-
CENTRES
Progammes & Centres
Location
Imported Coal Power Purchase Obligation (ICPPO) can bring uniformity in tariffs
Ashish Gupta, Observer Research Foundation
U |
nderstanding the situation that it is a necessity for
As we are aware that around 43,000 MW worth of power projects are awarded under competitive bidding route in which 13,000 MW are based on imported coal. These imported coal projects will be major sufferer as prices of coal rises significantly in the international market but the increment cannot be passed on to the consumers because under the competitive bidding route, power producers have to abide by the tariff quoted by them. Given
Yes, there is solution and it is working well for the renewable sector through Renewable Purchase Obligation (RPO) which is the minimum amount of energy to be purchase by the state utilities in order to meet the renewable targets and utilities are bound that portion of the electricity that they are supplying should be through renewable plants.
The prevailing situation demands for imported coal not only for projects based on imported coal but for other power plants as well. Seeing India’s requirement for coal imports, the above obligation for renewable energy may be replicated for imported coal in the form of Imported Coal Power Purchase Obligation (ICPPO) where in all utilities are mandated to procure some percentage of imported coal based power. The idea is to provide a level playing field for all the power plants and just not to provide cushion for imported coal based plants. The obligation could be removed in the future when domestic production increases. But the major hurdle is to get consensus as many states that have got cheap coal linkage will not be willing to take up additional obligations. Another hurdle is investment which will be required by the power plants for installing equipments which can accommodate imported coal as many of the power plants having technology for indigenous coal only.
Having said this, leaving behind the problems, implementing such kind of obligation will not only help in rationalizing the prices but also bring uniformity in tariffs across the country. The adoption of approach while implementing such obligation should be done in a manner where the interests of small & medium power projects will not be hampered and every one in the chain can achieve economies of scale.
ENERGY
Will a Trillion Dollars meet a Billion aspirations?
Lydia Powell, Observer Research Foundation
T |
he 12th Five Year plan estimates for infrastructure investment to sustain a growth of 9-9.5 percent in the next five years is about a trillion dollars, double that of the 11th plan period. The target for the 11th plan is said to have been met barring a few billion dollars with about 36 percent of the investment coming from the private sector. In the 12th Plan period, over 50 percent of investment in infrastructure is expected to come from the private sector in what has come to be called Public Private Partnerships (PPP). Even if anticipated investment materializes during the 12th Plan period, will it actually meet the aspirations for energy, transportation, housing and education of over billion people?
Public Private Partnerships are often seen as the best mix of public provision and privatization. In
As a recent paper points out, one of the arguments put forward to promote the case for PPPs is that ‘there is no alternative’. It is said that financial constraints on borrowing by the Government and a reluctance to increase user charges or taxes means that power projects or roads will not be built without PPPs. This argument is not necessarily true especially after the financial crisis which requires Governments to increase public spending and borrowing to support the financial sector and the economy. A serious problem with this argument is that it is used to dismiss the need to show value for money. If there is no alternative then it cannot be compared with anything to demonstrate that it is not offering value for money.
The second argument is that PPPs are better because they do not cost the public or the public sector anything. It is believed that the Government does not have to pay anything for public infrastructure projects built through the PPP mechanism and therefore the Government can spend on other worthy causes such as rural economic revival programmes. This is also untrue as construction of projects is financed with public funds or user revenue. Money is borrowed from the same financial institutions as PPPs do not access some special new source of finance. Over the life of a project it is very likely that PPPs will involve higher public spending than a conventional project because of higher cost of capital.
Then there is the notion that PPPs allow for risk transfer or risk sharing. In PPPs risk is said to be transferred to the private sector but what is not said is that this ‘risk transfer’ is not free. Contracts which transfer risks to the private partner such as delay in construction to the private partner typically cost 25 percent more than conventional contracts. Risk transfer may not always be the best solution for a delay in execution may cost the public sector more than what it paid for ‘risk transfer’. The IMF has cautioned that Governments may overprice risks and over compensate the private sector which would raise the cost of PPPs relative to direct public investment.
There is also the oft repeated argument that the private sector is more efficient than the Government and that they can finance projects cheaply and easily and operate services more efficiently. The first claim is clearly untrue as most Governments around the world can borrow more cheaply than private companies. The second claim has been disproved by a number of empirical studies. A study on electricity utilities in the
It must be kept in mind that PPPs do not come out of vacuum. They need to be created and this involves a significant transaction cost. Often these transaction costs make PPP projects far more expensive than public projects. Private companies have a vested interest in exaggerating the expected demand for a service and for projecting lower cost for setting up the service to get the project approved. A global study found that 90 percent of all rail and road projects had underestimated cost and overestimated demand. Renegotiations which are so common in PPP projects always favour of the private sector. Take the case of the
Governments speak about progressive ‘Partnerships’ between the ‘Public’ and ‘Private’ sector that will bring roads, energy and water but in reality Governments are abdicating their responsibility in providing basic services and giving away market share in public service provision to private companies at a discount. When PPPs boost cost and increase charges to make profits what they are essentially doing is pricing common people out of access to public services.
