gains are speculative investments in commodities as a hedge against inflation, as the value of the US dollar declines. OPEC’s net oil export revenue last year was $676 billion, according to EIA.
The basket has gained 73 per cent in the past year, rising from $58.20 a barrel on March 9, 2007. OPEC ministers last week ignored calls by US President George W Bush to increase output in order to help the global economy and, instead, left production targets unchanged at the meeting, giving 12 of its 13 members a combined quota of 29.67 million barrels a day. Some members, including
DNO confirms production sharing agreement with KRG
March 14, 2008. DNO has signed revised agreements with the Kurdistan Regional Government (KRG) amending the production sharing contract it holds for the Dohok and
POWER
Capacity crisis at JSW threatens global nuclear power plant production
March 17, 2008. A 100-year-old steel mill that once forged guns for the Japanese Imperial Navy has hit a production bottleneck that threatens to derail more than £150 bn of global nuclear power-plant construction. The capacity shortage at Japan Steel Works (JSW) has created a worldwide stampede among electricity producers to place orders with the Tokyo-based engineer for nuclear reactor cores a specialised component in which the company has an effective global monopoly. In some cases, European and American
Nuclear
Nigerian firm gives
March 14, 2008. Income Electrix Limited, a wholly African owned power solutions company has taken its competence beyond the shores of Nigeria, following its successful completion and commissioning of the phase one of a 36 MW Independent Power Plant (IPP) in Freetown, Sierra Leone recently. This first phase, with a capacity of 10 MW, is the first of the three IPP projects to be built by Income Electrix Limited under the country's three years emergency power plan. The diesel-fired plant, located on
Bulgaria thermal power plant for sale
March 14, 2008.
Singapore's Temasek sells power plant to
March 14, 2008.
Application has been filed to build a nuclear power plant in
March 14, 2008. Bruce Power Alberta will begin consulting people in the
Transmission / Distribution / Trade
Chinese firm pips REL, GMR to buy Tuas Power
March 17, 2008.
Russia's electricity monopoly sells stake in TGK-2 for $380 mn
March 14, 2008. A consortium of
The Russian electricity giant has also sold a 34.06% stake in another territorial generating company, TGK-6, to Integrated Energy Systems (IES holding) for 9.98 billion rubles ($421.3 mn). TGK-6 operates in four Russian regions and in Mordovia in the
Govt. approves project for improved supply of electricity
March 12, 2008. The works of the third phase of the Project of Rehabilitation and Expansion of the Luanda Electric Network, aimed at improving and increasing power supply in the capital, was recently approved by Angolan Government. Angop the Luanda Electricity Supply Company (Edel - E.P) signed a Usd 28.4 mn contract with China Machine-Building International Co.
The works to last 22 months, include the repair of the medium and low tension network of the Luanda Centre and South regions, with the supply and construction of the Section-Gaps 25 and 26, (Tourada) and (Morro Bento) areas, respectively. The project includes house connections and construction of two offices at the Ngola Kiluange and Maianga sub-stations. The rehabilitation and reinforcement of the
Policy / Performance
State regulators approve FPL plan for 2 more nuclear generators
March 18, 2008. Florida Power & Light can go forward with plans to build two new nuclear generators at its Turkey Point facility south of
Juno Beach-based FPL, which serves 4.5 million customers in 35 counties, said it must increase its electrical generation capacity by nearly a third to meet projected growth in demand between 2011 and 2020. Earlier this month, the state's second-largest electric company, Progress Energy
ANPP warns FG against electricity tariffs hike
March 18, 2008. The Federal Government must desist from its recent plans to hike electricity tariffs, the All Nigeria Peoples Party (ANPP) has warned. The party lamented that the plan to increase the tariffs was another way of perpetuating hardship in
UK's nuclear giant in takeover talks
March 17, 2008. Nuclear power station operator British Energy is in talks about a possible merger or takeover - and could fall into foreign hands. The company’s eight nuclear sites produce around one sixth of the
US plan would move nuclear waste to
March 17, 2008. A revised U.S. Department of Energy plan could send up to 9,000 containers of radioactive waste from southcentral
Marafiq releases RFP for power project
March 16, 2008. Power and Water Utility Company for Jubail and Yanbu (Marafiq), has announced the release of the Request for Proposals (RFP) for the Yanbu Independent Water and Power Project (Yanbu IWPP). This is the second IWPP project that is being tendered by Marafiq, the first being the Jubail IWPP, which achieved financial close in June 2007. The issuance of the RFP for Yanbu IWPP represents a major step forward in the development and privatization of the Kingdom’s water and power sector. The RFP is the product of significant work by various organizations in the Kingdom and has the full support of the Kingdom. This is also a reflection of the strong economy that the Kingdom is experiencing. Yanbu and Jubail industrial cities were symbols of the Kingdom’s strong growth in the industrial sector. The Yanbu IWPP’s production will meet the increasing demand for water and power in Yanbu Industrial City (YIC). Marafiq has issued the RFP to pre-qualified bidding groups to select a developer or a developer consortium to own 60 percent of a special-purpose project company that will build, own, operate and transfer (BOOT) the 1,700 MW and 150,000 cubic meters of water per day IWPP. The plant will be Cracked Heavy Fuel Oil fired, with Arabian Light Crude oil as backup. Marafiq will ultimately hold the remaining 40 percent of the shares in the project company. Marafiq’s owners are the Royal Commission for Jubail and Yanbu, Saudi Basic Industries Corporation, Saudi Aramco and the Public Investment Fund, each holding 24.81 percent. Private investors hold the remaining 0.76 percent. The project company will sell its entire capacity and output to a new off-taker company in Yanbu that is 100 percent owned by Marafiq. This will be done under a 25-year power and water purchase agreement with structured credit support from the Ministry of Finance. Bids are due to be submitted to Marafiq on August 27, 2008.