Globally, the concept of PPP has opened a large market for many companies. The shares of the 75 largest companies providing infrastructure services which account for the largest proportion of PPPs in a global index increased by over 250 percent over six years from 2001 compared to global average of 100 percent increase for all major companies. Financial institutions including specialist private equity firms operating so called infrastructure funds are actively buying into infrastructure PPPs. The largest of these is said to be the Australian Bank Macquarie. The underlying attraction of the investment is a reliable cash flow from essential services or government guaranteed payments. At the end of five years the Government may proudly say that a trillion dollars was invested in infrastructure but that may not mean that a billion aspirations have been met.
RENEWABLE ENERGY
Absorbing Latest Technologies and Repowering Wind Energy
Sonali Mittra, Observer Research Foundation
W |
ind energy is the fastest growing renewable sector in the country. With a cumulative deployment of over 13,000 MW capacity, it nearly accounts for 70% of the renewable energy installed capacity. The Ministry of New and Renewable Energy has been at the forefront of providing the support for accelerated development of wind energy through proactive and regulatory interventions so far, but there is definitely a need to revise the policies and introduce new innovative measures for optimal potential utilization of wind energy resource.
In the latest information released by the Ministry of New and Renewable Energy (MNRE), wind energy potential stands at 49, 130 MW at a height of 50m, as compared to earlier estimates of 45,000 MW. The Ministry has established 653 wind monitoring stations in the country through Centre for Wind Energy Technology (C-WET), Chennai for carrying out wind resource assessment. A second phase has already been initiated to assess potential of wind energy at a height of 100 m in 75 locations and at 120 m height in 4 locations. To harness this vast potential being explored with new assessment studies, it is being inherently realized that planning needs to done for developing the wind technology.
Technologies of megawatt class wind turbine have been changing all over the world. According to Dr. S. Gomathinayagam, executive director C-WET, wind power assessments have been extended to match the latest technologies available, for instance, taller towers with larger diameter rotors suitable for the Indian market. This is further pushed by the fact that the Indian market has matured over the past few years as a result of improvement in infrastructure available to handle bigger turbines and economics of the sector. The multi-megawatt turbines installed at a greater sub-height have allowed a single power generator to capture more energy per tower. Subsequently, larger machines have resulted in a steady increase in the capacity factor on average from 10-12% to 20-22%. Currently, megawatt-scale turbines account for over half the new wind power capacity installed in
The technological advancement and the new found result of the assessment studies in the sector demands for policy interventions for two main areas. One, given finding sites and establishing transmission corridors is a significant investment, government needs to make sure that the developers maximize the use of available sites for wind power generation, utilizing the latest technology available. Installing fewer higher capacity turbines versus installing a greater number of smaller turbines reduces overall capital investment by lowering installation, maintenance and potentially real estate cots, thereby being most cost-effective and energy efficient. Two, government should encourage repowering of old wind farm on a large scale. Replacing old turbines with new designs would bring considerable benefits to states which face power shortages and also are host to sites with good wind power potential, which is not being used efficiently at the moment. Currently, neither the states nor the central government provides dedicated policy support or incentives to bolster Indian wind power developers or investors to repower their old projects.
Therefore, a new policy package should be developed to address repowering incentives as well as providing appropriate buoyancy to the latest technologies available in the market at the new sites, for overall improvement in the capacity utilization of wind energy resource.
DATA INSIGHT
Region-wise Hydro Electric Potential & Achievement
As on March 31, 2012
Akhilesh Sati, Observer Research Foundation
Region/States |
Identified Capacity |
Capacity Developed |
||
Total (MW) |
Above 25 MW |
in MW |
in % (of above 25 MW) |
|
NORTHERN |
||||
Jammu & Kashmir |
14146 |
13543 |
2340 |
17.28 |
Himachal Pradesh |
18820 |
18540 |
7293 |
39.34 |
Punjab |
971 |
971 |
1206.3 |
100 |
Haryana |
64 |
64 |
0 |
0 |
Rajasthan |
496 |
483 |
411 |
85.09 |
Uttarakhand |
18175 |
17998 |
3426.4 |
19.04 |
Uttar Pradesh |
723 |
664 |
501.6 |
75.54 |
Sub Total (NR) |
53395 |
52263 |
15178.3 |
29.04 |
WESTERN |
||||
Madhya Pradesh |
2243 |
1970 |
2395 |
100 |
Chhattisgarh |
2242 |
2202 |
120 |
5.45 |
Gujarat |
619 |
590 |
550 |
93.22 |
Maharashtra |
3769 |
3314 |
2487 |
75.05 |
Goa |
55 |
55 |
0 |
0 |
Sub Total (WR) |
8928 |
8131 |
5552 |
68.28 |
SOUTHERN |
|
|
|
|
Andhra Pradesh |
4424 |
4360 |
2177.8 |
49.95 |
Karnataka |
6602 |
6459 |
3585.4 |
55.51 |
Kerala |
3514 |
3378 |
1881.5 |
55.7 |
Tamilnadu |
1918 |
1693 |
1722.2 |
100 |
Sub Total (SR) |
16458 |
15890 |
9366.9 |
58.95 |
EASTERN |
|
|
|
|
Jharkhand |
753 |
582 |
233.2 |
40.07 |
Bihar |
70 |
40 |
0 |
|
Orissa |
2999 |
2981 |
2027.5 |
68.01 |
West Bengal |
2841 |
2829 |
77 |
2.72 |
Sikkim |
4286 |
4248 |
570 |
13.42 |
A & Nicobar |
0 |
0 |
0 |
|
Sub Total (ER) |
10949 |
10680 |
2907.7 |
27.23 |
NORTH EASTERN |
|
|
|
|
Meghalaya |
2394 |
2298 |
240 |
10.44 |
Tripura |
15 |
0 |
0 |
|
Manipur |
1784 |
1761 |
105 |
5.96 |
Assam |
680 |
650 |
375 |
57.69 |
Nagaland |
1574 |
1452 |
75 |
5.17 |
Arunachal Pradesh |
50328 |
50064 |
405 |
0.81 |
Mizoram |
2196 |
2131 |
0 |
0 |
Sub Total (NER) |
58971 |
58356 |
1200 |
2.06 |
ALL |
148701 |
145320 |
34204.8 |
23.54 |
Source: Central Electricity Authority
NEWS BRIEF
NATIONAL
OIL & GAS
Upstream
Reliance cuts
May 8, 2012. Indian energy conglomerate Reliance Industries has cut estimates for proven gas reserves in its Indian blocks by 6.7 percent to 3.67 trillion cubic feet, it said. Reliance's growth outlook has been marred by falling gas output from its huge gas fields, with production less than half of what was originally estimated.
Oil drilling firms such as RIL, ONGC, SGPC face sea of troubles in KG Basin
May 7, 2012. Once seen as the solution to
DGH rejects commerciality of RIL gas finds
May 7, 2012. DGH has refused to recognise two significant natural gas discoveries that Reliance Industries had made in a
Cairn-Vedanta deal: Ex-ONGC Chairman RS Sharma denies foul play
May 5, 2012. Former chairman of ONGC RS Sharma stoutly denied any foul play or lapses by the state-owned company while approving the recently concluded $8.5 billion Cairn-Vedanta deal. This comes after the Supreme Court, taking cognizance of a public interest suit that sought criminal investigation as well as scrapping of the Cairn-Vedanta deal, issued notices to the government, Cairn Energy, Vedanta and ONGC.
ONGC undertakes massive exploration campaign in
May 3, 2012. State-run energy explorer has taken up a massive exploration campaign in the Chambal Valley of Rajasthan. In that area, ONGC is operating in three NELP Blocks - VN-ONN-2003/1, VN-ONN-2004/1 and VN-ONN-2004/2 awarded by the Government of India and the blocks encompass districts of
MRPL restarts 2 of 3 crude units
May 7, 2012. Mangalore Refinery and Petrochemicals Ltd (MRPL) has restarted two of three crude distillation units (CDUs) at a 300,000 barrels-per-day (bpd) plant that was closed more than a week ago following water shortages. The last of the CDUs is undergoing maintenance and is expected to restart in the second-half of May.
Numaligarh refinery extends shutdown to end-May
May 7, 2012.
Hindustan Petroleum delays Vizag plant maintenance
May 3, 2012. Hindustan Petroleum Corp has delayed maintenance plans at a crude unit and a secondary unit at its Vizag refinery in south
BPCL arm Bharat
May 2, 2012. Bharat Oman Refineries, a company promoted by state-run Bharat Petroleum Corporation with equity participation from Oman Oil Company, is raising $140 million (` 737 crore) of external commercial borrowing for its refinery project at Bina in Madhya Pradesh. BORL will raise the US-dollar term loan at an annual interest rate of 3.45% above Libor, or
Transportation / Trade
Diesel pipeline of
May 4, 2012. An Indian oil Corporation (IOC) diesel pipeline, connected from the
Pak to cap oil imports from
May 3, 2012. Pakistan is considering a proposal to limit oil imports from
Policy / Performance
IGL-PNGRB case adjourned again to May 22, 2012
May 8, 2012. IGL's (Indraprastha gas limited) hearing in the high court against the petroleum and natural gas regulatory board (PNGRB) has been adjourned to May 22, 2012. The sole supplier of compressed natural gas in Delhi/NCR has appealed in the court against the regulatory board's decision to regulate its network tariff and selling price. PNGRB in its order dated April 9, 2012 has asked IGL to cut down its network tariff by 63%. In a retrospective decision, it also asked the company to refund the difference to its customers for the period from April 1, 2008 till the date of issuance of order. IGL in its petition has however alleged that PNGRB is not entitled to regulate the price of gas sold by the company and the variables taken into account by the board to calculate the network tariff are misleading.
Gas consumption to jump to 356.16 mmscmd by 2014-15, says Jaipal Reddy
May 8, 2012. Oil minister Jaipal Reddy has said natural gas output from Reliance Industries' D6 block would drop to 20 million standard cubic meters per day in 2014-15 but output of coal bed methane would raise domestic gas production marginally.
The minister projected a wide gap between gas demand and supply of domestic output, which would be met by importing liquefied natural gas (LNG).
Domestic production of natural gas has fallen sharply because output from Reliance-operated D6 block, which started falling since March 2010 after achieving a peak of 61.8 mmscmd. The block's current output is about 34 mmscmd and according to Reddy it will average at 28 mmscmd in the current financial year. The output from D6 is expected to be around 24 mmscmd in 2013-14, Reddy said.
Reliance says that the block's output is on a decline because of geological complexities. But the oil ministry did not agree with RIL and on May 2 it slapped a notice to the company disallowing about $1 billion cost recovery. The government wants to deduct the amount from Reliance's share of profit from the field as it feels the company should be punished for building excessive infrastructure, which is now idling. RIL executives say the same facilities will be fully utilised and help cut costs drastically when it develops 16 new discoveries in the same block.