Jordan to hike electricity prices
March 13, 2008. The Jordanian government will raise the price of electricity later this week by up to 38 percent as the
China promotes new era of coal-fired
March 12, 2008. Despite global alarm about the threat that fossil fuel combustion poses to Earth's climate, coal appears poised to recover its 19th-century prominence as the world's top
Renewable Energy Trends
National
Tata BP Solar in deal for 128-MW project
March 17, 2008. Tata BP Solar has signed an agreement with Calyon Bank (Credit Agricole CIB) and BNP Paribas to raise $78 million to fund its 128-MW Solar Cell Expansion Project, which is in the advanced stages of implementation. The project eventually would be scaled up to a 180-MW solar cell manufacturing capacity. This is another step towards realising the designed potential of the 300-MW plant. The current manufacturing capacity of the company was 50 MW per annum. Tata BP Solar, a Tata Power and BP Solar joint venture, is
KSEB inks pact with wind
March 17, 2008. The Kerala State Electricity Board (KSEB) has signed agreements for purchase of power with four promoters of wind
DESI to take EmPower project to 10 more locations
March 17, 2008. Decentralised Energy Systems India Pvt Ltd (DESI) plans to expand its ‘100 village EmPower’ partnership programme to 10 more locations across
Commercial operations are running in four villages and 20 more will attain commercialisation in the next 18 months. DESI Power’s business model works by setting up low carbon, renewable
Signet signs MoU with TN to set up PV manufacturing unit
March 17, 2008. Signet Solar Inc, manufacturers of silicon thin film photovoltaic (PV) modules, will set up its first manufacturing plant at Sriperumbudur at an investment of Rs 2,000 crore ($491.3 mn) and has signed an MoU with the Tamil Nadu government in this regard. According to the company the construction of the 300 MW facility would begin later this year. The technology and manufacturing knowhow for the plant would be transferred from the company's German operations. The plant was expected to generate about 4,000 direct and indirect job opportunities. The Chennai plant would be the company's next major manufacturing unit after its German plant, with a planned capacity of over 300 MW of solar panels, produced every year.
The company's decision to expand manufacturing in
Eight small hydro projects set up in Manipur
March 15, 2008. The country had 615 small hydro power projects upto 25 MW aggregating 2108 MW as on 29.2.2008. Out of 615 projects, eight projects aggregating 5.450 MW were set up in Manipur. Sixty-eight projects aggregating 45.240 MW were Arunachal Pradesh; four projects aggregating 27.110 MW in
According to the Union Minister of State for New and Renewable Energy Shri Vilas Muttemwar stated that 5,403 potential sites were identified in the country to install small hydro projects. The projects would have a total capacity of 14,294.24 MW. Out of 5,403 sites, 113 sites with a total capacity of 109.10 MW were in Manipur. Five hundred sixty six sites with a total capacity of 1333.04 MW were in Arunachal Pradesh; 60 sites with 213.84 MW in
Gore:
March 15, 2008.
No renewable
March 12, 2008. The Union Government has set a target to generate 80,000 MW from conventional sources over the next four years, and is investing Rs 60,000 crore ($14.9 bn) in that period to generate, distribute and transmit electricity. However, the Union Power Minister, Mr Sushilkumar Shinde, has said that there is no policy in place as yet that makes it mandatory for a percentage of all power generated by a certain date to come from renewable sources. According to him there is a shortfall of 25,000 MW in the country today. In the last three five-year Plans, only 21,000 MW of the targeted 42,000 MW was added.