The oil ministry said,
India vows cuts in Iranian-oil imports as
May 8, 2012.
India is “certainly working toward lowering their purchase of Iranian oil” and “we hope they will do even more,”
RIL says unexpected geology shrank KG-D6 output; oil ministry unconvinced
May 8, 2012. Mounting mistrust between the oil ministry and Reliance Industries has cast a cloud on the future of the prized D6 block as the government continues to maintain a stern posture toward the company while RIL struggles to justify further expenditure on the deep-sea block it operates.
Matters came to a head when the ministry issued a notice to RIL saying it will disallow reimbursement of $1 billion from RIL's field-development costs as gas output has fallen sharply, leaving many facilities unutilised. RIL will be allowed to recover all its costs if gas output rises to previously projected levels, but the uncertainty, company say, is making operations difficult. RIL says gas output fell because of unexpected geology, and it plans to use the currently surplus infrastructure to pump gas from other fields in the region, but the government is unconvinced.
The oil ministry is contemplating further restrictions on recovery of development costs in the next two years, when output is projected to fall further, and it has no immediate plans to approve the block's budgets for the past two fiscal years unless the company accepts the deduction in the costs it can recover, oil ministry said.
India said to deny local branch for Iran bank on
May 7, 2012.
Assocham calls for variable diesel price hike
May 7, 2012. Industry body Assocham has called for variable pricing of diesel linked to end-consumers and early creation of fuel-pipeline-grid. Graduated steps should be taken towards market determined prices for diesel rather than de-regulation of the pricing system in one go, Assocham said. As for the pricing, the full market price should be charged for diesel used for moving large cars and luxury buses, while the increase should be very moderate for others to begin with, Assocham said. Smaller farmers should be exempt for sometime and in phases should be increased. Assocham has also suggested that the government should encourage replacing old vehicles, especially trucks, modern trailers with high efficiency engines.
'Petro sector contributed ` 1.88 tn to exchequer'
May 4, 2012. The petroleum sector contributed about ` 1,88,909 crore in the last two fiscals to the central exchequer. The contribution of petroleum sector to the central exchequer is ` 1,02,827 crore in the financial year 2010-11 and ` 86,082 crore in the year 2011-12 (up to February 2012), Minister of State for Finance S S Palanimanickam said. He said while in 2010-11, a total of ` 1,02,827 crore was collected in revenues from customs and cess on crude oil and petroleum products, in the 2011-12 fiscal, up to February this year, as much as ` 86,082 crore was collected through the same. The central government has from time to time impressed upon the states to reduce the state levies in line with the duty cuts undertaken by the central government, he said. Replying to another query, Palanimanickam said central excise duty comprises 22.5 per cent in the price of petrol, which costs ` 65.64 per litre in
DGH drafts new policy on exploitation of shale gas
May 4, 2012. In the wake of the CAG’s strictures against the Directorate General of Hydrocarbons (DGH) and the Petroleum Ministry on violations in the KG-D6 contract the DGH has now drafted a safe but encouraging policy on exploitation of shale gas. Shale gas is seen as the new hope for fuelling
Oil Ministry hikes penalty on RIL by 18 pc to $1.4 bn
May 4, 2012. The Oil Ministry has hiked the penalty it wants to impose on Reliance Industries and its British partner BP plc for falling natural gas output from KG-D6 fields, by 18 per cent to $1.46 billion. The Ministry had previously wanted to disallow $1.235 billion expenditure that RIL had incurred on putting production facilities at the
Indian petroleum industry continues to bleed heavily on under-recoveries
May 3, 2012. A marginal fall in Brent crude oil prices is not helping
Indian Govt in a bind over Cairn plea to sell crude to RIL refinery
May 2, 2012. Cairn India has sought government's permission to sell crude oil to Reliance Industries' refinery in the special economic zone (SEZ), putting the oil ministry in a fix because such supplies are regarded as deemed exports, which are forbidden by the production sharing contract. The oil ministry has recently allowed Cairn to raise crude oil output from its Rajasthan block by 17% to 8.785 million tonne in 2012-13 from 7.5 million tonnes. It plans to sell 3.25 million tonnes to Essar, 3.96 million tonnes to the other refinery of Reliance Industries, which sells products in the domestic market, and the balance to state-run MRPL and IOC.
Oil Ministry seeks clarifications from RIL on CBM gas price
May 2, 2012. Days ahead of the 60-day deadline for approving its gas sale price expired, the Oil Ministry has sought some clarifications from Reliance Industries on the gas it plans to produce from coal seams (CBM), thereby pushing back the approval clock by another two months. The Ministry had said that the contract with firms like RIL and Essar Oil, for producing coal bed methane (CBM) or gas from coal seams, provides for approval of the sale price formula within 60 business days "from the date of receipt of proposal or from the date of receipt of clarifications/additional information". RIL had submitted a proposal seeking a price of equivalent to 12.67 per cent of price of JCC, or Japan Customs-Cleared Crude oil, plus USD 0.26 per million British thermal unit (mmBtu), for the CBM it plans to produce from Madhya Pradesh blocks from end-2014.
Petronet to build LNG plant in
May 2, 2012. Petronet LNG Ltd. will invest ` 45 billion ($853.89 million) to build a liquefied natural gas (LNG) terminal on the country's east coast by 2016 to help meet the growing demand of the energy-hungry nation. Companies are building LNG import and regasification facilities on the east coast to meet demand of eastern and central part of
Oil companies asked to remove backlog of cylinders in
May 2, 2012.
POWER
Generation
Coal position at thermal power plants continue to be critical
May 8, 2012. Coal stock position at the thermal power stations in the country continue to be critical with as many as 29 plants receiving less fuel, leaving them with stocks for less than a week. As per latest CEA ( Central Electricity Authority) data (May 6), 29 power plants across the country have less than seven days of fuel stock including 14 stations that have only less than four days of stock. Of the 29 stations, 10 received less fuel while another two are reeling under inadequate fuel linkages. However, the reasons for this situation have not been mentioned in the report. State-run NTPC's thermal plants at Kahalgaon (Bihar) and Farakka (
Hydel power generators missed their generation target by about 4 pc during Apr 2012
May 7, 2012. Hydel power generators missed their generation target by about 4% during April 2012 against an excess generation of 18% during the previous corresponding period. According to figures released by the Central Electricity Authority, the hydel power units were to generate 8368 million units of electricity during April 2012. However, they managed to generate about 8041 million units during the period - a shortfall of 326 million units. During the previous corresponding period, the target for the month was set at 7521 million units and they generated 8874 million units, which was 1353 million units more than the target. Hydel units in southern
80 GW power generation capacity under construction: Govt
May 7, 2012. A mammoth 80,000 MW power generation capacity is under construction during the 12th Five Year Plan period ending March 31, 2017, Power Minister Sushilkumar Shinde said. He said that 21,000 MW of electricity generation capacity was added during 10th Plan period against the target of 42,000 MW. For the 11th Five Year Plan (2007-12), a target of 78,775 MW was set which was revised to 62,000 MW during mid-term appraisal. The actual capacity addition was 55,000 MW. Shinde said that in 2011-12 20,400 MW power generation capacity was added, which was much higher than the projection of 17,000 MW.
Madhucon Projects' first power project takes off
May 5, 2012. Infrastructure firm Madhucon Projects announced that its first coal-fired power project with a capacity of 150MW has commenced commercial operations. The power project, with a total capacity of 1,920MW to come up in three phases near Krishnapatnam in Andhra Pradesh, is being implemented by special purpose vehicle Simhapuri Energy Pvt Ltd. The first phase of the project will have two units of 150MW each and second phase will have similar capacities. In the third phase, the company plans to have two units of 660MW each. The company said the second unit of 150MW is expected to be operational by June, while two units of 150MW each in second phase are expected to begin operations before the year-end.
Mundra UMPP next unit to begin operations in August: Tata Power
May 4, 2012. Tata Power said it expects to commission the second 800-MW unit of its Mundra ultra mega power project (UMPP) in
Transmission / Distribution / Trade
Mafia using luxury coaches to transport coal
May 8, 2012. The police warned owners of luxury buses against colluding with the coal mafia to transport illegally-mined coal through NH-33 in Hazaribag and Ramgarh districts. Luxury buses carrying passengers have allegedly been carrying illegally-mined coal on the roofs of their vehicles and unloading it at specified spots. So long the police had focussed on trucks, tri-cycles and bi-cycles which are engaged in the transport of illegally-mined coal. Only last month the police seized tons of it.
Power distribution cos' losses cross ` 2k bn, says Crisil
May 7, 2012. The losses of power distribution companies crossed ` 2 lakh crore at the end of March this year, as lower consumer tariffs and higher fuel costs continued to hurt their bottom lines, according to Crisil. Analytical firm Crisil also said there should be about 6.5 per cent hike in electricity tariff per annum in the next five years, which would help in improving the health of distribution companies (discoms). There are about 89 discoms in the country. The estimates come against the backdrop of precarious financial health of discoms raising concerns of default in the banking system. The overall exposure of discoms to financial institutions is estimated to be ` 2.6 lakh crore. As per Crisil, power tariffs in
Vadodara saves ` 35 mn in street light consumption
May 6, 2012. The Vadodara Municipal Corporation (VMC) has taken action for energy efficiency in street light services and has been able to save energy worth ` 3.5 crore in a year. VMC said by implementing the international level lighting and intelligent street light controllers with GSM monitoring the yearly energy bill of the VMC is reduced to ` 10 crore from ` 13.50 crore. VMC got the national award for 'Energy Conservation in Street Lighting' by the Bureau of Energy Efficiency (BEE). Total area of coverage of VMC is 160 sq km and its total population is over 16 Lakh for which 1,691 km of street lighting is covered in Vadodara.
Power bills under BSES to go up, decline for Tata consumers
May 2, 2012. People getting power supply from BSES discoms will have to shell out more on electricity bills while consumers under Tata Power distribition limited will benefit from a marginal drop in the rates. Power regulator Delhi Electricity Regulatory Commission (DERC) increased power tariff by two per cent for consumers under BSES Yamuna Power Ltd while one per cent hike has been effected for consumers under BSES Rajdhani Power Ltd. The tariff has been brought down by one per cent for consumers getting supply from Tata Power Delhi Distribution Limited. The regulator adjusted the tariff-based power purchase cost of the distribution companies and the new tariff will be effective from May 1 for three months, DERC said.