Goldstone Infra to foray into renewable sector
March 12, 2008. Goldstone Infratech Limited (formerly Goldstone Teleservices Limited), the country's largest manufacturer and supplier of composite insulators, is foraying into the renewal
The company would initiate work on phase-II in six months from now. The company would primarily be targeting the European and the
First integrated renewable
March 12, 2008. Gurgaon-based R.S. India Group is setting up the first integrated renewable
The project is being set up with lease financial assistance of Rs 487 crore ($120.8 mn) by the Power Finance Corporation Ltd. The promoter, R.S. Group, is investing Rs 100 crore ($24.8 mn) in it, and the Power Trading Corporation has a 37 per cent equity participation in the new company formed for the purpose, R S India Wind Energy Pvt Ltd (RSIWEL) amounting to Rs 54 crore ($13.4 mn).
The first of the wind turbines, being put up by Denmark-based Vestas RRB, would be in place by the end of the month. The second phase will be commissioned by December, while a third phase, which would be financed through debt, is also on the anvil taking the total installed capacity to 500 MW by the end of 2009. The location of the facility has not yet been finalized.
Global
Green
March 16, 2008. Green Island Energy Ltd., a private B.C. power developer, says it has struck a deal with Covanta Holding Corp., a New Jersey-based
This project would be a boost to
Fluitecnik buys a Spire solar module manufacturing line
March 14, 2008. Spire Corp. received a contract from the solar division of Spanish renewable
Spire will supply the process technology and training to operate the factory, as well as assistance in qualifying the factory and its modules to meet International Electrotechnical Commission (IEC) standards and certification. The line will integrate Spire's key stringing and tabbing, lamination and testing machines along with intermediate tooling stations. The line will be designed to be easily expandable at a later date. Spire recently completed a 12 MW crystalline cell module line, expandable to 20 MW, for Fluitecnik in the
Wisconsin to purchase wind power from Minnesota
March 14, 2008. Wisconsin Public Service Corp. (WPSC), a subsidiary of Integrys Energy Group Inc. will buy wind power from a wind farm planned for southeastern
Davenport receives funding for newberry geothermal project
March 14, 2008. Ore.-based electric supplier Davenport Power will receive development capital for its Newberry geothermal project from US Renewables Group and Riverstone Holdings. Initial funds will be used to drill exploratory test wells in potential geothermal resource areas for underground geological features that have the right combination of heat and water to produce steam. If exploration is successful and a viable commercial resource is found during the exploratory drilling,
Petrobras and Mitsui to form bio
March 13, 2008. Petrobras and Mitsui signed documents needed to incorporate a company in
Dear Reader, You may have received complimentary copies of the ORF Energy News Monitor. Our objective in bringing out the newsletter is to provide a platform for focused debate on We look forward to receiving your patronage and support. ORF Centre for Resources Management |
ORF ENERGY NEWS MONITOR Subscription Form Please fill in BLOCK LETTERS |
Subscription rate slabs for Commercial entries, Research Institutes, Academics and Individuals will be provided on request. The subscription can be made for soft copy or for hard copy or for both. Selected ORF publications as well as advertising space in one issue of the ORF Energy News Monitor are offered as introductory free gifts for Commercial Sector only. |
Yes! I/we would like to receive copies of the weekly ORF Energy News Monitor for a period of ______year(s). I/we shall be entitled to one hard copy along with the option of soft copies to a list of e-mail addresses provided by me/us for the period of subscription. I/we also note that I/we shall get select ORF publications brought out during the period of subscription free. Name……………………………Address…………….………………………Telephone……………………Fax………………….E-mail………………… Please find enclosed cheque/Bank Draft No.........................dated …………………drawn at Please fill in this form and mail it with your remittance to ORF Centre for Resources Management OBSERVER RESEARCH FOUNDATION 20 Rouse Avenue New Delhi - 110 002 Phone +91.11.4352 0020 extn 2120 (Janardan Mistry) Fax: +91.11.4352 0003 E-mail: [email protected] |
Registered with the Registrar of News Paper for
Published on behalf of Observer Research Foundation,
Disclaimer: Information in this newsletter is for educational purposes only and has been compiled, adapted and edited from reliable sources. ORF does not accept any liability for errors therein. News material belongs to respective owners and is provided here for wider dissemination only. Sources will be provided on request.
Publisher:
Production team:
The views expressed above belong to the author(s). ORF research and analyses now available on Telegram! Click here to access our curated content — blogs, longforms and interviews.