CEA to meet power firms over CIL penalty clause
May 8, 2012. Power companies that have not signed the fuel supply pact with Coal
India’s dependency on imported coal forcing changes in power plants
May 8, 2012. India’s rising dependency on imported thermal grade coal and Coal India Limited’s (CIL) new fuel supply agreements (FSAs) based on imports have forced drastic technical changes on power generating companies, project developers and power equipment manufacturers. With the Coal Ministry projecting coal imports of 250-million tons by 2017, technical specifications of existing and planned thermal power plants have to be modified to accept a blend of domestic and imported coal of higher gross calorific value (GCV) with the latter not constituting less than 30%. Current Indian thermal power plants were designed to use blended feedstock with a maximum 15% import content of higher GCV.
Coal at cheaper rates to meet power requirements: Govt
May 7, 2012. Defending the move to force Coal
Reliance Power's Krishnapatnam UMPP may not be figure in 12th Plan projects
May 7, 2012. The government may not include Reliance Power's 4,000 MW ultra mega power project, at Krishnapatnam in Andhra Pradesh, in its proposal for additional 1 lakh MW power generation in the next five years. The firm, which is setting up the project, has filed a petition in the Delhi High Court after its principal coal supplier,
Rajasthan villages may get 24 hour power supply
May 6, 2012. All villages in Rajasthan are likely to get 24-hour power supply by March next year with the installation of 550 KV Grid stations across the State. For every three village panchayats, a 33 KV sub-station is being constructed, while 132 KV sub-stations would be established wherever needed. State Energy Minister Jitendra Singh said over the weekend that these would be the “encouraging results” of multi-pronged power sector reforms in production, transmission and distribution. Rajasthan had emerged as a leading State in the power sector.
Tata Power plans 15 mt coal import in FY13
May 4, 2012. Tata Power plans to import 15 million tonnes (mt) of coal during the year to March 2013. Coal accounts for more than half of
Power tariffs to be linked to fuel costs; move would hurt consumers but help new UMPPs
May 3, 2012. The power ministry will allow producers to raise tariffs if fuel costs of new projects rise, and will not oppose a hike in domestic gas prices. The move would hurt consumers but rescue large private investments that are threatened by uncertainty over fuel and tariffs. Linking tariffs to fuel costs will help new power projects, such as the next set of ultra mega power plants (UMPPs) yet to be awarded, and gas-fired electricity plants with a capacity of over 7,000 MW that have been built but are idling because of fuel scarcity, Power Minister Sushilkumar Shinde said.
INTERNATIONAL
OIL & GAS
Upstream
Rosneft, Statoil sign deal on developing fields in
May 7, 2012.
Petrobras announces O&G production in March 2012
May 7, 2012. Petrobras announces that its average oil and natural gas output in March, in
Libya’s NOC says Agoco hasn’t cut crude output
May 6, 2012. Libya’s Arabian Gulf Oil Co. (Agoco) has not reduced crude production, its parent National Oil Corp. (NOC) said. The company had reduced output by 30,000 barrels a day to about 340,000 barrels a day because protesters had been blocking the entrance to its headquarters for more than a week. National Oil denied that Agoco has decreased production.
Freedom from Gazprom tempts
May 2, 2012. For the first time in more than two centuries,
Sudan has restarted oil production from Heglig
May 2, 2012.
Wien bearish on oil for first time as production swells
May 2, 2012. Byron Wien, the chairman of Blackstone Group LP’s advisory services unit, is forecasting an annual drop in oil prices for the first time in his career as swelling production pushes global inventories higher. Wien said the
Transportation / Trade
Fuel-oil shipments to
May 7, 2012. Fuel-oil shipments to
TransCanada re-applies for Keystone XL pipeline permit
May 5, 2012. TransCanada Corp. has re-applied for a
Zhuhai Zhenrong books May fuel-oil shipment from
May 4, 2012. Zhuhai Zhenrong Co., the Chinese company censured by the
Pakistan LNG import plan in jeopardy as companies miss deadline
May 4, 2012. The LNG import plan has been put in jeopardy as all three LNG importers - Turkish firm Global Energy,
Iran may lose 9.5 pc of oil contracts as Asian buyers cut imports
May 4, 2012. Iran is poised to lose at least 192,000 barrels a day of crude-supply contracts, or about 9.5 percent of its global exports, as Asian buyers curb purchases amid western sanctions targeting the nation’s oil trade. Mangalore Refinery & Petrochemicals Ltd. and Essar Oil Ltd.,
Iran embargo impossible to meet as ships need its oil
May 3, 2012. Europe’s oil embargo on
Trafigura following raffles into heart of Asian trade
May 3, 2012. Staff at Trafigura Group, the third- largest independent oil trader, are getting a real-time snapshot of demand in the top crude and metals-consuming region as they look from their new office onto lines of ships off
MPC considering reversal of Capline pipeline
May 2, 2012. Marathon Petroleum Corp. (MPC) is exploring the possibility of reversing a major pipeline to bring oil from the Midwest to the
Supertankers delayed in china as nation fills strategic reserves
May 2, 2012. Delays emptying supertankers at ports in
Policy / Performance
Putin return lifts futures:
May 8, 2012. Russian stock futures climbed as Vladimir Putin returned to
Record gas use by
May 7, 2012.
Kuwaiti Co to invest in O&G exploration
May 6, 2012. Chairman and Managing Director of Kuwait Foreign Petroleum Exploration Company (KUFPEC), Nizar M Al-Adsani has called on Federal Minister for Petroleum & Natural Resources Dr. Asim Hussain to discuss KUFPEC's continued involvement in the oil and gas sector of
Frack first, disclose chemicals later under
May 4, 2012. Oil and natural gas companies won’t be forced to disclose chemicals used in hydraulic fracturing until work is completed, under a proposed U.S. rule issued that drew opposition from environmental groups. The proposal lets gas producers exclude trade secrets and confidential information. It would add about $11,833 in costs per well in 2013. President Barack Obama has pledged to increase gas production without harming the environment. The
Chesapeake seen offering biggest gain in
May 4, 2012. Chesapeake Energy Corp., battered by a glut-driven collapse in natural-gas prices and growing investor distrust of its management, still is the cheapest way of buying into the
Price rise seen moderate in
May 2, 2012. A prospective boom in
POWER
Govt mulls tapping other power generating plant in
May 8, 2012. To institute immediate measures in addressing
New hydro power plant to be built in
May 6, 2012. Georgian President Mikheil Saakashvili recently marked the launch of construction work for the Nenskra power station in a mountainous region in
Aboitiz Power plans to spend P170 bn for generation projects
May 6, 2012. Aboitiz Power Corp. plans to spend up to P170 billion in the next five years to rehabilitate old plants as well as establish new facilities across the country. The company said the planned expenditure will likely go to hydroelectric and clean coal projects to take advantage of a shortage in the market. In
Transmission / Distribution / Trade
Singapore Power said to seek $1.2 bn project facility
May 8, 2012. Singapore Power Ltd. hired six banks to help arrange a S$1.5 billion ($1.2 billion) 10-year project finance loan. The proceeds will help fund the construction of two tunnels to carry electricity cables under
AES agrees to sell ‘substantial majority’ of Chinese businesses
May 7, 2012. AES Corp. (AES) has signed two agreements to sell “a substantial majority” of its Chinese businesses for $134 million. The agreements include selling stakes in a coal-fired power plant and a windpower joint venture to Sembcorp Utilities and the previously announced sale of a stake in a development company to its joint venture partner, China Three Gorges New Energy Corp., the company said.
Nigeria needs 135 GW of electricity
May 8, 2012. The Federal Government (FG) said the nation requires about 135,000 MW of electricity to effectively power the economy. The Presidency said to achieve this, the country needs about 15 times of what was being presently generated. Minister of Power, Prof. Bath Nnaji said the country would exploit methods of fuel for power generation, gas, hydro, coal, wind and solar to achieve the target, adding that the current baseline of power generation was 3, 600 MW out of the 5, 700 MW available capacity.
Saudi targets 21 GW of nuclear power by 2032
May 8, 2012.
Jordan expects agreement on shale-oil plant with
May 7, 2012. Jordan expects to sign a final agreement with
RENEWABLE ENERGY / CLIMATE CHANGE TRENDS
National
Suzlon bags ` 3 bn contract for wind power project in
May 8, 2012. Wind turbine manufacturer Suzlon Group said it has bagged a ` 305 crore contract for setting up a 50 MW power project in
India barely taps 2.5 pc of its renewable energy potential
May 7, 2012. India has achieved an installed renewable power capacity of 24,914 MW as of end March 2012, against its potential renewable power generating capacity of 10,76,160 MW – about 2.3 per cent of the potential. The 24,914 MW of renewable power capacity installed so far in India comprises 17,353 MW wind power, 3,395 MW small hydel power, 3,325 MW bio-power and 941 MW solar power, according to information provided by minister of new and renewable energy Dr Farooq Abdullah. He said various studies undertaken in the past have estimated a potential of about 90,000 MW for power generation from wind, small hydel and biomass sources in the country in the medium term (up to 2032). The potential for solar energy has been estimated for most parts of the country at around 30-50 MW per square km of open, shadow-free area covered with solar collectors. Even if we take one per cent of the 32,87,263 square km land mass of the country, it would be enough to generate 986160 MW of solar power.
ReNew Wind Power's 25.2 MW wind farm starts generation
May 7, 2012. Mumbai-headquartered ReNew Wind Power has commissioned its first wind power project of 25.2 megawatts near
Focus should be on renewable energy, says APJ Abdul Kalam
May 6, 2012. Advocating the need for energy security, former president APJ Abdul Kalam said
Chandigarh to be developed as solar city
May 4, 2012. The Chandigarh Administration, the state governments of Punjab and Haryana have agreed to develop
India violating WTO obligations:
May 4, 2012. US solar industry is pushing the government to drag
MNRE may draft guidelines on offshore wind
May 4, 2012. The Ministry of New and Renewable Energy (MNRE) is likely to come out with draft guidelines for offshore wind energy in the next one month. Experts have bet big especially on Tamil Nadu's offshore wind potential. A pilot project off the coast of
Tamil Nadu to set up solar parks to generate 1 GW
May 3, 2012. Tamil Nadu government proposed to set up solar powered parks with the aim of generating 1000 MW in the next five years in the public-private participation mode. Initially ` 1,000 crore will be invested in southern parts of the state over 500 acres to produce 100 MW, Industries minister P Thangamani said. Replying to the grants for his department for 2012-13, the minister said the Tamil Nadu Industries Development Corporation (TIDCO) will set up such solar parks. Thangamani recalled that Chief Minister Jayalalithaa had mentioned in her 'vision 2023' document the intention to produce 11000 MW of solar power in the next 11 years.
ReGen Powertech raises ` 520 mn from PEs for expansion
May 2, 2012. ReGen Powertech, the Chennai-based wind turbine maker has raised ` 52 crore from two large private equity firms, as it looks to upgrade the capacity at its manufacturing plant in
Global
Canada set to miss modest emissions goals
May 8, 2012. Canada is acting too slowly to combat climate change and has little chance of achieving its modest 2020 target for cuts in greenhouse gas emissions. The report by Environment Commissioner Scott Vaughan is awkward for the right-of-center Conservative government, which green activists say is more interested in industrial development than in protecting the environment. The government, which pulled
Italy's solar growth seen slowing sharply in 2012
May 8, 2012. Growth of solar power capacity in Italy, the world's second-biggest market, is expected to slow to 1,500-2,500 MW in 2012 after a 9,300 MW leap in 2011, due to a planned cut in incentives. The Italian government has announced a plan to scale back production incentives to the photovoltaic and other renewable energy to ease the burden on consumers, who pay for the industry support with their power bills.
Korean company to generate 300 MW through solar energy
May 8, 2012. Global R&BD Division of CX Korea has informed after completion of formalities of NEPRA, Ministry of Water and Power etc their company would initiate project of establishment of 10 MW solar energy plant, which would later be extended upto 300 MW power generation through solar energy.
Energy Conversion to fire 300 as Uni-Solar auction fails
May 8, 2012. Energy Conversion Devices Inc., a
Norwegian Agency urges increased spill response in
May 7, 2012. Norway’s Climate and Pollution Agency urged increased spill response capability in the
China to construct more energy-efficient buildings
May 6, 2012. China wants energy-efficient buildings to account for 30 percent of all new construction projects by 2020 to bring its building energy consumption ratio closer to that of developed countries. In order to achieve that goal, the government will step up incentives for green buildings, improve industry standards and promote technological improvements and the development of related industries. The World Bank called on
The global solar industry aims at
May 4, 2012. Japan plans to close its last nuclear reactor this weekend, a move that will take nuclear power out of its energy supply for the first time since 1966. Among those who will celebrate the news will be solar companies as
Germany may fund more solar research amid subsidy cuts
May 4, 2012.
Banned carbon credit supply may fall short
May 4, 2012. Supply of soon-to-be banned emission credits in the European Union’s carbon market may fall short of expectations, boosting this year’s prices relative to 2013. The EU has banned the use of United Nations credits from some hydrofluorocarbon 23-producing chemical factories and adipic-acid manufacturers from its trading system from next May, saying these credits generate excessive profits. Those credits make up more than half of supply in the Clean Development Mechanism, the world’s biggest offsetting market.
Carbon market lobbyist criticizes ‘whopping falsehoods’
May 4, 2012. The carbon market has been damaged by three “whopping falsehoods” that slowed its growth and caused European lawmakers to question their belief in the system, said the retiring head of a carbon market lobby group. The first lie is that climate science is exaggerated, boring and unimportant, Henry Derwent, chief executive of the International Emissions Trading Association said. The second is that nations shouldn’t protect the climate because others aren’t and the third is that markets are not the best solution, he said.
Solar Catamaran ends first sun-powered round-world voyage
May 4, 2012. A PlanetSolar SA catamaran covered with 38,000 solar cells completed the first round-the world voyage fueled only by the sun. The catamaran’s roof is covered with SunPower Corp. panels that extend like wings over its hulls, powering six blocks of lithium-ion batteries. The voyage demonstrates there are fossil fuel-free alternatives other than sails to power ships across the sea as governments try to fight climate change by lowering carbon emissions. Shipping accounts for about 3 percent of all greenhouse gases.
Brazil seeks biofuel exports to
May 4, 2012. Brazilian biodiesel producers are seeking export agreements with Spanish oil companies after the European country moved to cut off imports of the renewable fuel from
Peak oil move over - now solve CO2
May 3, 2012. Trends in global economic growth and rising CO2 emissions rule out optimism that climate targets can be met, even while the world gets to grip with energy security. The continuing financial crisis and record high oil prices in 2008 haven't driven a low-carbon revolution which green lobbyists and agencies including the United Nations urged three years ago. In fact, the opposite seems to be happening. The world may have found a sticking plaster, at least, to peak oil with rising production of offshore crude, onshore tight oil, shale gas and tar sands, but increased output of such fossil fuels conflicts with the goal of limiting climate change.
EU green goals depend on CO2 market-Acciona
May 3, 2012. The European Union could fail to hit its green goals unless it manages to drive carbon prices on its Emissions Trading Scheme (ETS) to around three times current levels,
South Korean parliament approves carbon trading system
May 3, 2012. South Korea approved a cap-and-trade system to cut carbon emissions as President Lee Myung Bak seeks support from factories and power plants in the fastest-growing producer of greenhouse gases among industrialized democracies. The National Assembly passed a bill to establish a cap-and- trade system in the country by 2015 with the backing of both ruling and opposition parties. President Lee Myung Bak is struggling to sell the plan at home after pledging in December 2009 at the United Nations climate summit in
U.S. Clean Energy bill may boost prices after 2025, EIA says
May 3, 2012. A
The views expressed above belong to the author(s). ORF research and analyses now available on Telegram! Click here to access our curated content — blogs, longforms and interviews.